QUOTE(shyhhua @ May 27 2013, 05:40 PM)
second disbursement is 5%? it should be 10%. they are not building according to schedule?Amara Service Residence V2, by Jaya Megah
Amara Service Residence V2, by Jaya Megah
|
|
May 31 2013, 12:37 PM
|
![]() ![]()
Junior Member
197 posts Joined: Apr 2012 |
|
|
|
|
|
|
May 31 2013, 12:40 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]()
All Stars
10,722 posts Joined: Nov 2011 |
i saw got workers work at site wo....
no stop work la. |
|
|
Jun 7 2013, 05:36 PM
|
![]() ![]()
Junior Member
265 posts Joined: Apr 2008 |
|
|
|
Jun 7 2013, 06:08 PM
|
![]() ![]()
Junior Member
269 posts Joined: Jan 2013 |
It is a normal practice for developer. They will claim whatever the current site conditions allow.
|
|
|
Jun 7 2013, 06:13 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]()
All Stars
10,314 posts Joined: Dec 2009 From: Malaysia |
It is a bit odd a developer or contractor would conatruct the drain first as damage or build up of silts in the drains could occur.
If developer is in tight financial sitiation this could be a good move to help ease their cashflow as this 5% is claimable for entire development and not per unit basis like structures. Hhhhmmmm..... |
|
|
Jun 9 2013, 08:37 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,008 posts Joined: Nov 2007 From: Gombak,serdang |
QUOTE(kochin @ Jun 7 2013, 06:13 PM) It is a bit odd a developer or contractor would conatruct the drain first as damage or build up of silts in the drains could occur. they try to claim as much as possible for retail unit i believe. that why if u notice they already start architect works for ground. If developer is in tight financial sitiation this could be a good move to help ease their cashflow as this 5% is claimable for entire development and not per unit basis like structures. Hhhhmmmm..... |
|
|
|
|
|
Jun 9 2013, 05:35 PM
|
![]() ![]()
Junior Member
74 posts Joined: May 2011 |
any photos lately?
|
|
|
Jun 15 2013, 10:35 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,589 posts Joined: Mar 2005 From: Bolehland |
Long time didn't go to site. Progress already until 9th floor at Block A/D.
View from Block A ![]() Block A ![]() View from Block D ![]() Block D ![]() Is it normal they use sand brick at the exterior layer of the building? Normally i saw new development they were using clay brick at the exterior wall and sand bricks at interior |
|
|
Jun 15 2013, 11:31 PM
|
![]() ![]()
Junior Member
281 posts Joined: May 2011 |
Sorry noob question.
Why block B n C room height looks double volume high compare to block A n D? |
|
|
Jun 15 2013, 11:50 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,589 posts Joined: Mar 2005 From: Bolehland |
|
|
|
Jun 16 2013, 12:45 AM
|
![]() ![]()
Junior Member
281 posts Joined: May 2011 |
|
|
|
Jun 16 2013, 12:47 AM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,589 posts Joined: Mar 2005 From: Bolehland |
QUOTE(WLP3234 @ Jun 16 2013, 12:45 AM) But from the site photo attached in your previous post looks like double high volume,any taiko can enlight us? Thx thx... those are the general functional room if i not mistaken.i remembered there is one big room for function like meeting at block C, another i forgot what in Block B |
|
|
Jun 16 2013, 12:04 PM
|
![]() ![]() ![]()
Junior Member
391 posts Joined: Apr 2008 From: Kuala Lumpur |
Quick Question;
have all the duplex units been sold out? |
|
|
|
|
|
Jun 16 2013, 09:22 PM
|
![]() ![]()
Junior Member
74 posts Joined: May 2011 |
QUOTE(harrychoo @ Jun 15 2013, 10:35 PM) Long time didn't go to site. Progress already until 9th floor at Block A/D. cant view the photos you uploaded...cant open. i want to see...helps plsView from Block A ![]() Block A ![]() View from Block D ![]() Block D ![]() Is it normal they use sand brick at the exterior layer of the building? Normally i saw new development they were using clay brick at the exterior wall and sand bricks at interior |
|
|
Jun 17 2013, 08:15 AM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]()
All Stars
10,314 posts Joined: Dec 2009 From: Malaysia |
QUOTE(WLP3234 @ Jun 15 2013, 11:31 PM) what you see in the pics is comparing's A&D's units against car park floors.for the top floor, you are actually comparing A&D's units against the recreational deck. block B&C's unit is located behind thus you should be able to sight it from this angle shot only when it reaches substantial height. |
|
|
Jun 17 2013, 09:25 PM
|
![]() ![]()
Junior Member
74 posts Joined: May 2011 |
QUOTE(kochin @ Jun 17 2013, 08:15 AM) what you see in the pics is comparing's A&D's units against car park floors. design nice?for the top floor, you are actually comparing A&D's units against the recreational deck. block B&C's unit is located behind thus you should be able to sight it from this angle shot only when it reaches substantial height. |
|
|
Jun 18 2013, 09:37 AM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]()
All Stars
10,314 posts Joined: Dec 2009 From: Malaysia |
http://2.bp.blogspot.com/--cbAw1ECX9o/ThWM...omIMG_72141.jpg
ok lah... but i think i prefer this design: http://images02.olx.com.my/ui/18/48/91/135...layang-Baru.jpg taller hence more commanding view. |
|
|
Jun 18 2013, 06:05 PM
|
![]() ![]()
Junior Member
197 posts Joined: Apr 2012 |
received letter to ask for another 5%.
sewerage works completed.. so fast? it is totally not follow the schedule. they really need $$ urgently. |
|
|
Jun 18 2013, 06:32 PM
|
![]() ![]()
Junior Member
197 posts Joined: Apr 2012 |
QUOTE(swisspalm @ Jun 18 2013, 06:05 PM) received letter to ask for another 5%. drains serving the said building - donesewerage works completed.. so fast? it is totally not follow the schedule. they really need $$ urgently. sewerage works serving the said building -done may i know how we can verify it? from the site, didn't look likely. |
|
|
Jun 18 2013, 10:06 PM
|
![]() ![]() ![]() ![]() ![]()
Senior Member
992 posts Joined: Jun 2012 |
|