QUOTE(pcteck19 @ Mar 5 2012, 10:01 PM)
just visit the site this evening

1. all roads are done, base layer of coz, they gonna lay another layer

2. shower screen installed on master bedroom's toilet

3. installed electrical switch brand is Schneider, Vivace series. although Vivace is the cheapest in Schneider (Vivace < Pieno < Zen celo < Neo), at least not cheapo brand lo....

4. unifi fiber patch cord installed, located at tv panel, where beside tv port and RJ11 port
*
Thanks for the updates!!

Good!! never know that they will installed unifi fiber for us
Neo|ofGeo
post Mar 6 2012, 08:48 AM

Stop Complaining and Read
Group Icon
Elite
3,142 posts

Joined: Nov 2010


QUOTE(ndykh @ Mar 6 2012, 08:44 AM)
Thanks for the updates!!

Good!! never know that they will installed unifi fiber for us
*
Mostly they would do this nowdays
since it last longer then copper technology
actually most of Bandar Kinrara should have optic cable already set up
but since there are complication
there are delayed until this year



btw,
have anyone see the Kinrara Club House nearby Taman Damai Utama?
just saw it a few weeks ago
never knew about it

pcteck19
post Mar 6 2012, 10:11 AM

Getting Started
**
Junior Member
237 posts

Joined: Aug 2006
QUOTE(Neo|ofGeo @ Mar 6 2012, 08:48 AM)
have anyone see the Kinrara Club House nearby Taman Damai Utama?
just saw it a few weeks ago
never knew about it
*
that is private club house for Kinrara Residence
Neo|ofGeo
post Mar 6 2012, 10:28 AM

Stop Complaining and Read
Group Icon
Elite
3,142 posts

Joined: Nov 2010


QUOTE(pcteck19 @ Mar 6 2012, 10:11 AM)
that is private club house for Kinrara Residence
*
quite impressive,
IINM,2million house behind the club house?
3 storey
might be a good place if the lakes nearby become more clear

Immortal
post Mar 6 2012, 10:45 AM

Getting Started
**
Junior Member
221 posts

Joined: Sep 2005


That's a rain water catchment pond....not possible to get clearer water, as the water get cloudy like 'teh'o ' every time it rains....

That's 2 & 3 storey semi-d behind the club house....IINM, priced below 2mil...

This post has been edited by Immortal: Mar 6 2012, 10:48 AM
krgia10
post Mar 9 2012, 09:08 PM

Getting Started
**
Junior Member
183 posts

Joined: Oct 2010
From: 1 Malaysia 2 System 3 Voices
Finally got the copy of Loan Agreement.
pcteck19
post Mar 10 2012, 03:50 PM

Getting Started
**
Junior Member
237 posts

Joined: Aug 2006
QUOTE(krgia10 @ Mar 9 2012, 09:08 PM)
Finally got the copy of Loan Agreement.
*
swan & partners sent it to you? or you request from them?

does the loan doc come with the title (gelan)?
krgia10
post Mar 10 2012, 04:40 PM

Getting Started
**
Junior Member
183 posts

Joined: Oct 2010
From: 1 Malaysia 2 System 3 Voices
QUOTE(pcteck19 @ Mar 10 2012, 03:50 PM)
swan & partners sent it to you? or you request from them?

does the loan doc come with the title (gelan)?
*
Yes, lawyer firm courier it over. Photocopy of Title also come together.
pcteck19
post Mar 10 2012, 07:42 PM

Getting Started
**
Junior Member
237 posts

Joined: Aug 2006
QUOTE(krgia10 @ Mar 10 2012, 04:40 PM)
Yes, lawyer firm courier it over. Photocopy of Title also come together.
*
do we pay for MOT before? i cant recall it already
krgia10
post Mar 10 2012, 07:44 PM

Getting Started
**
Junior Member
183 posts

Joined: Oct 2010
From: 1 Malaysia 2 System 3 Voices
Paid already, a few thousand damage!
twins9
post Mar 10 2012, 08:09 PM

Regular
******
Senior Member
1,371 posts

Joined: Sep 2011
Went to look at the kinrara clubhouse again. The pool looks good, surrounded by a pond. The is a small kiddy pool too. But no showers, lots of nice recliners though. Ladies change room wash basin area looks nice. Only 10 simple lockers, 2 shower/change rooms and 1 toilet! LOL.

