Investment THE HERMINGTON @ KUCHAI LAMA | RES. KUCHAIMAS [OT], The Benchmark of Ownership in KL

views
     
pinkdm
post May 18 2018, 10:54 AM

Regular
******
Senior Member
1,039 posts

Joined: Jun 2017


QUOTE(leslauliu @ May 18 2018, 01:58 AM)
I think those buying rumahwip is safe and can be reimbursed under government insurance.

But for hermington, please read my earlier post.
*
Hi, in my opinion:-

for those who are concerned by this "https://www.edgeprop.my/content/1331912/kep...-dbkl-land-sale"

in my opinion, based on the remarks by the MP below, it should be of no worry if the projects ady started or accepted payments from buyer ! - my opinion innocent.gif hmm.gif

"“For RUMAWIP that are already completed [or still under construction], they can still proceed. Those are public housing for the benefit of the people, even though the whole procedure and transaction was wrong. So, let them proceed and complete and let the buyers get their houses.

“What we are talking about is to go after the developers and person involved in this case. And we also want MACC and DBKL to stop those projects that have not started construction, such as the Taman Rimba Kiara project,” he explained."


any comments ??? hmm.gif
JeFf_90
post May 18 2018, 11:00 AM

Getting Started
**
Junior Member
61 posts

Joined: Aug 2008
QUOTE(pinkdm @ May 18 2018, 10:54 AM)
Hi, in my opinion:-

for those who are concerned by this "https://www.edgeprop.my/content/1331912/kep...-dbkl-land-sale"

in my opinion, based on the remarks by the MP below, it should be of no worry if the projects ady started or accepted payments from buyer ! - my opinion  innocent.gif  hmm.gif

"“For RUMAWIP that are already completed [or still under construction], they can still proceed. Those are public housing for the benefit of the people, even though the whole procedure and transaction was wrong. So, let them proceed and complete and let the buyers get their houses.

“What we are talking about is to go after the developers and person involved in this case. And we also want MACC and DBKL to stop those projects that have not started construction, such as the Taman Rimba Kiara project,” he explained."


any comments ??? hmm.gif
*
If they really take action against those developers like AK. For sure their construction will be delayed.
tyenfei
post May 18 2018, 08:10 PM

A Ku La Ma Tata
*******
Senior Member
2,230 posts

Joined: Jan 2006
From: K. L.



Attached Image

Anyone can share knowledge about this?

Can find in link below. Got 2 application. Shd be RumahWip & Hermington


Portal OSC 3.0
http://www.epbt.gov.my/osc/Proj1_Info.cfm?Name=725511&S=S

http://www.epbt.gov.my/osc/Proj1_Info.cfm?Name=713993&S=S
kcwo
post May 19 2018, 08:18 AM

Getting Started
**
Junior Member
93 posts

Joined: Dec 2009
I just got this site progress video from my SA. Looking like pilling work have been started.
Hope everything go smooth for this project. sweat.gif

Just got error to upload the video. But if you pass by NPE you will see it. Wonder when my S&P can be stamped.. hmm.gif

This post has been edited by kcwo: May 19 2018, 08:21 AM
JeFf_90
post May 19 2018, 10:24 AM

Getting Started
**
Junior Member
61 posts

Joined: Aug 2008
QUOTE(kcwo @ May 19 2018, 08:18 AM)
I just got this site progress video from my SA. Looking like pilling work have been started.
Hope everything go smooth for this project. sweat.gif

Just got error to upload the video. But if you pass by NPE you will see it. Wonder when my S&P can be stamped.. hmm.gif
*
Just followed up with my Agent and being told that AK will going sign and stamping by this month..so just wait and see
chie87
post May 19 2018, 12:38 PM

New Member
*
Newbie
4 posts

Joined: Jun 2012


QUOTE(tyenfei @ May 18 2018, 08:10 PM)
Attached Image

Anyone can share knowledge about this?

Can find in link below. Got 2 application. Shd be RumahWip & Hermington
Portal OSC 3.0
http://www.epbt.gov.my/osc/Proj1_Info.cfm?Name=725511&S=S

http://www.epbt.gov.my/osc/Proj1_Info.cfm?Name=713993&S=S
*
IMO, both RUMAWIP and Hermington are within the same development plan. Can see 2 blocks mentioned in each applications.

