walle
post Jul 20 2012, 07:44 PM

Regular
******
Senior Member
1,151 posts

Joined: Aug 2008


QUOTE(doomdoom @ Jul 20 2012, 06:33 PM)
Anyone know how much the bank valuation now?
*
Not sure true o not but an agent that call me said 410k can get liao
maxnergy
post Jul 20 2012, 08:32 PM

Getting Started
**
Junior Member
104 posts

Joined: Feb 2010


Mine not yet overdue.. Too bad huh.. Mine is 1143sqft with 2 car parks.. How much you think can sell?
doomdoom
post Jul 20 2012, 10:01 PM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
QUOTE(walle @ Jul 20 2012, 07:44 PM)
Not sure true o not but an agent that call me said 410k can get liao
*
Wht ur unit size?
preliew
post Jul 21 2012, 12:40 AM

Getting Started
**
Junior Member
145 posts

Joined: Mar 2008
block D
user posted image

block A and B
user posted image

Garden
user posted image

user posted image

user posted image

user posted image

user posted image

user posted image

user posted image


doomdoom
post Jul 21 2012, 12:47 AM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
there are some minor defects, not major, all still fixable...with the paid price less than RM250psf at PJ location........proven it's a good buy...even though there are many negative comments for this prop...


block d lobby
user posted image

decorative main entrance door
user posted image

bedrooms decorative door
user posted image

even yard also use decorative door
user posted image

shower screen glass in bathroom
user posted image

the beam looks not nice
user posted image


anokcow
post Jul 21 2012, 12:48 PM

Getting Started
**
Junior Member
69 posts

Joined: Apr 2012
No water supply yet. Anybody start renovation? I heard can not start due to cf yet ready
doomdoom
post Jul 21 2012, 01:21 PM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
even though is not perfect in workmanship...but still quite satisfy with the work...especially those decorative doors for whole units...nice full tiles on common area...the park landscape is not too bad but can be improve more by planting more flowers and trees...eager to wait for the completion of the clubhouse and swimming pool area.....
ALVINTANCHENHANG
post Jul 23 2012, 12:05 AM

New Member
*
Junior Member
18 posts

Joined: Jul 2012


QUOTE(doomdoom @ Jul 21 2012, 01:21 PM)
even though is not perfect in workmanship...but still quite satisfy with the work...especially those decorative doors for whole units...nice full tiles on common area...the park landscape is not too bad but can be improve more by planting more flowers and trees...eager to wait for the completion of the clubhouse and swimming pool area.....
*
i only care when can get my CF..., i hope taipan really can give us CF another 3 weeks, no more cheat... mad.gif
, because taipan already took our 4 months maintainance fee without club house & facility, even CF taipan postpone to another 4 months they also earn, because we already get our key & sign so taipan no need paid us 4 months compensation..., without CF buyer can't renovation / can't stay & also will loss 4 months maintainance fee.... vmad.gif that's why i hope taipan promised 3 weeks can get CF is real 1...


Added on July 23, 2012, 12:09 am
QUOTE(ALVINTANCHENHANG @ Jul 23 2012, 12:05 AM)
i only care when can get my CF..., i hope taipan really can give us CF another 3 weeks, no more cheat... mad.gif
,  because taipan already took our 4 months maintainance fee without club house & facility, even CF taipan postpone to another 4 months they also earn, because we already get our key & sign so taipan no need paid us 4 months compensation...,  without CF buyer can't renovation / can't stay & also will loss 4 months maintainance fee.... vmad.gif  that's why i hope taipan promised 3 weeks can get CF is real 1...
*
somemore taipan never give & show me security card..., they promised got last time.


Added on July 23, 2012, 11:10 am[quote=ALVINTANCHENHANG,Jul 23 2012, 12:05 AM]
someone call me stop talking here, this idiot maybe is taipan people... drool.gif

This post has been edited by ALVINTANCHENHANG: Jul 23 2012, 11:10 AM
Jeff_lwh
post Jul 23 2012, 02:28 PM

Getting Started
**
Junior Member
294 posts

Joined: Jun 2005
From: Sec. 17, PJ / Cheras


I haven't got my letter yet. So those who got the key stop complaining... My unit is D-15-7.
khyuen
post Jul 23 2012, 02:42 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
QUOTE(Jeff_lwh @ Jul 23 2012, 02:28 PM)
I haven't got my letter yet.  So those who got the key stop complaining...  My unit is D-15-7.
*
Just got to taipan office to collect your keys. Bring cheque book along.
nadzimruddin
post Jul 23 2012, 02:45 PM

