 Amara Service Residence V2, by Jaya Megah

views
     
kienfu
post May 5 2013, 05:52 PM

Getting Started
**
Junior Member
78 posts

Joined: Aug 2008


the progress still the same, WTF!!!!!!!!!!!!!

i personally feel that this project will turn to abandance project.!

sad!!
aru843
post May 5 2013, 09:09 PM

New Member
*
Junior Member
43 posts

Joined: May 2011
QUOTE(kienfu @ May 5 2013, 05:52 PM)
the progress still the same, WTF!!!!!!!!!!!!!

i personally feel that this project will turn to abandance project.!

sad!!
*
Die la like this..This developer is very suck

adrian0229
post May 13 2013, 11:57 AM

Look at all my stars!!
*******
Senior Member
3,913 posts

Joined: Nov 2004
still stuck at lvl 7?
boyboy3663
post May 15 2013, 01:47 PM

Getting Started
**
Junior Member
114 posts

Joined: May 2011
how's the recent progress? hopefully not turn to abandance i buy for ownstay leh...
find my way
post May 16 2013, 11:21 AM

New Member
*
Junior Member
11 posts

Joined: May 2007
haiz cry.gif really worry about it ler.... cry.gif

This post has been edited by find my way: May 16 2013, 11:22 AM
sWeety1216
post May 17 2013, 11:40 AM

New Member
*
Junior Member
24 posts

Joined: May 2011
cham lo like me, me too buying for ownstay leh....



QUOTE(boyboy3663 @ May 14 2013, 09:47 PM)
how's the recent progress? hopefully not turn to abandance i buy for ownstay leh...
*
steven.sl86
post May 17 2013, 02:48 PM

New Member
*
Junior Member
33 posts

Joined: May 2011


QUOTE(boyboy3663 @ May 15 2013, 01:47 PM)
how's the recent progress? hopefully not turn to abandance i buy for ownstay leh...
*
dont worry too much..
they got another project is running also..


if no project then only scare... 3 storey de.. i forget what name already...
kyo2020
post May 17 2013, 08:23 PM

Getting Started
**
Junior Member
159 posts

Joined: Jul 2012
level 8 is the first residential floor. the first residential floor usually take much longer time to build. once it up, then progress will be fast.
property hunter
post May 18 2013, 01:13 PM

Getting Started
**
Junior Member
74 posts

Joined: May 2011
any photo to see?
kochin
post May 18 2013, 01:16 PM

I just hope I do!
********
All Stars
10,314 posts

Joined: Dec 2009
From: Malaysia


Guys, if you are so worried, go do a stakeout at the project site today. If really no construction in progress,then rally a group to storm the developer and kim realty office lor.
property hunter
post May 18 2013, 01:46 PM

Getting Started
**
Junior Member
74 posts

Joined: May 2011
agreed
wbyee78
post May 18 2013, 06:15 PM

Getting Started
**
Junior Member
269 posts

Joined: Jan 2013
Contractor is working on the transfer floor which usually takes 2 months to complete. After that, you can expect easily 3 floors per month.

property hunter
post May 26 2013, 12:55 PM

Getting Started
**
Junior Member
74 posts

Joined: May 2011
what is the progress now?
kochin
post May 27 2013, 03:29 PM

I just hope I do!
********
All Stars
10,314 posts

Joined: Dec 2009
From: Malaysia


nobody visited the site during the 3 days break last weekend?
i wanted to drop by after visiting veo.
but unfortunately i didn't even drop by veo.
sigh!
would appreciate updates if any from anybody.

how's raintree condo doing btw?
from outside, looks classy and nice and tall.
shyhhua
post May 27 2013, 04:57 PM

Getting Started
**
Junior Member
265 posts

Joined: Apr 2008


Selling price for Semarak & Penaga Condo size 926sf now going around RM300k while 1,098sf around RM330k only ler... wonder how far Amara can go after VP? hmm.gif
boyboy3663
post May 27 2013, 05:26 PM

Getting Started
**
Junior Member
114 posts

Joined: May 2011
i went there yesterday and the middle block (B and C) look like going to finish 8th floor soon .... while block A and D slightly higher than middle block
didnt take photo coz went at night time.

btw, anyone receive developer disbursement letter this month? i just get mine and disbursement of 5%

that means the construction is in progress rclxms.gif
kochin
post May 27 2013, 05:29 PM

I just hope I do!
********
All Stars
10,314 posts

Joined: Dec 2009
From: Malaysia


no worries.
SPA in aug 2011.
they still have plenty of time to deliver.
shyhhua
post May 27 2013, 05:40 PM

Getting Started
**
Junior Member
265 posts

Joined: Apr 2008


QUOTE(boyboy3663 @ May 27 2013, 05:26 PM)
i went there yesterday and the middle block (B and C) look like going to finish 8th floor soon .... while block A and D slightly higher than middle block
didnt take photo coz went at night time.

btw, anyone receive developer disbursement letter this month? i just get mine and disbursement of 5%

that means the construction is in progress  rclxms.gif
*
Ya, i got the 2nd disbursement letter for the 5% too
sWeety1216
post May 30 2013, 06:04 AM

New Member
*
Junior Member
24 posts

Joined: May 2011

rclxms.gif Yea, I got it too, on Monday I think.



QUOTE(shyhhua @ May 27 2013, 01:40 AM)
Ya, i got the 2nd disbursement letter for the 5% too
*
ape
post May 30 2013, 04:43 PM

Enthusiast
*****
Senior Member
849 posts

Joined: Apr 2006
dun worry lah, this developer just bought a land in damansara damai at record breaking price tag.

http://www.theedgemalaysia.com/in-the-fina...-for-rm84m.html