Taipan Group of Companies - Residency@Park51, Have you heard of this developer?
|
legendsky
|
May 9 2012, 09:49 AM
|
Getting Started

|
QUOTE(doomdoom @ May 8 2012, 08:34 AM) ya got email from DAP Lau, he will give syabas until this week...if not any solution from syabas come out this week, he will have a media press conference next week to address this issue... [I]I've informed Syabas about the concern raised by the buyers. I'm giving them some time to respond. If there aren't any respond from them within the next one week. I will call for a press conference to highlight the matter.
Weng San.When you get this reply email from LAU???? he mean next one week, so we need to wait next one week? Added on May 9, 2012, 9:53 amQUOTE(khyuen @ May 9 2012, 09:11 AM) it's already the 2nd week of May, i really hope they can deliver the keys within the next 3 weeks. The zest owner start to renovate their house, when is our turn??????????? This post has been edited by legendsky: May 9 2012, 09:53 AM
|
|
|
|
|
|
doomdoom
|
May 9 2012, 10:05 AM
|
|
yesterday just got this email from Lau...so this friday sent again to Lau and ask him..if no reply frm Syabas..then push lau to make it to public la..now is almost time for election..sure the politicians will behave very actively to help voters...
|
|
|
|
|
|
legendsky
|
May 9 2012, 10:26 AM
|
Getting Started

|
QUOTE(doomdoom @ May 9 2012, 10:05 AM) yesterday just got this email from Lau...so this friday sent again to Lau and ask him..if no reply frm Syabas..then push lau to make it to public la..now is almost time for election..sure the politicians will behave very actively to help voters... Then we wait what LAU can do for us. Anyone call to Taipan Sales Gallery recently????
|
|
|
|
|
|
khyuen
|
May 9 2012, 04:35 PM
|
Getting Started

|
sent an email today to taipan, awaiting an email reply.
|
|
|
|
|
|
Bahkuteh
|
May 9 2012, 09:41 PM
|
|
|
|
|
|
|
|
legendsky
|
May 10 2012, 01:24 PM
|
Getting Started

|
Just call Sales Gallery, Nothing updates, still not yet received any response from Syabas.
Delay Again. Well, this time they mention handover by first of June.
Good Jobs Taipan, keep delay again~
|
|
|
|
|
|
doomdoom
|
May 10 2012, 01:29 PM
|
|
QUOTE(legendsky @ May 10 2012, 01:24 PM) Just call Sales Gallery, Nothing updates, still not yet received any response from Syabas. Delay Again. Well, this time they mention handover by first of June. Good Jobs Taipan, keep delay again~ either is really syabas problem, or maybe developer is not fullfill syabas requirement..but according to Lau, is syabas problem...so in this case...please together sent email to Lau tomorrow and ask for his effort in this...
|
|
|
|
|
|
anokcow
|
May 11 2012, 09:20 AM
|
Getting Started

|
QUOTE(doomdoom @ May 10 2012, 01:29 PM) either is really syabas problem, or maybe developer is not fullfill syabas requirement..but according to Lau, is syabas problem...so in this case...please together sent email to Lau tomorrow and ask for his effort in this... My colleague bought Bandar putra 2 under IOI. Expectation end Dec 2012 but last month receive a letter from developer to get the key on 19/5. Ours???
|
|
|
|
|
|
khyuen
|
May 11 2012, 03:59 PM
|
Getting Started

|
My email to taipan 2 days ago.
May i know the status as of today. When can we take vacant possessions and the hand over of keys?
Reply from Taipan today.
Should be soon, waiting for last approval letter from Syabas side.
|
|
|
|
|
|
doomdoom
|
May 11 2012, 04:27 PM
|
|
QUOTE(khyuen @ May 11 2012, 03:59 PM) My email to taipan 2 days ago. May i know the status as of today. When can we take vacant possessions and the hand over of keys? Reply from Taipan today. Should be soon, waiting for last approval letter from Syabas side. haha, think he just simply reply...
|
|
|
|
|
|
doomdoom
|
May 11 2012, 05:28 PM
|
|
gt a reply from Lau wen san. He isgoing to organize a meeting with developer and syabas at MBPJ to resolve the problem..
Dear All,
I will organise a meeting at MBPJ to resolve this matter.
Will inform you once the details are confirmed.
Weng San --------------------------------------------------------------------------------
Date: Fri, 11 May 2012 16:29:59 +0800 (SGT) To: Taipan Group<taipan.info@gmail.com> Cc: LAU Weng San<lauwengsan@gmail.com> Subject: Re: Black list developer
Hi Taipan Can answer this question? Is really only waiting syabas issue letter? or actually Syabas is still waiting your side submit the correct documents and actually there are more stages to go before really can issue CF? Both sides tell the different stories.
This post has been edited by doomdoom: May 11 2012, 05:30 PM
|
|
|
|
|
|
doomdoom
|
May 11 2012, 05:31 PM
|
|
all buyers, especially block D buyers, kindly provide me your email address...so when Lau wen san reply my email mention about this issue, i will CC you all in the mail list...
|
|
|
|
|
|
pong85
|
May 11 2012, 09:25 PM
|
Getting Started

