 Ask me anything abt Construction Industry!, Q&A

views
     
TSiwubpreve
post Apr 11 2015, 01:47 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(AmpBuster @ Mar 13 2015, 08:14 PM)
Dunno if relevant, but how much does it cost to lay 1000 km of fibre?
*
no idea. need basis to estimate. like excavation cost how much per km, then lay of fibre cable how much per km, then how much of backfill and premix tar road per km. the cost times 1000 is the answer. this is how QS estimate the price.
TSiwubpreve
post Apr 11 2015, 01:48 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Runec @ Mar 16 2015, 12:29 AM)
I have a 0.67 acre project in Rungkup, Perak.

Do you have contacts for any civil and structural engineers in near there? Teluk Intan would be the nearest town.

Contacts for sub-contractors would be good also.

Thanks in advance
*
no idea on those remote place 1 sweat.gif
TSiwubpreve
post Apr 11 2015, 01:53 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(jolipoli81 @ Mar 19 2015, 03:30 PM)
say if the structural work already almost complete, then Architect say need windows coping as rain water might splash in. Main con ask subcon to cast the coping.

1. Which method will he use? Using lintel or cast it separately?

2. Subcon want to measure by kongsi kong rather than in meter run, because subcon said cannot cover. How to argue with him?
*
actually there are poly foam coping. light and easy to fix. but of course provided Architect accepted this proposal sweat.gif

look in the contract of variation work clauses. it allow main con to claim in daywork too if the work cannot be measured. but this case u can measure. so cannot claim daywork, but u can convert daywork to meter run. definitely the ordinary process of work is disrupted therefore different price have to be allow to cater such variation. u need to justify this to client. if client say can do at cheap cost, tell him pass u that subcon. u use that subcon and mark up 15% as allow in contract. PAM standard form of contract allow 15% mark up provided the subcon invoice shown to client. of course this best to be done b4 u physically execute the work.
TSiwubpreve
post Apr 11 2015, 01:55 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(memekfalui @ Mar 19 2015, 11:53 PM)
Construction material and tools source from China are at dirt cheap price if buy in bulk, true or false?
*
yes. lot of material is cheap if u can import in bulk quantities. Sanitary wares and fitting, glass, aluminium extrusion, tile, steel bar and etc. quality is on par as well.
TSiwubpreve
post Apr 11 2015, 01:55 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(vin_ann @ Mar 20 2015, 06:50 AM)
Construction materials are GST Standard rated right?

When developer unable to charge gst to house buyer, they will build in gst cost into the house price.

This will happens right?
*
developer won't make rugi business. for sure they factor in the GST in the selling price la sweat.gif
TSiwubpreve
post Apr 11 2015, 01:56 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Slyp @ Mar 23 2015, 03:03 PM)
is construction industry a better career development when compared to accounting/finance?
*
think account / finance is better career. imagine work at bank bonus 10 months, this will never happen at contractor sweat.gif
poooky
post Apr 11 2015, 01:57 PM

Enthusiast
*****
Junior Member
824 posts

Joined: Sep 2011
QUOTE(iwubpreve @ Apr 11 2015, 01:46 PM)
varies. i can tell u this markup go through many level already. for developer, 25% is profit while 75% is expenses to build the building up.

Out of 75%, 60% is main con and the balance 15% goes to consultant fee, local authority contribution, marketing & advertising, and etc.

Out of 60%, 54% is actual cost given to subcon fixing cost and maincon supervision cost while 6% is main con profit.

out of 54%, 46% is the material and labour subcon use while 8% is subcon profit.

in conclusion, actual material and labour cost to build is just 46% sweat.gif

of course this is different from project to project biggrin.gif
*
Didn't expect any1 to reply.

46% is a lot.I tot banglas worker wif peanut pay bring down d cost but I guess d cost savings ady songlap kaokao d.

Tq for d insight.

TSiwubpreve
post Apr 11 2015, 01:57 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(twins9 @ Mar 24 2015, 11:57 AM)
Mech engineer, 5 years experience, pay rm42k a year, is that a lot lower than civil engineer with similar 5 years experience?
*
bro, fresh engineer get RM2.6k at consultant. if contractor RM3k for fresh graduate is easy la sweat.gif got degree in mechanical engineering right?
TSiwubpreve
post Apr 11 2015, 01:59 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(timizama @ Mar 25 2015, 03:48 PM)
how much does it cost to make a swimming pool
about 1.6m deep, 12m long 6m wide?
plus the generator, filter mechanism and others
Quote me the cheapest price to highest?
*
better get a contractor to quote u. it involve various of specialist. sand filter, water pump supplier, swimming pool builder, M&E contractor fixing the thing and etc.
TSiwubpreve
post Apr 11 2015, 01:59 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Protagonist @ Mar 26 2015, 07:21 PM)
Boy, I pm you later  brows.gif
*
bro, what kang tao u have? do let me know brows.gif
TSiwubpreve
post Apr 11 2015, 02:01 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(blek @ Apr 5 2015, 09:56 PM)
How to become safety officers?
How to get the license?
Any requirement needed?
*
go attend seminar. obtain the green book. if not mistaken is niosh department. but nowadays they require degree in ESH would be a good stepping stone. Environment, safety and health.
soulmate
post Apr 13 2015, 11:47 AM

