Just went to site visit yesterday, here's some comment on the visit:-

1) Guard house for phase 1 is not built yet, but after talking to the salesperson, there will be a guard house shared by phase 1 n 4, while there will be another guard house for semi-d

2) I got into my own unit (somehow) and realize part of the master room toilet is not tiled yet. But other than that, the house are finished with quite good workmanship.

3) I saw some of the TNB exchange box are exposing some huge cables, I think they are not connected yet, and i saw a few workers are connecting the cables to the lamp post pillar.

4) Road are paved nicely and everything seems to be ready.

I think we still have to wait for a month or 2 before it can VP.
spreeeee
post May 26 2014, 05:49 PM

♠ . ♥ . ♣ . ♦
*******
Senior Member
3,812 posts

Joined: Apr 2009
From: West Malaysia

QUOTE(bennycfw @ May 26 2014, 01:42 PM)
Just went to site visit yesterday, here's some comment on the visit:-

1) Guard house for phase 1 is not built yet, but after talking to the salesperson, there will be a guard house shared by phase 1 n 4, while there will be another guard house for semi-d

2) I got into my own unit (somehow) and realize part of the master room toilet is not tiled yet. But other than that, the house are finished with quite good workmanship.

3) I saw some of the TNB exchange box are exposing some huge cables, I think they are not connected yet, and i saw a few workers are connecting the cables to the lamp post pillar.

4) Road are paved nicely and everything seems to be ready.

I think we still have to wait for a month or 2 before it can VP.
*
your unit is MR1?
bennycfw
post May 26 2014, 11:41 PM

Getting Started
**
Junior Member
73 posts

Joined: Nov 2013


QUOTE(spreeeee @ May 26 2014, 05:49 PM)
your unit is MR1?
*
Yes MR1, phase1
mankibon
post May 27 2014, 10:47 AM

Getting Started
**
Junior Member
57 posts

Joined: Jul 2009


View from my unit.. rclxms.gif


Attached thumbnail(s)
Attached Image
jason_chee
post May 27 2014, 05:53 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


2 months more? it's surpassed the SnP date and how do we claim the compensation? Anyone do that?
bennycfw
post May 27 2014, 05:58 PM

Getting Started
**
Junior Member
73 posts

Joined: Nov 2013


QUOTE(jason_chee @ May 27 2014, 05:53 PM)
2 months more? it's surpassed the SnP date and how do we claim the compensation? Anyone do that?
*
Yes, it is indeed delay in handover, as the salesperson claimed that MS wanted to deliver the house in perfect condition.
So, instead of rushing for handover, they rather pay late interest to buyer and deliver good product.

Already confirmed with lawyer on the compensation, that MS will issue a cheque amounted to the individual late interest during VP.
bennycfw
post May 27 2014, 05:59 PM

Getting Started
**
Junior Member
73 posts

Joined: Nov 2013


By the way, just curious if I can remove the tree and the grass patch in front of my gate?
jason_chee
post May 27 2014, 06:03 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(bennycfw @ May 27 2014, 05:59 PM)
By the way, just curious if I can remove the tree and the grass patch in front of my gate?
*
i dun think so. last time i check, i need to re-plant a new tree if the town council discover that.
lekkor
post May 27 2014, 06:17 PM

Getting Started
**
Junior Member
54 posts

Joined: Dec 2011
deliver the house in perfect condition? i doubt so. look at the road kerb, very obvious is dodgy workmanship, patches everywhere.

if what they claimed is true, why the power cables at the feeder pillar are pointing outward? why the water meter stand is without meter? obviously the substation isn't energised yet. don't be so stupid la... mah sing.

after all, make sure you guys claim lad from mah sing. hurray.....
koigh
post May 28 2014, 09:44 AM

Getting Started
**
Junior Member
205 posts

Joined: Apr 2012
QUOTE(lekkor @ May 27 2014, 06:17 PM)
deliver the house in perfect condition? i doubt so. look at the road kerb, very obvious is dodgy workmanship, patches everywhere.

