Taipan Group of Companies - Residency@Park51, Have you heard of this developer?
|
naventhran
|
Jul 25 2012, 12:44 AM
|
New Member
|
QUOTE(nadzimruddin @ Jul 24 2012, 12:14 PM) that is the normal procedure between TAIPAN & contractor. the contractor only accept the defect complaint within 2weeks time FROM the date stated on the letter from TAIPAN. if not, u have to fixed/repair the damages by urself. Today i have spoken to someone from FMB, will provide me details on how to go about for the maintenance fees that we are incurring for a property that we have not occupied yet. I was told that we can do something about it. Still vague about it will know more in a day or two
|
|
|
|
|
|
anokcow
|
Jul 25 2012, 09:13 AM
|
Getting Started

|
QUOTE(naventhran @ Jul 25 2012, 12:44 AM) Today i have spoken to someone from FMB, will provide me details on how to go about for the maintenance fees that we are incurring for a property that we have not occupied yet. I was told that we can do something about it. Still vague about it will know more in a day or two Pls provide more info after get some adv from FMB. I really unsatisfied about the developer. Also, those 1143sqf buyer pls refer to the drawing. The bath room door exactly facing with master bedroom door but from the drawing i refer, its' totally different
|
|
|
|
|
|
legendsky
|
Jul 25 2012, 09:41 AM
|
Getting Started

|
how the defect of all of your house? settle ?
|
|
|
|
|
|
anokcow
|
Jul 25 2012, 09:50 AM
|
Getting Started

|
QUOTE(legendsky @ Jul 25 2012, 09:41 AM) how the defect of all of your house? settle ? Not yet. Without water and power supply how to check ? Some switches not install properly; the ceiling also never help me to cover back... Yesterday email to Taipan HQ and shoot them but no reply from this developer. They shouldn't pass us the key since a lot of thing yet completed include utility, security cf and even car par also without lot no.....
|
|
|
|
|
|
maxnergy
|
Jul 25 2012, 10:13 AM
|
Getting Started

|
My unit have electric and water.
|
|
|
|
|
|
doomdoom
|
Jul 25 2012, 10:28 AM
|
|
QUOTE(maxnergy @ Jul 25 2012, 10:13 AM) My unit have electric and water. u r the lucky one!! how is ur unit? bad workmanship? how ur opinion on the common area n the park?
|
|
|
|
|
|
anokcow
|
Jul 25 2012, 10:50 AM
|
Getting Started

|
QUOTE(maxnergy @ Jul 25 2012, 10:13 AM) My unit have electric and water. How come your unit got electric and water ? Which unit you bought ?
|
|
|
|
|
|
maxnergy
|
Jul 25 2012, 10:54 AM
|
Getting Started

|
Water without meter, just need to go to control room And switch on, taipan had temporary connect it. There is small small defects.. Just need to rectify it, they said around 2 weeks time.. Common area is good, but I think can be improve.. The playground I think is rather packed with many equipments haha..it's nice, my unit is just 2nd flor and can see the playground from master room.. Hope it will not be too noisy.. Added on July 25, 2012, 11:29 amQUOTE(anokcow @ Jul 25 2012, 10:50 AM) How come your unit got electric and water ? Which unit you bought ? D-2-9 This post has been edited by maxnergy: Jul 25 2012, 11:29 AM
|
|
|
|
|
|
Pennbattle
|
Jul 25 2012, 12:39 PM
|
|
anyone get compensation from taipan?? all of u taken the key?? i did ask some advise from lawyer and been told not to take they key since we havent get the cf and we cant move in. the clubhouse oso not completed.....we have to write letter to taipan and they have to answer ask all that..... arrghhh headache la......
|
|
|
|
|
|
Fujixerox
|
Jul 25 2012, 12:44 PM
|
Getting Started

|
QUOTE(anokcow @ Jul 24 2012, 09:34 AM) Guys, have you checked your toilet ? Inside the chamber pot, found a lot of feces. Without water supply i also unable to clean it. 2 bath room chamber pot full with shit. . . DIRTY !!!!
|
|
|
|
|
|
raverz
|
Jul 25 2012, 06:02 PM
|
Getting Started

|
QUOTE(Pennbattle @ Jul 25 2012, 12:39 PM) anyone get compensation from taipan?? all of u taken the key?? i did ask some advise from lawyer and been told not to take they key since we havent get the cf and we cant move in. the clubhouse oso not completed.....we have to write letter to taipan and they have to answer ask all that..... arrghhh headache la...... I'll have to check with my lawyers for advice too.....I haven't collected my key yet as I'm overseas. I did not intend to collect until and unless CF is issued and water, electricity is connected legally at the very least as I can't afford the headache if it's discovered otherwise. I don't think I'm entitled to compensation until Sep/Oct. After that is a different question altogether. Does anyone know if the condo has piped gas? I intend on fitting a tankless natural gas heater to save on power costs for my stove, dishwasher, dryer, kitchen and bathroom faucets/showers. If anyone intends to do the same, please PM me so maybe can get better pricing on the heater units.
|
|
|
|
|
|
kenycw55
|
Jul 25 2012, 06:06 PM
|
Getting Started

