QUOTE(koigh @ Mar 12 2014, 08:49 AM)
Saw "The Two" banner hanging on lamp post in front Tesco Rawang......
It is the project already start?
*
i think so. there actual site are doing land clearing now. you can see it from NSK Rawang. but not too sure whether that's the accurate site or not. In sg. bakau (direction to M-Residence) also has major land clearing activities on hill nearby to highway. I think that's the linkage of The TWO between 2 site.
jason_chee
post Mar 22 2014, 12:15 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(koigh @ Mar 21 2014, 08:28 AM)
I found few advertisement of MR in i-property......
When target VP?
Most expensive is 750k corner lot phase 1
*
if Corner Lot Phase 1 SuperLink (22x80) then RM 750K is fair. But if Corner-Link (18x70), then it's a bit too expensive.
jason_chee
post Mar 27 2014, 11:05 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(Deathscythe@@ @ Mar 22 2014, 03:16 PM)
Phase one got 22 x 80 corner lot?
*
yes. Phase 1 comprises of 18x70 (Link House) and 22x70 (Superlink House).
jason_chee
post Mar 30 2014, 08:30 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(Chris Chew @ Mar 28 2014, 01:38 AM)
Bro, MR1 Phase 1 got 22x70 superlink?

Nvr heard of it and I thought only 18x70?
*
hmm.gif how come i typed 70. sorry sorry. it's suppose to be 22x80 (Superlink).

This post has been edited by jason_chee: Mar 30 2014, 08:31 PM
jason_chee
post Apr 1 2014, 04:52 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(Rusby @ Mar 31 2014, 11:33 AM)
But then, 22' x 80' still should not qualify as a superlink. Min width should be 24' with total land area approx 2k sf + built up close to 3k sf. Very misleading marketing strategy these days. Just m2c
*
IMO, Superlink is just a name coined for marketing purposes. The word SUPER sound like "Big" / "Giganctic" / "Spacious" / "Very Wide". Perhaps sound good. Some argued anything with 22" and > is consider as Superlink. Some said Not. It's very subjective. But if you refer back to MS, they called it Superlink for 22x80. biggrin.gif
jason_chee
post Apr 7 2014, 03:52 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(Lyh2929 @ Apr 1 2014, 10:06 PM)
Ya. Phase 1. Snp on 2 Mac 2012. More than 2 years de. Don't how they compensate us.
*
have u get any news from on VP date for MR1 - Phase 1?
jason_chee
post May 27 2014, 05:53 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


2 months more? it's surpassed the SnP date and how do we claim the compensation? Anyone do that?
jason_chee
post May 27 2014, 06:03 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(bennycfw @ May 27 2014, 05:59 PM)
By the way, just curious if I can remove the tree and the grass patch in front of my gate?
*
i dun think so. last time i check, i need to re-plant a new tree if the town council discover that.
jason_chee
post May 28 2014, 04:41 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


before CF, we need to pay Deposit to open account with TNB and SYABAS. this step not yet executed. i think might delay for 1 or 2 months. nvm. i wait patiently.
jason_chee
post May 30 2014, 12:13 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(bennycfw @ May 28 2014, 06:15 PM)
MR1 - Phase 1 and 2 already done this step last year 2013. now is pending completion on whatever which is not yet complete.
*
ooh... i can't remember that. my mistake on that.
jason_chee
post Jun 6 2014, 02:23 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


usually progressive is claim by developer sending invoice / progressive statement to lawyer and lawyer will advise bank to release money. Developer of course want to get the money asap. but before the completed the phase like 2(f) or 2(g) as stated in SnP, they can't simply issue claim. therefore i don't think there will be any interest charges on purchaser.
jason_chee
post Jun 18 2014, 12:55 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(novel87 @ Jun 17 2014, 08:19 PM)
How much is the sub sales price?
*
18x70 should be ranging from 520K-580K. some does put up 620K. u buying or selling?
jason_chee
post Jun 30 2014, 12:14 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


according to Mah Sing, Architect advice VP on 31st July 2014. This mean by the time owner receive the letter, it will be August. IMO, it will be either August or September looking at Hari Raya holiday at end of July.

