 M Residence 2, Review and status

views
     
aaron1717
post Jan 12 2017, 02:00 PM

Chui Shui in Property Manyak Best!
********
All Stars
10,188 posts

Joined: Apr 2012
QUOTE(nottiworks @ Jan 12 2017, 01:53 PM)
Really... so even no api also can VP. Can we complain or sue it?
*
its all down to black and white... in your SPA, did they mentioned anything such as api air ready by the time u VP? haha....
gks
post Jan 12 2017, 02:17 PM

Look at all my stars!!
*******
Senior Member
3,834 posts

Joined: May 2008
QUOTE(nottiworks @ Jan 12 2017, 01:53 PM)
Really... so even no api also can VP. Can we complain or sue it?
*
Read your SPA carefully. It read utilities ready for connection if not mistaken... Even though most developers already have water/ electricity meter/ fius already connected when VP but MahSing legally/ obligation wise nothing wrong with the way they handover.
Yveatel
post Jan 12 2017, 02:21 PM

Enthusiast
*****
Senior Member
880 posts

Joined: Nov 2013
From: Ceres


QUOTE(nottiworks @ Jan 12 2017, 01:53 PM)
Really... so even no api also can VP. Can we complain or sue it?
*
MS are not wrong. It is written clearly in SPA that VP can be done with the house "READY" for connection. However, professionally and ethically, MS should not even allow this to happen. So much for so called Top10 developers.
BEANCOUNTER
post Jan 12 2017, 04:43 PM

20k VIP Club
*********
All Stars
20,146 posts

Joined: May 2011
as I explained very clearly above, its the TNB that changed their work procedures that caught most developers off guard.

its not only MS has problem give api and air before vp.

go survey every single vped landed projects in klang valley this year and verify how many of those projects managed to vp with air and api...
Yveatel
post Jan 12 2017, 04:45 PM

Enthusiast
*****
Senior Member
880 posts

Joined: Nov 2013
From: Ceres


QUOTE(BEANCOUNTER @ Jan 12 2017, 04:43 PM)
as I explained very clearly above, its the TNB that changed their work procedures that caught most developers off guard.

its not only MS has problem give api and air before vp.

go survey every single vped landed projects in klang valley this year and verify how many of those projects managed to vp with air and api...
*
yup, it is not MS problem. But reputation and public perspective is important, isn't it?
BEANCOUNTER
post Jan 12 2017, 04:49 PM

20k VIP Club
*********
All Stars
20,146 posts

Joined: May 2011
QUOTE(Yveatel @ Jan 12 2017, 04:45 PM)
yup, it is not MS problem. But reputation and public perspective is important, isn't it?
*
even Setia eco glades when they vped their link terraces also no api.

you think their share prices took a nose dive?
Yveatel
post Jan 12 2017, 04:55 PM

Enthusiast
*****
Senior Member
880 posts

Joined: Nov 2013
From: Ceres


QUOTE(BEANCOUNTER @ Jan 12 2017, 04:49 PM)
even Setia eco glades when they vped their link terraces also no api.

you think their share prices took a nose dive?
*
Nope, because they are smart in marketing and branding. Where else, MS public perception - shitty buildup, bad design, chinaman company.

Which house do not have defects?

Case 1: House by MS
Shitty house, got so many defects. PM of MS did not check properly. Bad QC. Stupid architect design to put a pipe there. VP without Api and Air, complain!!

Case 2: House by another super reputable developer
It is common lar. Contractor's fault. Not developer's fault. VP without Api and Air, aiyah, TNB and Syabas fault lar. They need money lar to connect.

See the common replies in MS and other threads??

I am not saying you are wrong and you do not have to be so defensive... all I am saying is human mindset.

blibala
post Jan 12 2017, 06:11 PM

Regular
******
Senior Member
1,920 posts

Joined: Jan 2005
If project teams coordinate well there wont be serious delay in utilities supply. Birch vp for more than two months but still no api. If one month delay still consider acceptable. And now still dont know when can get api.

Developer always use Ready for connection to escape from their obligation.

Go find out the cause of delay. Then u will know the interesting answer.

This post has been edited by blibala: Jan 14 2017, 12:59 AM
BEANCOUNTER
post Jan 12 2017, 06:25 PM

20k VIP Club
*********
All Stars
20,146 posts

Joined: May 2011
QUOTE(Yveatel @ Jan 12 2017, 04:55 PM)
Nope, because they are smart in marketing and branding. Where else, MS public perception - shitty buildup, bad design, chinaman company.

Which house do not have defects?

Case 1: House by MS
Shitty house, got so many defects. PM of MS did not check properly. Bad QC. Stupid architect design to put a pipe there. VP without Api and Air, complain!!

Case 2: House by another super reputable developer
It is common lar. Contractor's fault. Not developer's fault. VP without Api and Air, aiyah, TNB and Syabas fault lar. They need money lar to connect.

See the common replies in MS and other threads??

I am not saying you are wrong and you do not have to be so defensive... all I am saying is human mindset.
*
Its ok de...i dont hold grunge.

At least mr2 is not overpriced (if u get in earlier) and its 'better' than i expected.....

