QUOTE(Lcsx @ Feb 4 2013, 05:38 PM)
Ok seems like they do some design for the hallways. I had some concern on the walkway design being to dull and boring initially.
might be. the walkway in between lift is quite narrow.... EMPIRE CITY @ Damansara Perdana/Mutiara Damansara, Mixed Development Project in Damasara KL
|
|
Feb 4 2013, 06:03 PM
|
![]() ![]()
Junior Member
289 posts Joined: Jan 2003 From: U.S.A |
|
|
|
|
|
|
Feb 5 2013, 09:57 AM
|
![]() ![]()
Junior Member
289 posts Joined: Jan 2003 From: U.S.A |
anyone go make payment today?
|
|
|
Feb 5 2013, 07:14 PM
|
![]() ![]()
Junior Member
55 posts Joined: Nov 2011 |
I am not sure why ED stuff is discussed here but I guess it is related to the same developer.
As to the VP of ED in particular Soho 2, I find it to be a very sloppy way to do the handover. Technically, they can say that the unit is ready but the surrounding environment have not met the safety and health aspect as far as one can see from the visit there. That is to say, the unit is ready, but it is not safe to even get there. Debris can be found over the place and construction is still ongoing in a some ways. For the architect to sign off the VP stage, I think there he has some explanation to do. To Empire, the developer, this would present an opportunity to avoid the late delivery penalty as it is about 36 months from date of SPA. Another observation, is that the units though fully furnished are not furnished yet. Buyers need to coordinate with multiple parties such as TV and Minibar (with an electrical shop), Air con with someone else after VP and god knows whom for the curtains etc etc........ I know many buyers are not too happy over this matter. Good luck!! |
|
|
Feb 5 2013, 07:41 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
7,923 posts Joined: Feb 2007 From: 1 Malaysia |
Wah.. Buyers need to arrange with multiple party
Time consuming |
|
|
Feb 6 2013, 08:54 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,686 posts Joined: Aug 2011 |
QUOTE(1lima @ Feb 5 2013, 07:14 PM) I am not sure why ED stuff is discussed here but I guess it is related to the same developer. Most "pariah" developer for vpAs to the VP of ED in particular Soho 2, I find it to be a very sloppy way to do the handover. Technically, they can say that the unit is ready but the surrounding environment have not met the safety and health aspect as far as one can see from the visit there. That is to say, the unit is ready, but it is not safe to even get there. Debris can be found over the place and construction is still ongoing in a some ways. For the architect to sign off the VP stage, I think there he has some explanation to do. To Empire, the developer, this would present an opportunity to avoid the late delivery penalty as it is about 36 months from date of SPA. Another observation, is that the units though fully furnished are not furnished yet. Buyers need to coordinate with multiple parties such as TV and Minibar (with an electrical shop), Air con with someone else after VP and god knows whom for the curtains etc etc........ I know many buyers are not too happy over this matter. Good luck!! Empire Next Titijaya, magna prima setiawalk also like that but not as bad as the 2 above( but this sort of thing coming from Setia is really disappointing bcoz the big mouth boss always talk about branding) Quite good vp Inp(surprisingly) Good vp Sunway Very " high class" vp Tan & Tan.... Really in a class of its own...every thing siap kau kau until main con also complaint too much work Very professional the person that sell to u have to me the person that also be there during vp( unless resign, may be resign also got to come back Regret : miss garden manor, worth every penny with tan tan branding Both sunway tan & tan after sales service is " top notch" but tan & tan has the " elegant touch" in short ada class But having said that, the pariah category is better than the " no category " ones like Mayland, only god knows when ur unit can vp |
|
|
Feb 6 2013, 10:37 AM
|
![]() ![]()
Junior Member
289 posts Joined: Jan 2003 From: U.S.A |
QUOTE(1lima @ Feb 5 2013, 07:14 PM) I am not sure why ED stuff is discussed here but I guess it is related to the same developer. i already checked with the Lawyer... saying VP based on the "unit" we purchase. by law VP is not related to the main entrace (i wonder how the Architect can stamp and sign off as completed). debris everywhere, Huge steel still can see inside the main entrance which is not cover at all.As to the VP of ED in particular Soho 2, I find it to be a very sloppy way to do the handover. Technically, they can say that the unit is ready but the surrounding environment have not met the safety and health aspect as far as one can see from the visit there. That is to say, the unit is ready, but it is not safe to even get there. Debris can be found over the place and construction is still ongoing in a some ways. For the architect to sign off the VP stage, I think there he has some explanation to do. To Empire, the developer, this would present an opportunity to avoid the late delivery penalty as it is about 36 months from date of SPA. Another observation, is that the units though fully furnished are not furnished yet. Buyers need to coordinate with multiple parties such as TV and Minibar (with an electrical shop), Air con with someone else after VP and god knows whom for the curtains etc etc........ I know many buyers are not too happy over this matter. Good luck!! for me also same thoughts.. they rushing for the 36 months penalty. but i go argue with this, they just smile, and in S&P stated they have the right to issue the VP. question back to the Architect, how they sign off with such kind of condition in the common areas. as latest information, SOHO 1 purchaser might get the reimbursement due to the late delivery . as Master approval plan. the unit must completed on 22nd Feb 2013 (send out VP with approve from Architect) yesterday, site survey, all mattress and sofa already moving in for SOHO 2. brand: GOOD NITE. light green colour for sofa. TV and Fridge need to collect after the settle all the payment by voucher (ESH electrical shop), hearding is the LCD 32inch sharp tv. |
