 Taipan Group of Companies - Residency@Park51, Have you heard of this developer?

views
     
kochin
post Apr 3 2012, 10:25 AM

I just hope I do!
********
All Stars
10,314 posts

Joined: Dec 2009
From: Malaysia


when was the first SPA for block D signed anyway.
they could very well be within SPA date and hence nobody can do anything on them.
besides, what's the rush? seems like the building is already completed. at this juncture, the developer would be more 'kan cheong' than you guys since they still got >15% stuck in HDA while the remaining works might cost them <2% of project cost.
chill!
raverz
post Apr 3 2012, 02:14 PM

Getting Started
**
Junior Member
211 posts

Joined: Oct 2005


QUOTE(kochin @ Apr 3 2012, 10:25 AM)
when was the first SPA for block D signed anyway.
they could very well be within SPA date and hence nobody can do anything on them.
besides, what's the rush? seems like the building is already completed. at this juncture, the developer would be more 'kan cheong' than you guys since they still got >15% stuck in HDA while the remaining works might cost them <2% of project cost.
chill!
*
I signed mine much later as I was once of the last few i believe. So I'm not really looking for compensation but a definite timeline to facilitate my planning. Who is the MP of this area anyway? is it the guy you've been writing to? I think we need to arrange a consultation with the MP as well as the developer so we can move forward with this.
khyuen
post Apr 3 2012, 09:31 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
i have done my part. Sent an email 2 days ago to Mr Lau.

Hope they can hand over the keys by month end April.
legendsky
post Apr 4 2012, 11:49 AM

Getting Started
**
Junior Member
125 posts

Joined: Oct 2008
From: KL


From DAP Mr. Lau,


I will discuss with Taipan and try to arrange for an appointment for you and other buyers to meet the developer.

Weng San.
doomdoom
post Apr 4 2012, 12:41 PM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
QUOTE(legendsky @ Apr 4 2012, 11:49 AM)
From DAP Mr. Lau,
I will discuss with Taipan and try to arrange for an appointment for you and other buyers to meet the developer.

Weng San.
*
see, it start to works..make sure Lau is on our side....
raverz
post Apr 4 2012, 04:39 PM

Getting Started
**
Junior Member
211 posts

Joined: Oct 2005


QUOTE(doomdoom @ Apr 4 2012, 12:41 PM)
see, it start to works..make sure Lau is on our side....
*
Just spoke to Vanessa. She said handover end of this month apparently. I asked if it's confirmed and she said yes.
Also asked how will we be notified to which she answered "by post".

Suggest more ppl call to confirm the same.

This post has been edited by raverz: Apr 4 2012, 04:39 PM
nadzimruddin
post Apr 4 2012, 05:06 PM

Getting Started
**
Junior Member
166 posts

Joined: Mar 2012
From: midvalley city


I'm one of the block D buyer. email mr.lau already. icon_rolleyes.gif
kshan223
post Apr 4 2012, 05:28 PM

New Member
*
Junior Member
25 posts

Joined: Oct 2007
QUOTE(raverz @ Apr 4 2012, 04:39 PM)
Just spoke to Vanessa. She said handover end of this month apparently. I asked if it's confirmed and she said yes.
Also asked how will we be notified to which she answered "by post".

Suggest more ppl call to confirm the same.
*
I've send complaint mail to Mr.Lau d.....hope he would take action....nxt planed to call the DAP local councillor Richard Yeoh Yong Woi 012-3028801 and check how he can help....btw who is Vanessa bro....is she one of Taipan staff? I do really hope could get the key soonest as got alot pending plans base on that.....m also currently checking whether can lodge a report with Kementerian Perumahan or no....will update u guys soon on this....
doomdoom
post Apr 4 2012, 08:20 PM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
QUOTE(raverz @ Apr 4 2012, 04:39 PM)
Just spoke to Vanessa. She said handover end of this month apparently. I asked if it's confirmed and she said yes.
Also asked how will we be notified to which she answered "by post".

Suggest more ppl call to confirm the same.
*
I think at this moment, not need call developer ask them when can handiver key, they sure wil say, next month, asap....then next month nothing happen....just use those political power to pressure them....now is almost time for election, sure the DAP politicians wil be very helpful to the voters....not need listen to wht vannesa say....let the DAP politicians called some media and ask the vannesaa to commit to public..