At least they didnt promised heaven and earth w smart marketing and colorful brochure.
Yveatel
post Jan 13 2017, 08:14 AM

Enthusiast
*****
Senior Member
880 posts

Joined: Nov 2013
From: Ceres


QUOTE(blibala @ Jan 12 2017, 06:11 PM)
If project teams coordinate well there wont be serious delay in utilities supply. Birch vp for more than two months but still no api. If one month delay still consider acceptable. And now still dont know when can get api.

Developer always use Ready for connection to escape from their obligation.

Go find out the cause of delay. Then u will know the interesting answer.
*
what's the cause? hmm.gif
blibala
post Jan 13 2017, 08:25 AM

Regular
******
Senior Member
1,920 posts

Joined: Jan 2005
QUOTE(Yveatel @ Jan 13 2017, 08:14 AM)
what's the cause? hmm.gif
*
later i kena mega_shok.gif

But you can sit down and think back. Why alpine delay for so many months? When everyone said TNB caused the delay, then why shud MS kept quiet and willing to pay LAD? There must be somewhere wrong in between. brows.gif





Yveatel
post Jan 13 2017, 09:03 AM

Enthusiast
*****
Senior Member
880 posts

Joined: Nov 2013
From: Ceres


QUOTE(blibala @ Jan 13 2017, 08:25 AM)
later i kena  mega_shok.gif

But you can sit down and think back. Why alpine delay for so many months? When everyone said TNB caused the delay, then why shud MS kept quiet and willing to pay LAD? There must be somewhere wrong in between.  brows.gif
*
innocent.gif
max_cavalera
post Jan 13 2017, 01:11 PM

rebirth
*******
Senior Member
5,614 posts

Joined: Jun 2006
From: Cyberjaya, Shah Alam, Ipoh



QUOTE(blibala @ Jan 13 2017, 09:25 AM)
later i kena  mega_shok.gif

But you can sit down and think back. Why alpine delay for so many months? When everyone said TNB caused the delay, then why shud MS kept quiet and willing to pay LAD? There must be somewhere wrong in between.  brows.gif
*
Means who wrong?

MS clever not include tnb in VP so if tnb delay2 they dont kena LAD due to other party not efficient?
blibala
post Jan 13 2017, 07:15 PM

Regular
******
Senior Member
1,920 posts

Joined: Jan 2005
QUOTE(max_cavalera @ Jan 13 2017, 01:11 PM)
Means who wrong?

MS clever not include tnb in VP so if tnb delay2 they dont kena LAD due to other party not efficient?
*
Dont think much. Enjoy your new home

zacharytong
post Jan 14 2017, 09:05 AM

New Member
*
Junior Member
8 posts

Joined: Dec 2016


QUOTE(blackagez @ Jan 11 2017, 03:12 PM)
Any Caspia owner here ?
I heard we will get key somewhere around June 2017 instead of March 2017 ?
any update ?
*
I heard the same news from my agent too~ if according to latest letter sent by them, my next step is wait them complete electric, water and pass key to me to get the next 12.5% money from bank.
And do you all have any Caspia whatsapp group to share information?
zacharytong
post Jan 14 2017, 09:09 AM

New Member
*
Junior Member
8 posts

Joined: Dec 2016


QUOTE(Yveatel @ Jan 12 2017, 09:16 AM)
shocking.gif  u bila hear that? I did not hear anything also... I still think it is March. Mine C1. They need pay me LAD leh like that.  brows.gif
*
i heard from my agent last month, but if according to latest letter sent by them, my next step is wait them complete electric, water and pass key to me to get the next 12.5% money from bank.
And do you all have any Caspia whatsapp group to share information? And what is LAD?
Yveatel
post Jan 14 2017, 12:03 PM

Enthusiast
*****
Senior Member
880 posts

Joined: Nov 2013
From: Ceres


QUOTE(zacharytong @ Jan 14 2017, 09:09 AM)
i heard from my agent last month, but if according to latest letter sent by them, my next step is wait them complete electric, water and pass key to me to get the next 12.5% money from bank.
And do you all have any Caspia whatsapp group to share information? And what is LAD?
*
LAD - liquidated ascertained damages (Damages paid due to developer's failure to complete the house on time written (individual - 2 years, strata - 3 years)

No, I am not aware of any Whatsapp group for Caspia alone.
hustlakings2417
post Jan 14 2017, 09:47 PM

Getting Started
**
Junior Member
54 posts

Joined: Jan 2015
How is the key handover and defect checking going on guys ?
zacharytong
post Jan 15 2017, 03:11 PM

New Member
*
Junior Member
8 posts

Joined: Dec 2016


QUOTE(Yveatel @ Jan 14 2017, 12:03 PM)
LAD - liquidated ascertained damages (Damages paid due to developer's failure to complete the house on time written (individual - 2 years, strata - 3 years)

No, I am not aware of any Whatsapp group for Caspia alone.
*
not only caspia, if have any m residence 2 whatsapp group also can invite me~
propertybbb
post Jan 15 2017, 03:14 PM

Look at all my stars!!
*******
Senior Member
2,663 posts

Joined: Feb 2013
How is the lake there? Curious to know how Mahsing upgrade works on the lake there. Surely will benefit MR2 residemce and ppls nearby.