|
Put me in the loop. Yinpong_c@hotmail.com
|
|
|
|
|
|
khyuen
|
May 11 2012, 10:50 PM
|
Getting Started

|
keep me in the loop too.
khyuen@yahoo.com
|
|
|
|
|
|
wancm
|
May 12 2012, 12:27 AM
|
New Member
|
Put me in the loop. alicia1982@gmail.com
This post has been edited by wancm: May 12 2012, 12:27 AM
|
|
|
|
|
|
legendsky
|
May 12 2012, 08:17 AM
|
Getting Started

|
my email. bonniechooi@yahoo.com
|
|
|
|
|
|
jelawat17
|
May 12 2012, 09:01 AM
|
Getting Started

|
Doomdoom mine too jelawat17@hotmail.com.
By the way, thanks for coordinating this.
Pls inform to Mr. Lau when having the meeting in MBPJ to also discuss on the compensation for handling over without the clubhouse facility. This I had confirmed from the lawyers that handle the signing of our S&P for Park51 the parcel of Block D is inclusive of the Club house facilities.
You (or everone) may contact the lawyers that handle yours.
Remember, this is to protect buyers who wanted to sell or rent their units with a lower price due to our condo now is an apartment/flat.
|
|
|
|
|
|
anokcow
|
May 12 2012, 10:01 PM
|
Getting Started

|
QUOTE(jelawat17 @ May 12 2012, 09:01 AM) Doomdoom mine too jelawat17@hotmail.com. By the way, thanks for coordinating this. Pls inform to Mr. Lau when having the meeting in MBPJ to also discuss on the compensation for handling over without the clubhouse facility. This I had confirmed from the lawyers that handle the signing of our S&P for Park51 the parcel of Block D is inclusive of the Club house facilities. You (or everone) may contact the lawyers that handle yours. Remember, this is to protect buyers who wanted to sell or rent their units with a lower price due to our condo now is an apartment/flat. Put me in the loop bnchem@gmail.com S&P stated no include club house and swimming pool facilities
|
|
|
|
|
|
jelawat17
|
May 12 2012, 11:03 PM
|
Getting Started

|
QUOTE(anokcow @ May 12 2012, 10:01 PM) Put me in the loop bnchem@gmail.com S&P stated no include club house and swimming pool facilities You are right & I do not denied that The Club House, Swimming Pool, Gym & Other ClubHouse Facilities are not part of the Common Facility as mentioned in the S&P (as these are open to public membership by Taipan) but is a part of the 'accessory parcel'. You may read your S&P Section 35(a) Interpretation for 'accessory parcel'. Remember the sales in promoting Park51 is with these facilities & the price we paid for is equivalent to other condo ex. Zen during year 2008-9. Anyway, as mentioned earlier, the Lawyers that handled this S&P also said we are entitled for this compensation. I hope everyone is clear about this!!!! Let's gather together for Bersih Park51. OK. TQ.
|
|
|
|
|
|
doomdoom
|
May 12 2012, 11:22 PM
|
|
Pass there today, dun see any workers working on clubhouse area, temple still there, the clubhouse and the swimming pool area, i think at least need another 1 year to complete judging frm the status and the way the developer work....see few workers work on block a and b.....but i see lots of workers at the area near police station there like demolish the old building and try to built something new...is the plaza sentral project by taiapan too?...if yes, means they rather arrange more man power to work on other thing than the condo work....thmubs down for this developer.....sucks...   Block b, another 2 levels reach top  Block a, reach top oledy
|
|
|
|
|