On first floor, the gym is really small and cramp for 600?? residents. The lounge and mph are reasonably sized. Top floor - one meeting room.

No other facilities like spa, jacuzzi, sauna, badminton or basketball courts. Rm50 per family is reasonable, I think, for such sparse facilities.


mrkenjiro
post Mar 12 2012, 08:46 PM

Casual
***
Junior Member
396 posts

Joined: Jan 2003


QUOTE(krgia10 @ Mar 10 2012, 07:44 PM)
Paid already, a few thousand damage!
*
Almost 10k man for MOT. Btw I have also received the courier copies.
pcteck19
post Mar 12 2012, 10:15 PM

Getting Started
**
Junior Member
237 posts

Joined: Aug 2006
QUOTE(mrkenjiro @ Mar 12 2012, 08:46 PM)
Almost 10k man for MOT. Btw I have also received the courier copies.
*
now i remember, i paid 10k for MOT before as well

btw, i yet to receive the copies, as now i got business trip in JB
mrkenjiro
post Mar 13 2012, 08:26 AM

Casual
***
Junior Member
396 posts

Joined: Jan 2003


I was informed that the bank just disbursed another 10% for road and drain.
The next milestone is delivery of key (after electricity and water supplied)
krgia10
post Mar 13 2012, 09:06 AM

Getting Started
**
Junior Member
183 posts

Joined: Oct 2010
From: 1 Malaysia 2 System 3 Voices
Me too... just received the letter yesterday. Can't wait for the VP.
pcteck19
post Mar 13 2012, 10:32 AM

Getting Started
**
Junior Member
237 posts

Joined: Aug 2006
QUOTE(mrkenjiro @ Mar 13 2012, 08:26 AM)
I was informed that the bank just disbursed another 10% for road and drain.
The next milestone is delivery of key (after electricity and water supplied)
*
just check my loan account, bank yet to withdraw this 10% for road and drain


Added on March 15, 2012, 12:14 pmtoday only the bank withdraw the 10% for drain & road


Added on March 20, 2012, 8:41 pmvisit the site this evening, meet 1 supervisor who wearing a MS tag, he said phase 2B will be ready on mid/end of April.

as i guess, VP time will be around mid of May

This post has been edited by pcteck19: Mar 20 2012, 08:41 PM
mrkenjiro
post Mar 21 2012, 09:17 AM

Casual
***
Junior Member
396 posts

Joined: Jan 2003


QUOTE(pcteck19 @ Mar 13 2012, 10:32 AM)
just check my loan account, bank yet to withdraw this 10% for road and drain


Added on March 15, 2012, 12:14 pmtoday only the bank withdraw the 10% for drain & road


Added on March 20, 2012, 8:41 pmvisit the site this evening, meet 1 supervisor who wearing a MS tag, he said phase 2B will be ready on mid/end of April.

as i guess, VP time will be around mid of May
*
Happy to hear that.
My only concern is the workmanship since MS rushed to complete the house within the pre-agreed SPA (with MH). MS only took around 1 year to complete what should have been 2.
SKfolk
post Mar 21 2012, 11:07 AM

Enthusiast
*****
Senior Member
928 posts

Joined: Mar 2012
QUOTE(Immortal @ Mar 6 2012, 10:45 AM)
That's a rain water catchment pond....not possible to get clearer water, as the water get cloudy like 'teh'o ' every time it rains....

That's 2 & 3 storey semi-d behind the club house....IINM, priced below 2mil...
*
Good, that means there will be no flood because the developer provide the retention pond.
TSndykh
post Apr 19 2012, 04:13 PM

Getting Started
**
Junior Member
66 posts

Joined: May 2011


has anyone signed and returned back the Letter of consent in relation to Guaraded Neighbourhood Scheme, Kinrara Residence‏?

if you not aware, please call your lawyer & ask them to email u this letter.

thanks.
luvimp
post Apr 19 2012, 05:51 PM

Casual
***
Junior Member
375 posts

Joined: Jul 2008


QUOTE(ndykh @ Apr 19 2012, 04:13 PM)
has anyone signed and returned back the Letter of consent in relation to Guaraded Neighbourhood Scheme, Kinrara Residence‏?

if you not aware, please call your lawyer & ask them to email u this letter.

thanks.
*
Signed the TNB and Syabas application letter and paid the amount for the application.
Returned to Mah Sing.