 1120 Park Avenue - PJ South, any comments?

views
     
lamode
post May 22 2010, 09:56 PM

anything could happen!
*******
Senior Member
3,904 posts

Joined: Jul 2007
QUOTE(kyrieAZ @ May 22 2010, 11:03 AM)
salam semua... mcm mana dgn perkembangan pembinaan? dh start piling ke?
selalunya mana2 projek pun preliminary works mesti lambat...sy x risau sgt pada mula ni sbb sy akan risau sekiranya xda apa2 berlaku dalam tempoh setahun lagi...jd pada yg risau lambat start tu...jgn risau sgt ya...
*
english please? notworthy.gif
kyrieAZ
post May 22 2010, 11:57 PM

New Member
*
Junior Member
10 posts

Joined: Feb 2010
QUOTE(lamode @ May 22 2010, 09:56 PM)
english please?  notworthy.gif
*
i'm sorry mr lamode....my english is very bad...but let me explain a little bit what i'm saying up there... so i read this forum but don't drop any comment...i read that many ppl in here get a bit concern about the project... by the way my opinion is that any project i think the earthwork is very damn slow... trust me if the earthwork is done then the building and other works follows must be quick enough to finish....so don't worry to all buyers (i'm the one who buy too)... this project will finish on time.!!!

by the way...i'm a malay guy who buy this house...got bumi price...quite worthy...

see ya... whistling.gif
lamode
post May 23 2010, 12:02 PM

anything could happen!
*******
Senior Member
3,904 posts

Joined: Jul 2007
QUOTE(kyrieAZ @ May 22 2010, 11:57 PM)
i'm sorry mr lamode....my english is very bad...but let me explain a little bit what i'm saying up there... so i read this forum but don't drop any comment...i read that many ppl in here get a bit concern about the project... by the way my opinion is that any project i think the earthwork is very damn slow... trust me if the earthwork is done then the building and other works follows must be quick enough to finish....so don't worry to all buyers (i'm the one who buy too)... this project will finish on time.!!!

by the way...i'm a malay guy who buy this house...got bumi price...quite worthy...

see ya... whistling.gif
*
no offense, i am also one of the buyer, but i see the otherwise, this project will be delay.
if the very first day they planned to do the piling work on late may / June, then fine, i would say the chances for completed on time is high, but this is not the case, first they said would start piling on march, then keep on dragging and til now still no reach piling stage yet, all we have is very little earth work at snail construction speed.

what i trying to say is they have no planning / bad planning, for this reason, i personally expected delay on VP.
WEE2000
post May 23 2010, 10:56 PM

Getting Started
**
Junior Member
219 posts

Joined: Aug 2005


QUOTE(lamode @ May 23 2010, 12:02 PM)
no offense, i am also one of the buyer, but i see the otherwise, this project will be delay.
if the very first day they planned to do the piling work on late may / June, then fine, i would say the chances for completed on time is high, but this is not the case, first they said would start piling on march, then keep on dragging and til now still no reach piling stage yet, all we have is very little earth work at snail construction speed.

what i trying to say is they have no planning / bad planning, for this reason, i personally expected delay on VP.
*
bro, u left ur receipt with me. ask me get for u, then neve collect it, haih...
preliew
post May 24 2010, 10:41 AM

Getting Started
**
Junior Member
145 posts

Joined: Mar 2008
sure will delay, 5 block within same time....quite impossible leh...but delay better than they juz gulung the money then runaway la...
ntick
post May 24 2010, 02:28 PM

Casual
***
Junior Member
348 posts

Joined: Jan 2003
Dear all,

since we are in the same boat....we can form a resident community...in fb then put some pressure to the developer.....
already 5 month ...but seems not start piling.....sure will delay 1.....

we should evry month check the progress........btw 1 am 1st phrase buyer...on december.....

Bank already start pay money to developer ??as what i know that if piling is not start..bank will not release the money to developer..is it true??

This post has been edited by ntick: May 24 2010, 02:30 PM
cheraspeople
post May 24 2010, 02:40 PM

Enthusiast
*****
Senior Member
756 posts

Joined: Dec 2009
QUOTE(ntick @ May 24 2010, 02:28 PM)
Dear all,

since we are in the same boat....we can form a resident community...in fb then put some pressure to the developer.....
already 5 month ...but seems not start piling.....sure will delay 1.....

we should evry month check the progress........btw 1 am 1st phrase buyer...on december.....