Getting Started
**
Junior Member
166 posts

Joined: Mar 2012
From: midvalley city


QUOTE(khyuen @ Jul 23 2012, 02:42 PM)
Just got to taipan office to collect your keys. Bring cheque book along.
*
u got until this friday (27th july 2012) to check defects.
raverz
post Jul 23 2012, 04:19 PM

Getting Started
**
Junior Member
211 posts

Joined: Oct 2005


QUOTE(nadzimruddin @ Jul 23 2012, 02:45 PM)
u got until this friday (27th july 2012) to check defects.
*
What do u mean? I thought there's a warranty for 'x' yrs as per any project?
doubt they can fix anything in 5 days.....they haven't even delivered water connections from what I see on the forums.

the build may be good from the picture but water connection is a must for VP. I don't think anyone can consider it to be VP without man's basic needs.
Also, on the brochures, websites and even from what the salesman informed me before buying is that there will be 5 star security with card entry, cctv and intercoms. If this is not present, it's my belief that it is in violation of the agreement. Can someone confirm this? If so, we have grounds to make demands.

I will be seeking every possible avenue to seek redress / claim for compensation as they ask for payment and we have made them timely but they did not live up to their end of the deal so why should we?

I have concerns on how this is going to be managed and where the fees collected are to be channeled to. Since there's no security, waste collection, etc, we should not be footing the bill for the other blocks since Taipan should be paying for those until the respective owners take over.

Another concern is the lack of lighting in the corridors from what I see in the pictures. I must confess I have yet to make a trip back to M'sia to collect the keys as it's hard getting flights and time off from work.

Also, the CF is not released and thus, no renovations can be carried out until then from what I understand. This is another ground for not being able to term it 'Vacant Possession'.

My final concern for now is the fact that they have stipulated regulations on the exterior appearance but did not fit the units with the grills for the entrances. If this is the case, they should appoint and pay for the installation for those tennants who chose to install grills.
nadzimruddin
post Jul 23 2012, 04:38 PM

Getting Started
**
Junior Member
166 posts

Joined: Mar 2012
From: midvalley city


QUOTE(raverz @ Jul 23 2012, 04:19 PM)
What do u mean? I thought there's a warranty for 'x' yrs as per any project?
doubt they can fix anything in 5 days.....they haven't even delivered water connections from what I see on the forums.

the build may be good from the picture but water connection is a must for VP. I don't think anyone can consider it to be VP without man's basic needs.
Also, on the brochures, websites and even from what the salesman informed me before buying is that there will be 5 star security with card entry, cctv and intercoms. If this is not present, it's my belief that it is in violation of the agreement. Can someone confirm this? If so, we have grounds to make demands.

I will be seeking every possible avenue to seek redress / claim for compensation as they ask for payment and we have made them timely but they did not live up to their end of the deal so why should we?

I have concerns on how this is going to be managed and where the fees collected are to be channeled to. Since there's no security, waste collection, etc, we should not be footing the bill for the other blocks since Taipan should be paying for those until the respective owners take over.

Another concern is the lack of lighting in the corridors from what I see in the pictures. I must confess I have yet to make a trip back to M'sia to collect the keys as it's hard getting flights and time off from work.

Also, the CF is not released and thus, no renovations can be carried out until then from what I understand. This is another ground for not being able to term it 'Vacant Possession'.

My final concern for now is the fact that they have stipulated regulations on the exterior appearance but did not fit the units with the grills for the entrances. If this is the case, they should appoint and pay for the installation for those tennants who chose to install grills.
*
i mean we have until this friday to collect the key, do the defect inspection and fill up the complaint form provided by TAIPAN.. otherwise TAIPAN will not responsible for any defect/damage/loss of the property.
doomdoom
post Jul 23 2012, 07:50 PM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
QUOTE(raverz @ Jul 23 2012, 04:19 PM)
What do u mean? I thought there's a warranty for 'x' yrs as per any project?
doubt they can fix anything in 5 days.....they haven't even delivered water connections from what I see on the forums.

the build may be good from the picture but water connection is a must for VP. I don't think anyone can consider it to be VP without man's basic needs.
Also, on the brochures, websites and even from what the salesman informed me before buying is that there will be 5 star security with card entry, cctv and intercoms. If this is not present, it's my belief that it is in violation of the agreement. Can someone confirm this? If so, we have grounds to make demands.

I will be seeking every possible avenue to seek redress / claim for compensation as they ask for payment and we have made them timely but they did not live up to their end of the deal so why should we?

I have concerns on how this is going to be managed and where the fees collected are to be channeled to. Since there's no security, waste collection, etc, we should not be footing the bill for the other blocks since Taipan should be paying for those until the respective owners take over.

Another concern is the lack of lighting in the corridors from what I see in the pictures. I must confess I have yet to make a trip back to M'sia to collect the keys as it's hard getting flights and time off from work.

