QUOTE(tehaikseong @ Mar 22 2012, 03:20 PM)
If the current resident do not want to join, then we set up our own, fence up to new phase only.
Hai tehaikseong, i would like to join, unfortunately a lot of people from phase 1/2 seems like they have no interest in it. Is really frustrated that after 3 years we still have no TM line.
Lately my main fuss box masuk air, and my living area ceiling got a big patch of water stain. So I call the renovation guy cum plumber to come and c this problem, he claims that my master bedroom toilet pipe was not fix probably and there is a lot of gaps around the flooring, and the stupid designer, design the house in a way that the main fuss box is build below the master bedroom toilet. AND IS A BIG STUPID DESIGN.
Added on April 2, 2012, 5:07 pmQUOTE(edwinlcw @ Apr 2 2012, 04:58 PM)
why you will cry more when you take your key?? many defected materiel inside the house??
btw.. when to phase 5 site yesterday.. the drain outside has been done and i can see that there is alot more piles of wood there and the extra pillar has been cut...
Ya lor edwinlcw, uncountable defects.... and the best part is after 3 years you still c defects. And when you ask people to come and fix your defects they are not cheap.... minimum at least 1k and above...... crazyyyyyyyyyyyyy
This post has been edited by LTSAudrey: Apr 2 2012, 05:07 PM