if what they claimed is true, why the power cables at the feeder pillar are pointing outward? why the water meter stand is without meter? obviously the substation isn't energised yet. don't be so stupid la... mah sing.

after all, make sure you guys claim lad from mah sing. hurray.....
*
If not mistaken, water meter and electricity can be connected after received the CF......
lekkor
post May 28 2014, 04:39 PM

Getting Started
**
Junior Member
54 posts

Joined: Dec 2011
No la. Each every house must has water, electricity, sewerage facilities in order to obtain CF. With CF then only ready for occupying.


jason_chee
post May 28 2014, 04:41 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


before CF, we need to pay Deposit to open account with TNB and SYABAS. this step not yet executed. i think might delay for 1 or 2 months. nvm. i wait patiently.
bennycfw
post May 28 2014, 06:15 PM

Getting Started
**
Junior Member
73 posts

Joined: Nov 2013


QUOTE(jason_chee @ May 28 2014, 04:41 PM)
before CF, we need to pay Deposit to open account with TNB and SYABAS. this step not yet executed. i think might delay for 1 or 2 months. nvm. i wait patiently.
*
MR1 - Phase 1 and 2 already done this step last year 2013. now is pending completion on whatever which is not yet complete.
Hello_kitty 89
post May 28 2014, 09:28 PM

On my way
****
Senior Member
551 posts

Joined: Feb 2012
QUOTE(xenite @ May 26 2014, 11:10 AM)
after reading the snp, indeed you cannot do external renovation for mr1
*
Which clause? brows.gif
koigh
post May 29 2014, 08:42 AM

Getting Started
**
Junior Member
205 posts

Joined: Apr 2012
QUOTE(bennycfw @ May 28 2014, 06:15 PM)
MR1 - Phase 1 and 2 already done this step last year 2013. now is pending completion on whatever which is not yet complete.
*
Yes, I also have paid the deposit......
jason_chee
post May 30 2014, 12:13 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(bennycfw @ May 28 2014, 06:15 PM)
MR1 - Phase 1 and 2 already done this step last year 2013. now is pending completion on whatever which is not yet complete.
*
ooh... i can't remember that. my mistake on that.
tboxmy
post Jun 2 2014, 10:37 AM

Casual
***
Junior Member
478 posts

Joined: Oct 2006


QUOTE(bennycfw @ May 27 2014, 05:58 PM)
Yes, it is indeed delay in handover, as the salesperson claimed that MS wanted to deliver the house in perfect condition.
So, instead of rushing for handover, they rather pay late interest to buyer and deliver good product.

Already confirmed with lawyer on the compensation, that MS will issue a cheque amounted to the individual late interest during VP.
*
"IN PERFECT CONDITION"? Who told you that?

Thank you, its worth a Good laugh for the day.
bennycfw
post Jun 2 2014, 02:24 PM

Getting Started
**
Junior Member
73 posts

Joined: Nov 2013


QUOTE(tboxmy @ Jun 2 2014, 10:37 AM)
"IN PERFECT CONDITION"? Who told you that?

Thank you, its worth a Good laugh for the day.
*
well don't laugh, salesperson told me that. anyway, isn't that better hear that rather than some negative news?
helmyz85
post Jun 2 2014, 08:22 PM

New Member
*
Junior Member
26 posts

Joined: Sep 2012


Oh you guys are so lucky.. can get a lot compensation.. can pay for kitchen cabinet or plaster ceiling..
tboxmy
post Jun 3 2014, 05:41 PM

Casual
***
Junior Member
478 posts

Joined: Oct 2006


QUOTE(bennycfw @ Jun 2 2014, 02:24 PM)
well don't laugh, salesperson told me that. anyway, isn't that better hear that rather than some negative news?
*
Yes, but some honesty is appreciated from them if possible.

198 Pages « < 162 163 164 165 166 > » Top
 

Change to:
| Lo-Fi Version
0.0355sec    0.70    6 queries    GZIP Disabled
Time is now: 3rd December 2025 - 04:14 PM