My S&P Dated 30 Dec 09, and stamped on 31 Dec 09
1120 Park Avenue - PJ South, any comments?
1120 Park Avenue - PJ South, any comments?
|
|
Apr 18 2011, 11:32 AM
|
![]() ![]()
Junior Member
119 posts Joined: Feb 2009 |
My S&P Dated 30 Dec 09, and stamped on 31 Dec 09
|
|
|
|
|
|
Apr 18 2011, 11:49 AM
|
![]() ![]() ![]()
Junior Member
439 posts Joined: Jan 2003 |
If they work on weekends and the weather is good, i think can deliver ahead schedule. In deed, seems they work on weekends. Recently weather is not really good and raining.
|
|
|
Apr 18 2011, 09:53 PM
|
![]()
Newbie
1 posts Joined: Apr 2011 |
Hi, I'm new here.
My unit no is B1-11-09 |
|
|
Apr 18 2011, 10:50 PM
|
![]() ![]() ![]()
Junior Member
439 posts Joined: Jan 2003 |
|
|
|
Apr 19 2011, 12:56 AM
|
![]() ![]()
Junior Member
98 posts Joined: Mar 2006 |
|
|
|
Apr 19 2011, 12:57 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,481 posts Joined: Jan 2003 From: Kuala Lumpur |
|
|
|
|
|
|
Apr 20 2011, 03:52 PM
|
![]()
Junior Member
17 posts Joined: Nov 2010 |
Thank you Vincemy for going the extra mile to get those great pictures to us. Isnt it nice to see something different every week, meaning there is real change taking place at the site. By the way, did the workers ask you questions or prevent you from snapping those pictures? Anyway thanks once again.
|
|
|
Apr 20 2011, 06:09 PM
|
![]() ![]()
Junior Member
93 posts Joined: Oct 2010 |
can peter finish the whole 5 block in 2years time? wat i think the building only can done by end of the year 2013
|
|
|
Apr 20 2011, 09:45 PM
|
![]() ![]()
Junior Member
78 posts Joined: May 2010 |
QUOTE(Befair @ Apr 20 2011, 03:52 PM) Thank you Vincemy for going the extra mile to get those great pictures to us. Isnt it nice to see something different every week, meaning there is real change taking place at the site. By the way, did the workers ask you questions or prevent you from snapping those pictures? Anyway thanks once again. You are welcome, Befair. Yes, it is nice to see the project progressing really well every week.I went in & left the site like 'Speedy Gonzales' before the workers realised I was there, haha, just joking. So far, nobody asks or stops me from taking the photos. Actually, I took most of the photos outside the perimeter fence except for some which I took at the main entrance - I wouldn't want to be accused of trespassing and it is also risky to enter without adequate PPE. Cheers! This post has been edited by vincemy: Apr 21 2011, 09:05 AM |
|
|
Apr 21 2011, 10:12 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,481 posts Joined: Jan 2003 From: Kuala Lumpur |
if u keep coming every week, they might think u're one of the contractor or developer lor..
QUOTE(vincemy @ Apr 20 2011, 09:45 PM) You are welcome, Befair. Yes, it is nice to see the project progressing really well every week. I went in & left the site like 'Speedy Gonzales' before the workers realised I was there, haha, just joking. So far, nobody asks or stops me from taking the photos. Actually, I took most of the photos outside the perimeter fence except for some which I took at the main entrance - I wouldn't want to be accused of trespassing and it is also risky to enter without adequate PPE. Cheers! |
|
|
Apr 21 2011, 01:01 PM
|
![]() ![]()
Junior Member
55 posts Joined: Jan 2011 |
QUOTE(cmk96 @ Apr 18 2011, 11:07 AM) Construction is one thing....getting CF is another. Without CF... no keys will be given. Hope the developer don't compromise on quality for speed... Nowadays CF not depend on quality of the building.If really depend on quality,a lot of building in Malaysia cant get CF. CF depend on how much and how fast developer can give $$$$.. haha...this is Malaysia |
|
|
Apr 21 2011, 01:45 PM
|
![]() ![]()
Junior Member
134 posts Joined: Mar 2011 |
by pass 1220 park everyday notice the wall is very thin.
