Taipan Group of Companies - Residency@Park51, Have you heard of this developer?
|
khyuen
|
Dec 7 2011, 08:19 PM
|
Getting Started

|
just paid the Electric and Water deposits today at the Sales Gallery. Was inform that Park 51 will only be ready after CNY. Most probably will get your house keys in Feb 2012. Targeted for Inspection and CF in Jan 2012.
Can't wait to move in.... any neighbors in Block D?
Added on December 7, 2011, 8:23 pm Since they are delaying the project, was browsing through the S&P that 1 of the clause stated in the S&P. The developers need to complete upon 36 months of the S&P agreement date, Park 51 developers need to pay compensation to house buyers of 10% per annum of purchase price on a daily rate. Anyone knows how can we claim from the developers?
This post has been edited by khyuen: Dec 7 2011, 08:25 PM
|
|
|
|
|
|
khyuen
|
Dec 8 2011, 11:52 PM
|
Getting Started

|
QUOTE(doomdoom @ Dec 7 2011, 10:39 PM) what the stamp date for the S&P? the stamp date was 3rd Dec 2008.
|
|
|
|
|
|
khyuen
|
Dec 9 2011, 04:25 PM
|
Getting Started

|
QUOTE(doomdoom @ Dec 9 2011, 08:33 AM) it;s over exceed 36 months...just ask developer charge for LAD... doom, what is LAD?
|
|
|
|
|
|
khyuen
|
Feb 4 2012, 12:14 AM
|
Getting Started

|
Let's form a group to claim compensation from the developer. I guess all block D owners should voice out your opinion. Looking at the main entrance, i assume it will take another 2 months to complete. Most probably possible to take VP in May.
|
|
|
|
|
|
khyuen
|
Feb 13 2012, 09:29 PM
|
Getting Started

|
how do we file claim for compensation? anyone has any experience in doing this for the 10% compensation?
|
|
|
|
|
|
khyuen
|
Feb 17 2012, 04:40 PM
|
Getting Started

|
As expected a delay, hope they can expedite on the inspection approval with the officers.
Added on February 17, 2012, 4:43 pm Can some kind soul post some photos on the latest development.
This post has been edited by khyuen: Feb 17 2012, 04:43 PM
|
|
|
|
|
|
khyuen
|
Mar 1 2012, 09:27 AM
|
Getting Started

|
Anyone called up taipan group?
Added on March 1, 2012, 9:30 amTried calling this morning....but no one pick up.
This post has been edited by khyuen: Mar 1 2012, 09:30 AM
|
|
|
|
|
|
khyuen
|
Mar 29 2012, 06:03 PM
|
Getting Started

|
Sent email many time but no reply. Wtf??
|
|
|
|
|
|
khyuen
|
Mar 31 2012, 11:55 AM
|
Getting Started

|
Can Mr Lau do something about it, if we sent him an email? I am also a block D buyer, but i doubt he can do anything on it.
|
|
|
|
|
|
khyuen
|
Apr 3 2012, 09:31 PM
|
Getting Started

|
i have done my part. Sent an email 2 days ago to Mr Lau.
Hope they can hand over the keys by month end April.
|
|
|
|
|
|
khyuen
|
Apr 5 2012, 09:50 AM
|
Getting Started

|
Can we have Ricard Yeoh email address. I guess we need to sent more emails to pressure the developers. Added on April 5, 2012, 11:11 amThe email reply from Taipan today, i sent them an email on the 1st of March 2012 and taipan only reply today. Hi, We are currently waiting for approval letter from Bomba and Syabas respectively for the CF to be completed. We will inform you through post once the date of handover of keys is set. Sorry for the inconveniences.. -- Regards, Andrew Jr. (Andy) Taipan Group of Companies http://www.taipangroup.com.myTel: +603 - 33716010 Fax: +603 - 33715998 *** This mail is sent on behalf of Taipan Group of Companies. If you are no longer interested, you can reply taipan.info@gmail.com with the subject "Unsubscribe". This post has been edited by khyuen: Apr 5 2012, 11:11 AM
|
|
|
|
|
|
khyuen
|
Apr 10 2012, 03:27 PM
|
Getting Started