..your girlfriend said im a good kisser
******
Senior Member
1,276 posts

Joined: Jan 2003
From: ..in your heart 中心 Status: Blessed

QUOTE(iwubpreve @ Oct 17 2014, 01:30 PM)
hey guys, u may ask me anything about construction industry and i'll try my best to answer all ur question.
biggrin.gif

Construction Industry is so complex and actually affect various party namely,

House buyer / Purchaser
Developer
Consultant (Architect, Engineer and etc)
Main Contractor
Subcontractor / Vendor / Supplier
Local Authority (DBKL, BOMBA, SYABAS, TNB, TELEKOM, POS, JKKP, IWK and etc.)

u can also ask me about construction law. I know a lot abt that too biggrin.gif
*
my friend took this QS course in uni

how good is job prospect for a QS in construction industry, any recommendation for which comp. or kind of related job for a fresh grad QS to apply?

thanks
TSiwubpreve
post Apr 13 2015, 12:40 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(soulmate @ Apr 13 2015, 11:47 AM)
my friend took this QS course in uni

how good is job prospect for a QS in construction industry, any recommendation for which comp. or kind of related job for a fresh grad QS to apply?

thanks
*
Langdon Seah, KPK. for gain experience.

This post has been edited by iwubpreve: Apr 13 2015, 12:40 PM
beyd
post Apr 18 2015, 10:07 PM

Getting Started
**
Junior Member
77 posts

Joined: May 2010
hello TS, want to ask u something..

it been my dream to built house using a container.. i dont have problem with the exterior since i can clad it with timber... what i want to know is.. how to get smooth finish on the interior so that it felt like a cement wall..and also i dont want it to feel hollowed and feel like there`s a cavity inside it..

what`s ur oppinion TS? if i want to achieve a house like this https://www.youtube.com/watch?v=5riy3rs8J4U in malaysia, which way is cheaper? container or common brickwork..?
ihatemynahs
post Apr 19 2015, 05:28 PM

New Member
*
Junior Member
48 posts

Joined: Dec 2010


QUOTE(beyd @ Apr 18 2015, 10:07 PM)
how to get smooth finish on the interior so that it felt like a cement wall..and also i dont want it to feel hollowed and feel like there`s a cavity inside it..
*
Use cement board to clad the interior walls and use foam insulation to fill the cavity between the board and the container wall.

But I doubt the dampening effect will be perfect because the container walls are corrugated to begin with.

The insulation advantages would be a cooler interior and perhaps better soundproofing.

Just my two cents.
ycs
post Apr 21 2015, 11:40 AM

MEMBER
*******
Senior Member
4,217 posts

Joined: Jan 2003
From: Selangor



can you help to spec a hollow rectangular/square metal tube for metal column and horizontal support for 18' x 6' clay roofing for the side of house? what thickness/grade of metal to use?

thinking to use 2"x4" for 18' support and 3"x3" for column support

edit: nvm, sorted out with supplier using 1.9mm RHS and SHS

This post has been edited by ycs: Apr 23 2015, 02:27 PM
birdman8
post Apr 24 2015, 04:19 PM

Getting Started
**
Junior Member
96 posts

Joined: Mar 2015
hello,
why the malaysian road got some many potholes if compare to other third world countries such as vietnam or indonesia ?
is it fair to say it is due to the quality of the construction material or method used to save costs?
heavenly91
post Apr 25 2015, 05:15 PM

Follow One Course Until Successful.
******
Senior Member
1,717 posts

Joined: Apr 2010
From: Selangor



Still driving PREVE?
blek
post Apr 26 2015, 09:51 PM

Enthusiast
*****
Junior Member
718 posts

Joined: Oct 2008
how to calculate premium for CAR and WCP insurance?
SUSzaini900
post Apr 27 2015, 08:08 PM

New Member
*
Junior Member
38 posts

Joined: Aug 2007
Just now i've a meeting with a consultant.

He asked me whether i can do design and supervision work for geotechnical scope.

my question is how much profit and job scope am i seeing for the supervision work?

currently we are doing the geotechnical design work.