|
|
|
Apr 21 2011, 03:40 PM
|
![]() ![]()
Junior Member
200 posts Joined: Feb 2009 |
QUOTE(kimgary2010 @ Apr 21 2011, 01:01 PM) Nowadays CF not depend on quality of the building. any example CF issued without depend on quality? any proof?If really depend on quality,a lot of building in Malaysia cant get CF. CF depend on how much and how fast developer can give $$$$.. haha...this is Malaysia |
|
|
|
|
|
Apr 21 2011, 07:06 PM
|
![]() ![]()
Junior Member
233 posts Joined: Mar 2006 |
hey guys, is it ibs
industrialized building system, the building build like a lego even the water pipes and wiring is assembled that way confirm very2 hard to install extra plug point |
|
|
Apr 22 2011, 02:15 PM
|
![]() ![]()
Junior Member
78 posts Joined: May 2010 |
QUOTE(AbangCorp @ Apr 21 2011, 07:06 PM) hey guys, is it ibs I don't see any precast concrete walls or columns that were then fitted together like a lego. It is still early stage of constructions and so far only the main structural frames and load-bearing walls up to 1st floor (for T1, T2 & T3) had been erected. As far as I can see, the load-bearing walls were all cast-in-situ and not pre-fabricated. Pre-fabricated columns and walls would have some problems on joints and poor fittings. It may however still be an IBS but more of a hybrid IBS one in which other IBS components such as interlocking precast concrete blocks, pre-fabricated steel & timber roof trusses, drywalls and even bathroom pods may later be used. I am just speculating the aforesaid and anyway I don't think IBS is in anyway inferior to other methods of construction (if done properly and under close supervision). So don't worry about IBS. But you are right - we will find it very very hard to install extra plug points or conceal pipes (for aircon and water) and electrical wiring. Cheersindustrialized building system, the building build like a lego even the water pipes and wiring is assembled that way confirm very2 hard to install extra plug point This post has been edited by vincemy: Apr 22 2011, 03:42 PM |
|
|
Apr 23 2011, 03:32 PM
|
![]() ![]()
Junior Member
93 posts Joined: Oct 2010 |
if there any possible the sunway student will like to stay here since the apartment there quiet old.
|
|
|
Apr 23 2011, 04:46 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
4,973 posts Joined: Dec 2010 |
QUOTE(HUJIUNEN @ Apr 23 2011, 03:32 PM) if there any possible the sunway student will like to stay here since the apartment there quiet old. sunway students wont stay there la, wht u gt at that area??...old rundown shoplots and lots of mat rempit la...sunway students all rich one leh, they will live at bandar sunway or pj there.... |
|
|
Apr 23 2011, 08:11 PM
|
![]() ![]()
Junior Member
78 posts Joined: May 2010 |
Today (23rd April 2011) I snapped some pictures from the usual locations (behind Petronas, main entrance and Pangsapuri Damai Senja) and included a new location behind the row of shop houses along Jalan PJS 1/50.
I am pleasantly surprised that the progress of T4 has actually reached 2nd floor and the 1st floor curtain/partition walls of T3 had been erected. I am now not sure about those pictures which I said in my previous posts that T4 & T5 were slow. I stand corrected. Cheers. Attached thumbnail(s) |
|
|
Apr 23 2011, 11:52 PM
|
![]()
Junior Member
39 posts Joined: Dec 2009 From: Malaysia |
Vincemy, really appreciated your consistent update!
I assume ur picture no.21, 22 & 23 are showing the car park for phase 2 blocks? |
|
|
Apr 24 2011, 12:53 AM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,904 posts Joined: Jul 2007 |
have they settled those old houses where the tower 5 meant to be?
|
|
Topic ClosedOptions
|