Added on April 4, 2012, 8:21 pm
QUOTE(kshan223 @ Apr 4 2012, 05:28 PM)
I've send complaint mail to Mr.Lau d.....hope he would take action....nxt planed to call the DAP local councillor Richard Yeoh Yong Woi 012-3028801 and check how he can help....btw who is Vanessa bro....is she one of Taipan staff? I do really hope could get the key soonest as got alot pending plans base on that.....m also currently checking whether can lodge a report with Kementerian Perumahan or no....will update u guys soon on this....
*
Yes very good, i am block A buyer, i wil raise my concern to Richard YEoh also....wht his email?

This post has been edited by doomdoom: Apr 4 2012, 08:21 PM
khyuen
post Apr 5 2012, 09:50 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Can we have Ricard Yeoh email address. I guess we need to sent more emails to pressure the developers.


Added on April 5, 2012, 11:11 amThe email reply from Taipan today, i sent them an email on the 1st of March 2012 and taipan only reply today.

Hi,

We are currently waiting for approval letter from Bomba and Syabas respectively for the CF to be completed. We will inform you through post once the date of handover of keys is set. Sorry for the inconveniences..

--
Regards,

Andrew Jr. (Andy)
Taipan Group of Companies
http://www.taipangroup.com.my
Tel: +603 - 33716010
Fax: +603 - 33715998

*** This mail is sent on behalf of Taipan Group of Companies. If you are no longer interested, you can reply taipan.info@gmail.com with the subject "Unsubscribe".


This post has been edited by khyuen: Apr 5 2012, 11:11 AM
doomdoom
post Apr 5 2012, 11:11 AM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
Reply from the developer regaridng my complaint about the funny flashing light on top of block D.


Hi,


The blinking lights up there is just a tester, we will revert back to 1 single light once Block D's CF is out. Currently awaiting approval letter from Bomba and Syabas as we are still rushing them. Sorry for the inconveniences..


Added on April 5, 2012, 11:14 amI think the develoepr feel the pressure when the policitian come into pressure them so they finally take some time to reply the email...


so the move is good, complaint to politician can make them feel pressure and they will fasten up the process....all buyers please continue the war...

This post has been edited by doomdoom: Apr 5 2012, 11:14 AM
legendsky
post Apr 5 2012, 03:31 PM

Getting Started
**
Junior Member
125 posts

Joined: Oct 2008
From: KL


QUOTE(khyuen @ Apr 5 2012, 09:50 AM)
Can we have Ricard Yeoh email address. I guess we need to sent more emails to pressure the developers.


Added on April 5, 2012, 11:11 amThe email reply from Taipan today, i sent them an email on the 1st of March 2012 and taipan only reply today.

Hi,

We are currently waiting for approval letter from Bomba and Syabas respectively for the CF to be completed. We will inform you through post once the date of handover of keys is set. Sorry for the inconveniences..

--
Regards,

Andrew Jr. (Andy)
Taipan Group of Companies
http://www.taipangroup.com.my
Tel:  +603 - 33716010
Fax: +603 - 33715998

*** This mail is sent on behalf of Taipan Group of Companies. If you are no longer interested, you can reply taipan.info@gmail.com with the subject "Unsubscribe".
*
I also get reply email from taipan, just same with u. I think they cut and paste only ... rclxub.gif


Added on April 5, 2012, 3:34 pmFew week ago, Vanessa also said waiting Bomba officer to sent back the report only. but now the email reply leave Bomba and Syabas report. Why suddenly come out Syabas?????