|
|
|
|
|
Feb 6 2013, 11:44 AM
|
![]()
Junior Member
13 posts Joined: Nov 2012 |
QUOTE(1lima @ Feb 5 2013, 07:14 PM) I am not sure why ED stuff is discussed here but I guess it is related to the same developer. hi all buyers,As to the VP of ED in particular Soho 2, I find it to be a very sloppy way to do the handover. Technically, they can say that the unit is ready but the surrounding environment have not met the safety and health aspect as far as one can see from the visit there. That is to say, the unit is ready, but it is not safe to even get there. Debris can be found over the place and construction is still ongoing in a some ways. For the architect to sign off the VP stage, I think there he has some explanation to do. To Empire, the developer, this would present an opportunity to avoid the late delivery penalty as it is about 36 months from date of SPA. Another observation, is that the units though fully furnished are not furnished yet. Buyers need to coordinate with multiple parties such as TV and Minibar (with an electrical shop), Air con with someone else after VP and god knows whom for the curtains etc etc........ I know many buyers are not too happy over this matter. Good luck!! So what do you guys plan to do? Just proceed to pay the balance amount and get the keys? Or you guys will appeal for it by write in to Empire office? |
|
|
Feb 6 2013, 01:26 PM
|
![]() ![]()
Junior Member
289 posts Joined: Jan 2003 From: U.S.A |
QUOTE(Lyner88 @ Feb 6 2013, 11:44 AM) hi all buyers, I already make the payment. inspection on 26th Feb. So what do you guys plan to do? Just proceed to pay the balance amount and get the keys? Or you guys will appeal for it by write in to Empire office? they very confident can get the CCC on end of Feb. |
|
|
Feb 6 2013, 05:19 PM
|
![]()
Junior Member
38 posts Joined: Jul 2012 |
Hi,
Anyone who wish to sell pls PM me, I intend to buy for own stay. Thanks! |
|
|
Feb 6 2013, 09:32 PM
|
![]() ![]()
Junior Member
289 posts Joined: Jan 2003 From: U.S.A |
|
|
|
Feb 6 2013, 09:33 PM
|
![]() ![]()
Junior Member
289 posts Joined: Jan 2003 From: U.S.A |
|
|
|
Feb 6 2013, 11:18 PM
|
![]() ![]()
Junior Member
55 posts Joined: Nov 2011 |
QUOTE(kinx @ Feb 6 2013, 09:33 PM) Architect got balls mah!!! But then again the first VP inspection is 25 Feb, more than a month from their letter dated 20 Jan. Really con buyers of more than a month out of 6 months defect liability. |
|
|
Feb 6 2013, 11:23 PM
|
![]() ![]() ![]()
Junior Member
301 posts Joined: Nov 2012 |
is it really that easy to rent your unit out as there are super many studios units at this area already........ actually i m thinking to get one small unit here for investment but somehow not confident whether can rent out within a short time or not.....
|
|
|
|
|
|
Feb 6 2013, 11:29 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,346 posts Joined: Jul 2009 |
QUOTE(1lima @ Feb 6 2013, 11:18 PM) Architect got balls mah!!! But then again the first VP inspection is 25 Feb, more than a month from their letter dated 20 Jan. Really con buyers of more than a month out of 6 months defect liability. I could not agree more with DT about this developer Anyone has any reply from Architect about how they approved the VP with safety and health issues compromised? |
|
|
Feb 6 2013, 11:30 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,346 posts Joined: Jul 2009 |
QUOTE(iamgoodman @ Feb 6 2013, 11:23 PM) is it really that easy to rent your unit out as there are super many studios units at this area already........ actually i m thinking to get one small unit here for investment but somehow not confident whether can rent out within a short time or not..... Need to take some time lar........ |
|
|
Feb 7 2013, 05:55 AM
|
![]() ![]()
Junior Member
289 posts Joined: Jan 2003 From: U.S.A |
QUOTE(1lima @ Feb 6 2013, 11:18 PM) Architect got balls mah!!! But then again the first VP inspection is 25 Feb, more than a month from their letter dated 20 Jan. Really con buyers of more than a month out of 6 months defect liability. But the today photo with paint[ |
|
|
Feb 7 2013, 03:01 PM
|
![]() ![]()
Junior Member
55 posts Joined: Nov 2011 |
QUOTE(kinx @ Feb 7 2013, 05:55 AM) But the today photo with paint[ They are speeding it up at the expense of 1 month defect liability period. Buyers rugi lar........ Need to pay maintenance some more!! |
|
|
Feb 7 2013, 05:08 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
7,923 posts Joined: Feb 2007 From: 1 Malaysia |
1month defect period only? This standard for all empire projects?
|
|
|
Feb 7 2013, 05:31 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,016 posts Joined: Apr 2006 |
Is this empire city vp or empire damansara vp we are talking about?
|
|
|
Feb 7 2013, 10:37 PM
|
![]() ![]() ![]()
Junior Member
332 posts Joined: Oct 2011 |
QUOTE(airline @ Feb 7 2013, 05:08 PM) I think it is 6 months defect liability. But from the letter of VP to the first inspection date is more than one month apart. So effectively after the inspection the purchaser is left less than 5 months of defect liability. |
|
Topic ClosedOptions
|
| Change to: | 0.0229sec
0.95
6 queries
GZIP Disabled
Time is now: 18th December 2025 - 03:13 PM |