Bank already start pay money to developer ??as what i know that if piling is not start..bank will not release the money to developer..is it true??
*
i dont think bank has released the 1st payment to developer yet. If they have done so we will be informed.
WEE2000
post May 24 2010, 04:02 PM

Getting Started
**
Junior Member
219 posts

Joined: Aug 2005


if a community if formed, pls let me know wat i can help/do. i'm also one of the buyer.
20yrsinsrisentosa
post May 24 2010, 05:26 PM

Getting Started
**
Junior Member
221 posts

Joined: Dec 2009
QUOTE(cheraspeople @ May 24 2010, 02:40 PM)
i dont think bank has released the 1st payment to developer yet. If they have done so we will be informed.
*
1st phase buyer here like ntick too. last sat 22nd may 2010 went to post office to collect a letter sent by lawyer. the letter about confirmation of drawdown to developer. i wonder to should i return the letter to lawyer to indicate my confirmation now...
sam59
post May 24 2010, 07:22 PM

Casual
***
Junior Member
379 posts

Joined: Mar 2010
agree that we set up a community in facebook..


Added on May 24, 2010, 7:47 pmthe 1st drawdown, is it normally upon commencement of piling or after completion of piling? can somebody check the S&P? if it is after completion of piling, then this is a fraud!

This post has been edited by sam59: May 24 2010, 07:47 PM
20yrsinsrisentosa
post May 24 2010, 09:25 PM

Getting Started
**
Junior Member
221 posts

Joined: Dec 2009
QUOTE(sam59 @ May 24 2010, 07:22 PM)
agree that we set up a community in facebook..
how about the following?
http://www.facebook.com/album.php?profile=...87641111&ref=ts
http://www.facebook.com/#!/profile.php...09951126&ref=ts

ch_leong
post May 25 2010, 11:48 AM

Casual
***
Junior Member
439 posts

Joined: Jan 2003


It should be after piling is completed then release $

Instalments Payable % Amount
1. Immediately upon the signing of 10% RM
this Agreement.
2 2
2. Within twenty one (21)
working days after receipt by the
Purchaser of the Vendor's written notice
of the completion of:-
(a) the work below ground level 10% RM
including piling and foundation
of the said Building comprising
the said Parcel
(b) the reinforced concrete 15% RM
framework and floor slab of
the said Parcel
© the walls of the said Parcel 10% RM
with door and window frames
placed in position
(d) the roofing/ceiling, electrical 10% RM
wiring, plumbing (without
fittings), gas piping (if any)
and internal telephone trunking
and cabling to the said
Parcel
(e) the internal and external 10 RM
plastering of the said Parcel
(f) the sewerage works serving the 5 RM
said Building
(g) the drains serving the said 5 RM
Building
(h) the roads serving the said 5 RM
Building
3. On the date the Purchaser takes 12.5 RM
takes possession of the said Parcel with
water and electricity supply ready for
connection to the said Parcel
4. Within twenty-one (21) working 2.5 RM
days after receipt by the Purchaser
of the written confirmation of the
Vendor’s submission to and acceptance
by the Appropriate Authority
of the application for subdivision
2 3
of the said Building
5. On the date the Purchaser takes vacant 5 RM
possession of the said Parcel as in item 3 and to
be held by the Vendor’s solicitor
as stakeholder for payment to the
Vendor as follows:-
(a) two point five per centum (2.5%) at the RM
expiry of six (6) months after
the date the Purchaser takes vacant
possession of the said Parcel
(b) two point five per centum (2.5%) at the RM
expiry of eighteen (18) months
after the date the Purchaser takes vacant
possession of the said Parcel
--------------
TOTAL 100 RM
========

This post has been edited by ch_leong: May 25 2010, 11:48 AM
sam59
post May 25 2010, 11:55 AM

Casual
***
Junior Member
379 posts

Joined: Mar 2010
called the office just now..they said 1st drawdown for BOTH phases will only be in August.
how can somebody said already received notice of 1st drawdown?
anybody received this notice too???
ch_leong
post May 25 2010, 01:19 PM

Casual
***
Junior Member
439 posts

Joined: Jan 2003


I didn't receive any notice. For 1st disbursement, piling must be done and certified by architect. This is what I know from my previous experience.
sam59
post May 25 2010, 02:16 PM

Casual
***
Junior Member
379 posts

Joined: Mar 2010
me too..i didn't receive anything yet. any 1st phase buyer received this notice?
graneon
post May 25 2010, 11:18 PM

Getting Started
**
Junior Member
90 posts

Joined: Oct 2008
tak habis habis lagi pasal delay. kalau pihak pemaju nak delay apa kita boleh buat...tunjuk perasaan, hantar memorandum, report polis??? jangan lupa kita dah sign SPA...SPA kata 3 tahun siap jadi 3 tahun lah tu. Kalau risau sangat sampai tak boleh tidur cuma ada satu option...cancel saja SPA, hangus 10%. pada siapa yang tak mau cancel termasuk saya...tunggu aje la.

