 Royal Regent Mayland - Buyers : Demand Explanation, Ban them

views
     
TSThenry9999999
post Nov 23 2013, 12:12 AM, updated 12y ago

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
Dear Royal Regent Buyers,

For those Royal Regent Buyers, I think is time now we need to stand together to get Mayland to give the detail explanation : on the progress of this property.

Just received a letter from bank dated : 2013-Nov, in which the disbursement amount is only around 75% of the total loan amount. Therefore the possibilties to get the VP in this year is lower now.

This developer has broken their verbal promises again and again.

It's time to stand together to get them sort out the things out.

This post has been edited by Thenry9999999: Nov 23 2013, 04:42 AM
shinebr8
post Nov 23 2013, 12:13 AM

Enthusiast
*****
Senior Member
875 posts

Joined: Jan 2013
When is contractual vp?
SUStikaram
post Nov 23 2013, 12:32 AM

10k Club
********
All Stars
10,722 posts

Joined: Nov 2011
QUOTE(shinebr8 @ Nov 23 2013, 01:13 AM)
When is contractual vp?
*
2 months ago.
dopeziggy
post Nov 23 2013, 01:34 AM

Getting Started
**
Junior Member
133 posts

Joined: Jul 2013
I passed by the road and it looks like it's completed.
airline
post Nov 24 2013, 03:05 AM

7 stars
*******
Senior Member
7,923 posts

Joined: Feb 2007
From: 1 Malaysia
Can compare with empire damansara

forever1979
post Nov 24 2013, 05:45 AM

Look at all my stars!!
*******
Senior Member
2,854 posts

Joined: Jul 2013


I am not a owner but i think is better than you guys take action only after the project completed.

If normal complains, they just don;t bother.
If wanted to take legal action, then it might affect the working progress on the project.
MrHunter
post Nov 24 2013, 10:29 AM

Enthusiast
*****
Senior Member
740 posts

Joined: Nov 2012
Why bother if u can get LAD from them later. But getting LAD from them is tough. Mayland may jus giv u extra carpark ha.
mybenz
post Nov 24 2013, 11:33 AM

Enthusiast
*****
Senior Member
730 posts

Joined: Feb 2013
This is MayLand ... Good luck buyers
tengster
post Nov 24 2013, 11:45 AM

Look at all my stars!!
*******
Senior Member
5,612 posts

Joined: Jan 2009
QUOTE(MrHunter @ Nov 24 2013, 10:29 AM)
Why bother if u can get LAD from them later. But getting LAD from them is tough. Mayland may jus giv u extra carpark ha.
*
+1

Oh maybe Mayland can give you a nightmare.... Or may get VP by May....
Calculator2013
post Nov 24 2013, 12:12 PM

Regular
******
Senior Member
1,275 posts

Joined: Jul 2013


QUOTE(Thenry9999999 @ Nov 23 2013, 12:12 AM)
Dear Royal Regent Buyers,

For those Royal Regent Buyers, I think is time now we need to stand together to get Mayland to give the detail explanation : on the progress of this property.

Just received a letter from bank dated : 2013-Nov, in which the disbursement amount is only around 75% of the total loan amount. Therefore the possibilties to get the VP in this year is lower now.

This developer has broken their verbal promises again and again.

It's time to stand together to get them sort out the things out.
*
Sorry to hear this news, guys. sad.gif
All the best and good luck!!!

tengster
post Nov 24 2013, 12:29 PM

Look at all my stars!!
*******
Senior Member
5,612 posts

Joined: Jan 2009
Actually delay two months, no need to cowpeh too much.... Looks at a Selayang Spring, one will feel better.
TSThenry9999999
post Nov 24 2013, 03:12 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(tengster @ Nov 24 2013, 12:29 PM)
Actually delay two months, no need to cowpeh too much.... Looks at a Selayang Spring, one will feel better.
*
Anyhow, even is only two months.
Never know how long they will delay!
Based on their track record, it will be worrying.
So, lesson learnt : never ever to buy from them.

This post has been edited by Thenry9999999: Nov 24 2013, 05:18 PM
TSThenry9999999
post Nov 24 2013, 03:58 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(mybenz @ Nov 24 2013, 11:33 AM)
This is MayLand ... Good luck buyers
*
+1
Siao_Lang
post Nov 24 2013, 04:03 PM

Casual
***
Junior Member
454 posts

Joined: Aug 2013
Anybody has any idea what the expected rental for this area once it's completed? wink.gif
TSThenry9999999
post Nov 24 2013, 05:37 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(Siao_Lang @ Nov 24 2013, 04:03 PM)
Anybody has any idea what the expected rental for this area once it's completed? wink.gif
*
Can refer Iproperty : ard Rm 1.5k to Rm 2.5k.