|
An email sent to Simon of Taipan Group from Mr Lau today.
Discussion on delivery of Block D Park 51 Residency
FROM:
LAU Weng San
TO:
Simon Igutius Taipan Focus
Message flagged Tuesday, April 10, 2012 3:12 PM Dear Simon,
I would like to make an arrangement to discuss with you together with a group of house buyers who have purchased block D in 2008 requesting for vacant possession from your side. As I can observe, Block D is already completed and I wonder what is the reason that is holding you up from handing over the vacant possession to the buyers on time.
Please reply if you can fix a suitable date, time and venue for the meeting.
Thank you.
Regards, Weng San
This post has been edited by khyuen: Apr 10 2012, 04:03 PM
|
|
|
|
|
|
khyuen
|
Apr 10 2012, 04:39 PM
|
Getting Started

|
All these indicate that Puncak Niaga is a bankrupt company (PN17) and should not be allowed to continue managing the water resources in Selangor and that the Privatisation and Concession Agreement should be terminated. 2) From the Puncak Niaga Financial Statement FYE 2010 on page 259, you will see that: i) The Executive Directors’ Remunerations amount to RM15,580,872 ii) One of them earned between RM6,800,000 to RM6,900.000 Given the above and also: 1) That PNSB/SYABAS has not been able to reduce the Non-Revenue Water -- which currently is above 30% (when it should be not more than 20%) -- due to non-replacement of pipes, as provided in the Concession Agreement. 2) That SYABAS has been paying the water treatment companies only about 40% of their bills since Pakatan Rakyat took over the state government. (The companies are now suing SYABAS for about RM2 billion in unpaid bills). 3) That SYABAS has also refused to approve the water supply for new development projects in Kuala Lumpur and Selangor, thus jeopardising the Selangor as well as the Federal Government's ‘Transformation Plan’ -- as no new development projects, residential, commercial and industrial, will be approved by SYABAS.
This post has been edited by khyuen: Apr 10 2012, 04:39 PM
|
|
|
|
|
|
khyuen
|
Apr 10 2012, 04:40 PM
|
Getting Started

|
3) That SYABAS has also refused to approve the water supply for new development projects in Kuala Lumpur and Selangor, thus jeopardising the Selangor as well as the Federal Government's ‘Transformation Plan’ -- as no new development projects, residential, commercial and industrial, will be approved by SYABAS.
Looks like SYABAS is the culprit here.
|
|
|
|
|
|
khyuen
|
Apr 18 2012, 09:06 AM
|
Getting Started

|
any news on the developers?
|
|
|
|
|
|
khyuen
|
Apr 19 2012, 02:22 PM
|
Getting Started

|
so we should be getting around Rm 10,000 from the developers, if delay another month it will Rm 12,000. Enough to renovate your kitchen.
|
|
|
|
|
|
khyuen
|
Apr 23 2012, 12:02 PM
|
Getting Started

|
Mr Lau Weng San will be having a meeting with the developers in Park 51 office today at 1pm. Anyone free please join him in the sales office today.
|
|
|
|
|
|
khyuen
|
Apr 23 2012, 02:49 PM
|
Getting Started

|
It's already more than 4 months after S&P dated Dec 3rd 2011 for completion on Block D. Definitely going to ask for full repayment from Taipan Group.
|
|
|
|
|
|
khyuen
|
Apr 23 2012, 05:46 PM
|
Getting Started

|
QUOTE(anokcow @ Apr 23 2012, 03:27 PM) Your S&P also dated 3/12? Same with me. From 4/12/2012 to 3/5/2012 it has delay 5 months !!! Yes 5 months! must claim from them.
|
|
|
|
|
|
khyuen
|
Apr 24 2012, 04:22 PM
|
Getting Started

|
latest email from Lau Weng San.
Dear Shanmugan,
The important thing to do is to press Syabas for the approval. Pushing Taipan will not work because as businessman will try to avoid clash with the authority, fearing that they will be given "special" treatment by the authority in future.
Anyway, I have informed Taipan that in future they should inform me if they are delayed by any government authority. I will write to Syabas to push them for the approval.
Thank you.
Regards, Weng San
|
|
|
|
|