|
QUOTE(anokcow @ Apr 24 2012, 11:22 AM) Ha.ha..For me, this is not first time thru the courts. I just get adv from lawyer . We can direct go to tribunal . This can talk later. Now the main is push developer when can get the key. Also, any outcome for the discussion within developer and Lao Weng San which held yesterday? Added on April 24, 2012, 11:26 amAre you sure ?? This is first time i heard a Condo without swimming pool !!! Even the cheap apartment also ready with swimming pool facility while get the key and CF. What kind of such developer? Condo ?? She spoil her reputation herself!! Who want to buy the next block or new project launch from her ?? Well,or you could check thru Bar Council, as I remember they do provide voluntarily lawyers for citizens
|
|
|
|
|
|
legendsky
|
Jul 25 2012, 06:53 PM
|
Getting Started

|
Many defect in my unit, wall paint feel not nicely, alot of hole around the windows frame, even the door in second bed room also install terbalik... so funny~
When the time I collect the key, they have help me test all the power point, fan point... now, waiting the water supply from them.
|
|
|
|
|
|
TrekY22
|
Jul 25 2012, 07:48 PM
|
New Member
|
QUOTE(legendsky @ Jul 25 2012, 06:53 PM) Many defect in my unit, wall paint feel not nicely, alot of hole around the windows frame, even the door in second bed room also install terbalik... so funny~ When the time I collect the key, they have help me test all the power point, fan point... now, waiting the water supply from them. wow, you are lucky someone actually went to the unit with you.... they just asked me to go up myself ! not enough manpower.
|
|
|
|
|
|
naventhran
|
Jul 25 2012, 10:31 PM
|
New Member
|
QUOTE(raverz @ Jul 25 2012, 07:02 PM) I'll have to check with my lawyers for advice too.....I haven't collected my key yet as I'm overseas. I did not intend to collect until and unless CF is issued and water, electricity is connected legally at the very least as I can't afford the headache if it's discovered otherwise. I don't think I'm entitled to compensation until Sep/Oct. After that is a different question altogether. Does anyone know if the condo has piped gas? I intend on fitting a tankless natural gas heater to save on power costs for my stove, dishwasher, dryer, kitchen and bathroom faucets/showers. If anyone intends to do the same, please PM me so maybe can get better pricing on the heater units. Guys, If we can collect the keys it would be better, and for those who want to wait also can cause the defects then the developer has the right to say that they are no more liable to the defects. I thought of collecting it and later only ask for payback.... P.S when we sign the letter receiving the Key we can put a clause there saying " accepted with protest" which will be useful in the long run for us all. *Just my 2 cents*
|
|
|
|
|
|
raverz
|
Jul 26 2012, 05:19 PM
|
Getting Started

|
QUOTE(naventhran @ Jul 25 2012, 10:31 PM) Guys, If we can collect the keys it would be better, and for those who want to wait also can cause the defects then the developer has the right to say that they are no more liable to the defects. I thought of collecting it and later only ask for payback.... P.S when we sign the letter receiving the Key we can put a clause there saying " accepted with protest" which will be useful in the long run for us all. *Just my 2 cents* In the S&P, there is a 24 month warranty on defects. Please don't spread rumors which scares all of us unnecessarily. We're all already pissed off with this developer and don't require any more heartache. hope you understand. The developer has no right to say that. BTW, I ask again to those who have already collected the keys, is there any piped gas connection? They were supposed to fit as per the S&P and what the sales person told me. For those who were asking if there was centralized astro or whatever, I believe the developer has to provide an MATV connection in each unit as per the fourth schedule in the S&P.
|
|
|
|
|
|
naventhran
|
Jul 27 2012, 12:12 AM
|
New Member
|
QUOTE(raverz @ Jul 26 2012, 06:19 PM) In the S&P, there is a 24 month warranty on defects. Please don't spread rumors which scares all of us unnecessarily. We're all already pissed off with this developer and don't require any more heartache. hope you understand. The developer has no right to say that. BTW, I ask again to those who have already collected the keys, is there any piped gas connection? They were supposed to fit as per the S&P and what the sales person told me. For those who were asking if there was centralized astro or whatever, I believe the developer has to provide an MATV connection in each unit as per the fourth schedule in the S&P. There is definately a 24 months defect liability period, as it is a standard in any CAR (Contractor All Risk) policy, and that includes anything that occurs after you have taken possession of the property and you cannot fault the developer after that...dude what more heart ache you can already get?
|
|
|
|
|
|
walle
|
Jul 29 2012, 02:18 PM
|
|
Collected my keys. Apparently the 2 weeks issue highlighted previously is actually 2 weeks for key collection..after 2weeks developer will consider all keys disburse to owner. However owner still able to report any defect after that. All defect, developer is liable within the 24 months.
My units consider quite ok..no major defects..
This post has been edited by walle: Jul 29 2012, 02:20 PM
|
|
|
|
|
|
kenycw55
|
Jul 29 2012, 09:35 PM
|
Getting Started

|
QUOTE(anokcow @ Jul 25 2012, 09:13 AM) Pls provide more info after get some adv from FMB. I really unsatisfied about the developer. Also, those 1143sqf buyer pls refer to the drawing. The bath room door exactly facing with master bedroom door but from the drawing i refer, its' totally different Well, my friend got it with the opposite side. According to the drawing, from main entrance door all the rooms should be on the left side but when we go inside all on the right side
|
|
|
|
|
|
anokcow
|
Jul 30 2012, 12:53 AM
|
Getting Started

|
No body consider about compensation ?
|
|
|
|
|