windz1984
post Nov 29 2013, 02:33 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


still no news yet for the VP, another buyer here. Sigh
Fortunekl
post Nov 29 2013, 09:37 PM

Casual
***
Junior Member
376 posts

Joined: Apr 2011
Regalia delay 1.5 year.... This one now only 2 months... Sap sap Sui.....
windz1984
post Nov 29 2013, 10:32 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


sad.gif
For project under DIBS, if after 36 months still not VP, so the interest will be pay by owner or developer? Any sifus got idea?
TSThenry9999999
post Nov 30 2013, 03:03 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(windz1984 @ Nov 29 2013, 02:33 PM)
still no news yet for the VP, another buyer here. Sigh
*
I called them this morning.
Their reply is : call them back in two weeks time.
Only 80% completion.
And the letter is ready to send out for VP, but waiting don't know what the h*ck from their top management.

Spread the words out, and let the world know : this is Mayland

As long as the main entrance in Jln Kuching is not ready, CF won't be ready - liar : saying waiting govt approval.

ecin
post Nov 30 2013, 11:20 AM

location
*******
Senior Member
5,857 posts

Joined: Dec 2010
QUOTE(Fortunekl @ Nov 29 2013, 09:37 PM)
Regalia delay 1.5 year.... This one now only 2 months... Sap sap Sui.....
*
sweat.gif sweat.gif
TSThenry9999999
post Nov 30 2013, 12:33 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(Fortunekl @ Nov 29 2013, 09:37 PM)
Regalia delay 1.5 year.... This one now only 2 months... Sap sap Sui.....
*
delay is not major issues.
They have to give the actual delivery date, so that the buyers can plan ahead : house renting contract renewal, etc.

They really treat their buyers as second class.
windz1984
post Nov 30 2013, 01:04 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


No choice leh, but their project price appreciation quite ok.
Small unit 8xxsf now asking for >600k in I property
Building.Up
post Nov 30 2013, 03:30 PM

Getting Started
**
Junior Member
61 posts

Joined: Nov 2013


I thought the agent told me building will be ready by end of the year n now shock to know that it's around 80% complete only..... Well, I guess with Mayland, anything is possible.... Was shock bout the issue with Dorsett Place Waterfront in subang.
windz1984
post Nov 30 2013, 05:19 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Anyone still interested to buy their future Sri Putramas 4?
froglai88
post Nov 30 2013, 06:15 PM

Casual
***
Junior Member
410 posts

Joined: Aug 2011
From: Well


Many investors still buying ML products despite knowing their track record & workmanship, I guess bcoz of high cap appreciation.. When I bgt my 1st prop from them, some told me don't b surprise if delay vp for up to a yr. But this prop seem to b vp on time in 2014.. Fingers crossed .
windz1984
post Nov 30 2013, 06:25 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(froglai88 @ Nov 30 2013, 06:15 PM)
Many investors still buying ML products despite knowing their track record & workmanship, I guess bcoz of high cap appreciation.. When I bgt my 1st prop from them, some told me don't b surprise if delay vp for up to a yr. But this prop seem to b vp on time in 2014.. Fingers crossed .
*
+1 rclxms.gif
ecin
post Nov 30 2013, 06:30 PM

location
*******
Senior Member
5,857 posts

Joined: Dec 2010
bad symptom of ..
dann wilson
post Nov 30 2013, 06:53 PM

Getting Started
**
Junior Member
139 posts

Joined: Aug 2012
Am puzzled if anyone is still considering them at all.... cool2.gif
pinolam
post Dec 2 2013, 01:56 AM

Getting Started
**
Junior Member
298 posts

Joined: Jan 2003
From: KL
also demand explaination: where the heck is the (forgot how many acre) private jogging track / play ground / garden. and query on the second entrance / exit to the main road. its ridiculous if owner require to passby putramas2 before enter the guardhouse.
pinolam
post Dec 2 2013, 01:58 AM

Getting Started
**
Junior Member
298 posts

Joined: Jan 2003
From: KL
anyway if vp really can sell 600k for 800+sf as in iprop advertised...okla mayland still can be forgiven lol.
femlab
post Dec 2 2013, 02:52 PM

New Member
*
Junior Member
24 posts

Joined: Apr 2011
QUOTE(pinolam @ Dec 2 2013, 01:56 AM)
also demand explaination: where the heck is the (forgot how many acre) private jogging track / play ground / garden. and query on the second entrance / exit to the main road. its ridiculous if owner require to passby putramas2 before enter the guardhouse.
*
Last time when to showroom, SA mention that the jogging track/ playground is NOT private. Dunno if they change it to private, but either way it is still not there.