IMO, the letter just indication of Cheque Bearing name. My SnP has 2 names (mine and my sister in law) but loan under 1 name (sister in law). If the cheque issue under 2 name, then i'll have problem banking in. I help my sister in law to purchase a unit and i can't cancel my name according to Mah Sing rules.

This post has been edited by jason_chee: Jun 30 2014, 12:18 PM
jason_chee
post Jun 30 2014, 12:42 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(koigh @ Jun 30 2014, 12:23 PM)
In that case, the VP should count from Aug/Sep, the day we get the key, right?
It not fair if architect advice on 31st jul but actual date in Aug/Sep. mad.gif
*
not really. CF will be ready early. then Developer will issue VP letter and send to purchaser. by the time purchaser receive the letter, it's 1 or 2 weeks away from VP date. then purchase has to arrange to pay final balance such as advance maintenance fees and etc. Then Clearance Letter will be issue out for purchase to collect the Key. It could be 3 or 4 weeks from Date of VP Letter. Besides, there is LAD involved for Phase 1. So, it's also subject to the settlement of LAD between purchaser and Developer. If Architect Advise 31st July, most likely VP letter will be out on 1st or 2nd week of aug. Purchase will receive the letter 1 week later. It could be 1st Week of September only get key. This is just my 2 cents.

But yes, CF date will be early cos need consent from few authorities before architect advise MS to issue VP Letter.

This post has been edited by jason_chee: Jun 30 2014, 12:43 PM
jason_chee
post Jul 1 2014, 03:00 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


need to check with DMC. If i remember correctly, nothing being mentioned about Guard house. It's Fencing and Guarded. I don't think Guard House is included. Please check back DMC for better understanding cos we, the purchaser, signed it.
jason_chee
post Jul 1 2014, 04:18 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(kekura @ Jul 1 2014, 03:26 PM)
previously, the sales did mention to me that residents need to use access card to enter gate...
*
hmm... not sure about that. But i don't trust what SA said. haha. i check with Lawyer when i sign DMC. I saw a phrase there. best is, cross-check in DMC.
jason_chee
post Jul 1 2014, 08:27 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


I just checked DMC. It stated...

"Guarded Neighbourhood means the scheme of guarded community provided for M Residence, Rawang with the provision of security control services by licensed security officers and the construction of security guard house at the entrance and the exit points at such location deemed appropriate by the developer including but not limited to provision of suhc other services as deemed fit by the developer, and this scheme shall subject always to all rules, regulations, bye-laws or guidelines passed, imposed and/or gazetted by the authority at any time and from time to time."

So, yes, by right Developer has to build Guard House at Entry and Exit. But again developer could argue it's for "M Residence, Rawang" as whole and not specific to Phase 1 only.

This post has been edited by jason_chee: Jul 1 2014, 08:27 PM
jason_chee
post Jul 2 2014, 12:26 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(helmyz85 @ Jul 2 2014, 12:22 PM)
Really need to have the guard house (as well as the guards, of course, with routine patrol) as my house in phase 1 is facing phase 4 (under construction), thus having higher risk of breaking in and entering. Need to really sure it is safe before start moving in my things bit by bit.
*
yes, understood your point. IMO, we can't take for granted on security. we can't rely 100% on security. i believe in securing own unit. put in grill, cctv and alarm as pre-caution.
jason_chee
post Jul 2 2014, 12:54 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(helmyz85 @ Jul 2 2014, 12:36 PM)
True that. However, if no one monitors continuously, the culprit may leisurely take out all the individual units security systems in place. Both individual unit security and overall M Residence security work together here.
*
yup. the first thing have to do is to get MS to build the Guard house. Then only can appoint good security company.
jason_chee
post Jul 2 2014, 02:45 PM

Regular
******
Senior Member
1,559 posts

Joined: Oct 2004


QUOTE(koigh @ Jul 2 2014, 02:22 PM)
In that case, can MS vp without the guard house and fence? Don't want later after vp, they cuci tangan....
*
they can VP without Guard House. if no mistake, fences already up and in placed. I believe they won't cuci tangan. Is phase 1 and phase 4 using same entrance / exit point? If yes, then i think MS will build guard house before VP of Phase 4.

btw, anyone get in touch with MS on guard house issue? Currently we only in "assumption" mode over the guard house. Nothing concrete yet.

This post has been edited by jason_chee: Jul 2 2014, 02:45 PM