This post has been edited by graneon: May 25 2010, 11:21 PM
ch_leong
post May 26 2010, 06:09 PM

Casual
***
Junior Member
439 posts

Joined: Jan 2003


Hello graneon,

cool down man. Many of here are first timer, pastilah mereka ini risaukan. Itu hard earned money mereka. Bagi buyer yang ade experience, mestilah lebih tenang.

I dah kata kepada mereka, VP early nampaknya tak jadilar, tapi i rasa siap dalam 3 tahun ini pasti jadi. I dah nampak banyak earth work kat site. Furthermore Peter's group punya projek taklah terbengkelai, cuma kualitinya mungkin kurang sikit.


itulah pendapat 2 sen saya.

QUOTE(graneon @ May 25 2010, 11:18 PM)
tak habis habis lagi pasal delay. kalau pihak pemaju nak delay apa kita boleh buat...tunjuk perasaan, hantar memorandum, report polis??? jangan lupa kita dah sign SPA...SPA kata 3 tahun siap jadi 3 tahun lah tu. Kalau risau sangat sampai tak boleh tidur cuma ada satu option...cancel saja SPA, hangus 10%. pada siapa yang tak mau cancel termasuk saya...tunggu aje la.


*
This post has been edited by ch_leong: May 26 2010, 06:10 PM
kyrieAZ
post May 26 2010, 06:56 PM

New Member
*
Junior Member
10 posts

Joined: Feb 2010
QUOTE(ch_leong @ May 26 2010, 06:09 PM)
Hello graneon,

cool down man. Many of here are first timer, pastilah mereka ini risaukan. Itu hard earned money mereka. Bagi buyer yang ade experience, mestilah  lebih tenang.

I dah kata kepada mereka, VP early nampaknya tak jadilar, tapi i rasa siap dalam 3 tahun ini pasti jadi. I dah nampak banyak earth work kat site. Furthermore Peter's group punya projek taklah terbengkelai, cuma kualitinya mungkin kurang sikit.
itulah pendapat 2 sen saya.
*
i'm agree wth that.... i'm a first time buyer also but i think its ok too me...
patricktoh
post May 27 2010, 09:06 AM

Casual
***
Junior Member
490 posts

Joined: Jan 2006
From: Kuala Lumpur


Not to pour cold water. Trust me, delay is the initial sign of things go off track. Buyers must keep pressing the developer like no tomorrow.

Developer can promise sky & earth but if they wind down the business, buyers get nothing. I have fa riend who got stuck in this kind project for 10 years. The project completed 85% then stopped. He was paying like RM400 per month of bank interest for past 6-7 years. At the end he got back the $ paid for but the hussles & frustrations are uncountable.

This post has been edited by patricktoh: May 27 2010, 09:07 AM
graneon
post May 27 2010, 12:24 PM

Getting Started
**
Junior Member
90 posts

Joined: Oct 2008
QUOTE(patricktoh @ May 27 2010, 09:06 AM)
Not to pour cold water. Trust me, delay is the initial sign of things go off track. Buyers must keep pressing the developer like no tomorrow.

Developer can promise sky & earth but if they wind down the business, buyers get nothing. I have fa riend who got stuck in this kind project for 10 years. The project completed 85% then stopped. He was paying like RM400 per month of bank interest for past 6-7 years. At the end he got back the $ paid for but the hussles & frustrations are uncountable.
*
Trust me bro, developer will not listen to you no matter how you pressure them. I'll be more worried if the developer start the construction early but stopped work at 85%. Project that started early may have greater chance of being abandon. thats because more work done means more billings, thus more profits. When a project progress further, the developer will probably utilized all their credit facilities. Creditors aging may also be in their max. Non payment to contractors will eventually leads to stop work. There are also many other factors to take into consideration in which i could go on. To cut the story short, the success of a project really depends on it's management and the ability to plan and effectively utilized its cashflow. So if the management decide that it's still not the right time to start the construction, it could be for the benefit of the project. the developer is probably waiting for majority of purchasers' financier facilities to be ready so that any progressive billings can be disbursed effectively.

On the bright side, if the developer did not start any work you will probably lose only your 10% as loan has not been disbursed. I know we will still be at the losing end but thats the concept of Sell and Built. You need to be aware of the risk before buying. If you dont want to take the risk then buy a completed project instead.

This post has been edited by graneon: May 27 2010, 08:49 PM

133 Pages « < 85 86 87 88 89 > » Top
Topic ClosedOptions
 

Change to:
| Lo-Fi Version
0.0310sec    0.60    6 queries    GZIP Disabled
Time is now: 15th December 2025 - 12:36 PM