I found the link below showing the type of Borang code for each type of application
http://www.epbt.gov.my/osc/JMohon_index2.cfm

There are also more different kinds of applications that were approved if u search by Nama Projek: PT 15659 (the lot number)

Attached Image


QUOTE(kcwo @ May 19 2018, 08:18 AM)
I just got this site progress video from my SA. Looking like pilling work have been started.
Hope everything go smooth for this project. sweat.gif

Just got error to upload the video. But if you pass by NPE you will see it. Wonder when my S&P can be stamped.. hmm.gif
*
Photo taken 2 days ago..Although not much ppl working, i can see the excavator and crane operating la..
Attached Image

If the pilling work has started i think can worry less. They got the approval for it based on the record below too.
http://www.epbt.gov.my/osc/Proj1_Info.cfm?Name=713993&S=S

I heard from my friend's friend who work as a consultant in this field (not with this developer) said this project already got the Development Order so is safe to continue the work without any obstructions. Worst case is the developer got fined, unable to pay and file for bankruptcy mega_shok.gif

BTW, Anyone created a whatsapp group for the buyers of this project? Do let me know if there's already one so we can update each other. Or we could PM each others phone number to create 1
JeFf_90
post May 19 2018, 12:55 PM

Getting Started
**
Junior Member
61 posts

Joined: Aug 2008
QUOTE(chie87 @ May 19 2018, 12:38 PM)
IMO, both RUMAWIP and Hermington are within the same development plan. Can see 2 blocks mentioned in each applications.

I found the link below showing the type of Borang code for each type of application
http://www.epbt.gov.my/osc/JMohon_index2.cfm

There are also more different kinds of applications that were approved if u search by Nama Projek: PT 15659 (the lot number)

Attached Image
Photo taken 2 days ago..Although not much ppl working, i can see the excavator and crane operating la..
Attached Image

If the pilling work has started i think can worry less. They got the approval for it based on the record below too.
http://www.epbt.gov.my/osc/Proj1_Info.cfm?Name=713993&S=S

I heard from my friend's friend who work as a consultant in this field (not with this developer) said this project already got the Development Order so is safe to continue the work without any obstructions. Worst case is the developer got fined, unable to pay and file for bankruptcy  mega_shok.gif

BTW, Anyone created a whatsapp group for the buyers of this project? Do let me know if there's already one so we can update each other. Or we could PM each others phone number to create 1
*
Maybe you can be one who create the group ..
maxseng
post May 19 2018, 03:32 PM

New Member
*
Newbie
8 posts

Joined: Aug 2012
QUOTE(JeFf_90 @ May 19 2018, 12:55 PM)
Maybe you can be one who create the group ..
*
Agree, we should have a group to update each other.
I will creata a facebook group for buyer now.
https://www.facebook.com/groups/205377496741412/

I just went to see this morning, still see people working there, hope everything will be fine.

This post has been edited by maxseng: May 19 2018, 03:35 PM
JeFf_90
post May 19 2018, 03:41 PM

Getting Started
**
Junior Member
61 posts

Joined: Aug 2008
QUOTE(maxseng @ May 19 2018, 03:32 PM)
Agree, we should have a group to update each other.
I will creata a facebook group for buyer now.
https://www.facebook.com/groups/205377496741412/

I just went to see this morning, still see people working there, hope everything will be fine.
*
Alright bro..just update here so we can join and update latest news
leslauliu
post May 19 2018, 08:35 PM

Getting Started
**
Junior Member
248 posts

Joined: Apr 2018
QUOTE(pinkdm @ May 18 2018, 10:54 AM)
Hi, in my opinion:-

for those who are concerned by this "https://www.edgeprop.my/content/1331912/kep...-dbkl-land-sale"

in my opinion, based on the remarks by the MP below, it should be of no worry if the projects ady started or accepted payments from buyer ! - my opinion  :innocent:  :hmm:

"“For RUMAWIP that are already completed [or still under construction], they can still proceed. Those are public housing for the benefit of the people, even though the whole procedure and transaction was wrong. So, let them proceed and complete and let the buyers get their houses.

“What we are talking about is to go after the developers and person involved in this case. And we also want MACC and DBKL to stop those projects that have not started construction, such as the Taman Rimba Kiara project,” he explained."


any comments ??? :hmm:
*
For now, anything is possible, let's wait for the announcement. Best if not to pay anything to any developers listed in the probe.