This post has been edited by legendsky: Apr 5 2012, 03:34 PM
doomdoom
post Apr 5 2012, 03:38 PM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
QUOTE(legendsky @ Apr 5 2012, 03:31 PM)
I also get reply email from taipan, just same with u. I think they cut and paste only ... rclxub.gif


Added on April 5, 2012, 3:34 pmFew week ago, Vanessa also said waiting Bomba officer to sent back the report only. but now the email reply leave Bomba and Syabas report. Why suddenly come out Syabas?????
*
ya, so you shuold write another email to taipan and CC Lau wen sang...askl taipan why everytime is different stories?....

give them pressure...dun let them just entertain us...come go write email complaint and complaint....remember cc DAP guys...
raverz
post Apr 9 2012, 12:12 PM

Getting Started
**
Junior Member
211 posts

Joined: Oct 2005


QUOTE(doomdoom @ Apr 5 2012, 03:38 PM)
ya, so you shuold write another email to taipan and CC Lau wen sang...askl taipan why everytime is different stories?....

give them pressure...dun let them just entertain us...come go write email complaint and complaint....remember cc DAP guys...
*
Could this be the reason for delay?
http://www.malaysia-today.net/mtcolumns/48...ook-at-selangor
khyuen
post Apr 10 2012, 03:27 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
An email sent to Simon of Taipan Group from Mr Lau today.


Discussion on delivery of Block D Park 51 Residency


FROM:

LAU Weng San

TO:

Simon Igutius Taipan Focus



Message flagged
Tuesday, April 10, 2012 3:12 PM
Dear Simon,

I would like to make an arrangement to discuss with you together with
a group of house buyers who have purchased block D in 2008 requesting
for vacant possession from your side. As I can observe, Block D is
already completed and I wonder what is the reason that is holding you
up from handing over the vacant possession to the buyers on time.

Please reply if you can fix a suitable date, time and venue for the meeting.

Thank you.

Regards,
Weng San

This post has been edited by khyuen: Apr 10 2012, 04:03 PM
kshan223
post Apr 10 2012, 03:37 PM

New Member
*
Junior Member
25 posts

Joined: Oct 2007
Hi guys...below is the reply i got frm Mr.Lau....I believe the others got it too as i saw he've cc the mail to 3 other buyers who bought it on 2008....hopefully we could meet wth the management and sought this things out....Btw....i dont have Richard's mail ID....only got HP number which i obtain from DAP selangor website....

Dear Simon,

I would like to make an arrangement to discuss with you together with
a group of house buyers who have purchased block D in 2008 requesting
for vacant possession from your side. As I can observe, Block D is
already completed and I wonder what is the reason that is holding you
up from handing over the vacant possession to the buyers on time.

Please reply if you can fix a suitable date, time and venue for the meeting.

Thank you.

Regards,
Weng San

doomdoom
post Apr 10 2012, 04:38 PM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
yeah, now let the developer feel the pressure...
khyuen
post Apr 10 2012, 04:39 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
All these indicate that Puncak Niaga is a bankrupt company (PN17) and should not be allowed to continue managing the water resources in Selangor and that the Privatisation and Concession Agreement should be terminated.
2) From the Puncak Niaga Financial Statement FYE 2010 on page 259, you will see that:
i) The Executive Directors’ Remunerations amount to RM15,580,872
ii) One of them earned between RM6,800,000 to RM6,900.000
Given the above and also:
1) That PNSB/SYABAS has not been able to reduce the Non-Revenue Water -- which currently is above 30% (when it should be not more than 20%) -- due to non-replacement of pipes, as provided in the Concession Agreement. 
2) That SYABAS has been paying the water treatment companies only about 40% of their bills since Pakatan Rakyat took over the state government. (The companies are now suing SYABAS for about RM2 billion in unpaid bills).
3) That SYABAS has also refused to approve the water supply for new development projects in Kuala Lumpur and Selangor, thus jeopardising the Selangor as well as the Federal Government's ‘Transformation Plan’ -- as no new development projects, residential, commercial and industrial, will be approved by SYABAS.

This post has been edited by khyuen: Apr 10 2012, 04:39 PM
doomdoom
post Apr 10 2012, 04:39 PM

Look at all my stars!!
*******
Senior Member
4,973 posts

Joined: Dec 2010
by the way, last 2 days pass by there, saw lots of workers working around at clubhouse area....let give them pressure gao gao and let them full speed to complete the work that suppose to complete last year..
khyuen
post Apr 10 2012, 04:40 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
3) That SYABAS has also refused to approve the water supply for new development projects in Kuala Lumpur and Selangor, thus jeopardising the Selangor as well as the Federal Government's ‘Transformation Plan’ -- as no new development projects, residential, commercial and industrial, will be approved by SYABAS.

Looks like SYABAS is the culprit here.