Also, the CF is not released and thus, no renovations can be carried out until then from what I understand. This is another ground for not being able to term it 'Vacant Possession'.

My final concern for now is the fact that they have stipulated regulations on the exterior appearance but did not fit the units with the grills for the entrances. If this is the case, they should appoint and pay for the installation for those tennants who chose to install grills.
*
I dun think developer will install grill for u, in fact they did mentioned wont provide grill door when during launch......i think those problems like no enough lighting at corridor, security not complete yet, all are not major problems and i belive with buyers pressure, they will do it...look at the materials they provide, full tiles in kitchen n bathroom, full tiles on corridor, nice decorative doors in whole units, nice thick glass shower screen...if their intention just an to save cost n give bad meaterials, they can give the lousier materials (cheap doors,ugly tiles), cement floor on corridor....well, be patient, this property woth less than RM 250psf, its a excelent buy at PJ location...
naventhran
post Jul 23 2012, 09:07 PM

New Member
*
Junior Member
14 posts

Joined: Apr 2012


QUOTE(nadzimruddin @ Jul 23 2012, 05:38 PM)
i mean we have until this friday to collect the key, do the defect inspection  and fill up the complaint form provided by TAIPAN.. otherwise TAIPAN will not responsible for any defect/damage/loss of the property.
*
I totally agree as why do we have to pay for the maintenance fees for the month of July ( maybe August) if we have not got full access to our house. If there is no water supply, no proper security and even no proper entrance yet. Also I will be going this Satuday to collect the key in the morning, anyone else coming or you all have collected the key? We have to query further and also what about the 4 month compensation?

C


Added on July 23, 2012, 9:08 pm
QUOTE(naventhran @ Jul 23 2012, 10:07 PM)
I totally agree as why do we have to pay for the maintenance fees for the month of July ( maybe August) if we have not got full access to our house. If there is no water supply, no proper security and even no proper entrance yet. Also I will be going this Satuday to collect the key in the morning, anyone else coming or you all have collected the key? We have to query further and also what about the 4 month compensation?

*
CANNOT PROVIDE THE KEYS ON TIME WANT TO GIVE 2 WEEKS TIME FRAME FOR DEFECT CHECK THAT IS A BIT OF RUSH.......

This post has been edited by naventhran: Jul 23 2012, 09:08 PM
ALVINTANCHENHANG
post Jul 23 2012, 11:11 PM

New Member
*
Junior Member
18 posts

Joined: Jul 2012


If collect your key please ask TAIPAN : (1.) why corridors light just few only? (2.) when can get CF & compensation? (3.) security card? (4.)why maintenance not RM0.15cen? (5.) when buyer collected key developer will stop paid compensation? (6.) even TAIPAN postpone CF again, buyer still need to paid maintenance fee every month?
walle
post Jul 23 2012, 11:58 PM

Regular
******
Senior Member
1,151 posts

Joined: Aug 2008


QUOTE(nadzimruddin @ Jul 23 2012, 04:38 PM)
i mean we have until this friday to collect the key, do the defect inspection  and fill up the complaint form provided by TAIPAN.. otherwise TAIPAN will not responsible for any defect/damage/loss of the property.
*
To me that is bs, do they really set that rule?if yes i gonna create some situation there..
snetha11
post Jul 24 2012, 08:34 AM

Getting Started
**
Junior Member
116 posts

Joined: Jul 2011


QUOTE(doomdoom @ Jul 21 2012, 12:47 AM)
there are some minor defects, not major, all still fixable...with the paid price less than RM250psf at PJ location........proven it's a good buy...even though there are many negative comments for this prop...
block d lobby
user posted image

decorative main entrance door
user posted image

bedrooms decorative door
user posted image

even yard also use decorative door
user posted image

shower screen glass in bathroom
user posted image

the beam looks not nice
user posted image
*
the shower is nice!!!!! but the beam is quite ugly though sad.gif
anokcow
post Jul 24 2012, 09:34 AM

Getting Started
**
Junior Member
69 posts

Joined: Apr 2012
Guys, have you checked your toilet ? Inside the chamber pot, found a lot of feces. Without water supply i also unable to clean it. 2 bath room chamber pot full with shit. . . DIRTY !!!!
nadzimruddin
post Jul 24 2012, 11:14 AM

Getting Started
**
Junior Member
166 posts

Joined: Mar 2012
From: midvalley city


QUOTE(walle @ Jul 23 2012, 11:58 PM)
To me that is bs, do they really set that rule?if yes i gonna create some situation there..
*
that is the normal procedure between TAIPAN & contractor. the contractor only accept the defect complaint within 2weeks time FROM the date stated on the letter from TAIPAN. if not, u have to fixed/repair the damages by urself.