Hope new government can help those buyers in any way.
JeFf_90
post May 22 2018, 08:30 PM

Getting Started
**
Junior Member
61 posts

Joined: Aug 2008
Dropped by on Sunday to have a look. Undergoing pilling process. Sunday not much worker but still moving.
leslauliu
post May 23 2018, 02:33 PM

Getting Started
**
Junior Member
248 posts

Joined: Apr 2018
QUOTE(JeFf_90 @ May 22 2018, 08:30 PM)
Dropped by on Sunday to have a look. Undergoing pilling  process. Sunday not much worker but still moving.
*
Sources said many AK on hold their projects. Most just put little people just to show projects were still on going but for show only.

For hermington cases, if over 900 units building, should at least 200 to 300 worker working.

A group for piling, a group for substructure, a group for forming steel, a group forming formwork, a group pouring concrete and etc
WL9009
post May 23 2018, 03:22 PM

Getting Started
**
Junior Member
193 posts

Joined: Jan 2018


The Hermington still got unit left 20th floor below.
special unit left wor.
edwedw
post May 23 2018, 05:47 PM

Getting Started
**
Junior Member
96 posts

Joined: Dec 2017
Sources... hmm.gif hmm.gif
No offense but appreciate if you can tell us more about AK projects and those is the list from MP Lim. You seems like hate AK a lot from all your recent post tho... sweat.gif

QUOTE(leslauliu @ May 23 2018, 02:33 PM)
Sources said many AK on hold their projects. Most just put little people just to show projects were still on going but for show only.

For hermington cases, if over 900 units building, should at least 200 to 300 worker working.

A group for piling, a group for substructure, a group for forming steel, a group forming formwork, a group pouring concrete and etc
*
JeFf_90
post May 23 2018, 06:13 PM

Getting Started
**
Junior Member
61 posts

Joined: Aug 2008
QUOTE(WL9009 @ May 23 2018, 03:22 PM)
The Hermington still got unit left 20th floor below.
special unit left wor.
*

All is 3A? rclxs0.gif
coolguy99
post May 24 2018, 08:32 AM

Look at all my stars!!
*******
Senior Member
7,356 posts

Joined: Aug 2015



people still dare to buy AK?
pinkdm
post May 24 2018, 11:55 AM

Regular
******
Senior Member
1,039 posts

Joined: Jun 2017


QUOTE(coolguy99 @ May 24 2018, 08:32 AM)
people still dare to buy AK?
*
hi, any buyer go check the site !
if so, mind update here w some photos !? innocent.gif

This post has been edited by pinkdm: May 24 2018, 12:10 PM
leslauliu
post May 24 2018, 04:25 PM

Getting Started
**
Junior Member
248 posts

Joined: Apr 2018
QUOTE(edwedw @ May 23 2018, 05:47 PM)
Sources...  :hmm:  :hmm:
No offense but appreciate if you can tell us more about AK projects and those is the list from MP Lim. You seems like hate AK a lot from all your recent post tho...  :sweat:
*
I dont hate AK personally, just that the developer supposed to correct the agents and lawyers about the shared podium issue.

If you read my previous posts, i was explaining hermington and kuchaimas about shared podium issues after based on my check with ptg and dbkl but many netizens still believed the agents and lawyers.

Then i told them to check with authorities. Luckily now new government and all truth came out.

This post has been edited by leslauliu: May 24 2018, 06:16 PM
leslauliu
post May 24 2018, 07:57 PM

Getting Started
**
Junior Member
248 posts

Joined: Apr 2018
Here is compiled list on 64 land probe which widely circulating now.

This post has been edited by leslauliu: May 24 2018, 08:34 PM


Attached File(s)
Attached File  64_plot__1_.pdf ( 173.11k ) Number of downloads: 315
tyenfei
post May 25 2018, 10:24 AM

A Ku La Ma Tata
*******
Senior Member
2,230 posts

Joined: Jan 2006
From: K. L.



Received this 30 minutes ago. SMS.

Meaning everything shd be on track?

Dear Sir/Madam Kindly collect Sales and Purchase Agreement (unit number) at our office @ No.29-1, Jalan Manis 6,Taman Segar, Cheras 56100 Kuala Lumpur (same row with Maybank Taman Segar). For further enquiry, you may contact us at 03-9130 0015 during weekdays office hours 9am to 5pm.