Currently I am staying in SP2, i believes that once 2nd entrance of SP3 is open to public, traffic will be quite bad since people from dutamas/kepong site will use that road to bypass to bulatan..darn..now morning crawl to u-turn in front of SP1 (morning rush hours) strech all d way to traffic light kuarters kerajan there..
kekura
post Dec 2 2013, 05:00 PM

Casual
***
Junior Member
322 posts

Joined: Jan 2003
Based on my experience with SP2, Mayland will pay the late completion without hassle. Only the calculation is little shorter than the actual, they have their own argument. Whether you want the cash immediately or going to court to settle the actual delay period, Mayland gives you the options.

The playground attracted me. But looking at the condition now, I don't think it will materialize especially since its public.

They have also just put up a big Royal Regalia advertisement poster near the Publika traffic light junction. Guess many units still unsold...
TSThenry9999999
post Dec 2 2013, 06:02 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
The playground attracted me too.
The playground now is : stones and grasses.

Sudahlah, budak ini tahu advertisement saja, buat janji kosong. Mayland memang boleh!

This post has been edited by Thenry9999999: Dec 2 2013, 11:09 PM


Attached thumbnail(s)
Attached Image
kekura
post Dec 4 2013, 09:07 AM

Casual
***
Junior Member
322 posts

Joined: Jan 2003
Suffer a bit only, later MRT Circle Line (Phase 3) is just opposite the Royal Regent then you'll smile again...

This post has been edited by kekura: Dec 4 2013, 09:15 AM
TSThenry9999999
post Dec 4 2013, 09:29 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(kekura @ Dec 4 2013, 09:07 AM)
Suffer a bit only, later MRT Circle Line (Phase 3) is just opposite the Royal Regent then you'll smile again...
*
Hou Sam Lo.
The MRT phase 3 still long way to go.
The phase 1 proposed completion : 2017.
Phase 2 still not coming.
Paris Wong
post Dec 4 2013, 12:11 PM

Getting Started
**
Junior Member
110 posts

Joined: Nov 2013
Mayland good track record??? any sifus here to answer cool.gif cool2.gif
froglai88
post Dec 6 2013, 04:56 AM

Casual
***
Junior Member
410 posts

Joined: Aug 2011
From: Well


QUOTE(Paris Wong @ Dec 4 2013, 02:11 PM)
Mayland good track record??? any sifus here to answer cool.gif  cool2.gif
*
Depend what track record you talking about ? Based on some experienced buyers, for VP on time.. rclxub.gif But for capital appreciation brows.gif

Good luck thumbup.gif

This post has been edited by froglai88: Dec 6 2013, 04:58 AM
pinolam
post Dec 6 2013, 10:33 AM

Getting Started
**
Junior Member
298 posts

Joined: Jan 2003
From: KL
QUOTE(tengster @ Nov 24 2013, 11:45 AM)
+1

Oh maybe Mayland can give you a nightmare.... Or may get VP by May....
*
extra car park? any possible? anyone experience before?

by the way, not just the lanscape park and another road to town is not ready, suspect the "grand lobby" also not seen.
windz1984
post Dec 6 2013, 07:15 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Seems like so many hiccups
TSThenry9999999
post Dec 6 2013, 08:53 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(pinolam @ Dec 6 2013, 10:33 AM)
extra car park? any possible? anyone experience before?

by the way, not just the lanscape park and another road to town is not ready, suspect the "grand lobby" also not seen.
*
Really?
Big shit there.

This post has been edited by Thenry9999999: Dec 9 2013, 08:30 AM
ibwo
post Dec 6 2013, 09:38 PM

Casual
***
Junior Member
306 posts

Joined: Dec 2011
hopefully no leak issues like putramas 1 and 2...
windz1984
post Dec 6 2013, 11:45 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(Thenry9999999 @ Dec 6 2013, 08:53 PM)
Really?
Then maybe VP by May next year.
Big shit there.
*
If that is the case, we purchaser need to serve the interest or still bear by developer? Anyone got idea? rclxub.gif
TSThenry9999999
post Dec 6 2013, 11:54 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(windz1984 @ Dec 6 2013, 11:45 PM)
If that is the case, we purchaser need to serve the interest or still bear by developer? Anyone got idea? rclxub.gif
*
Still bear by developer, I guess.
Bank will call buyer to start pay installment when the disbursement is 100%.
Not receiving any call from Bank yet, better check with your bank.
a6oon
post Dec 8 2013, 08:53 PM

New Member
*
Junior Member
9 posts

Joined: Nov 2013
Hi everyone, considering to purchase a small sub sale unit. Agent asking for 600+ psf. Ok mou?
I've seen their workmanship on SP2.

My concerns are:
- cars parked along roadside SP2
- private park for tenant. Is it true?
- completion date May 2014?
- direct access to Jln Kuching. is it true?

Thank you all in advance.

Koshka
post Dec 9 2013, 01:36 AM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(a6oon @ Dec 8 2013, 08:53 PM)
Hi everyone, considering to purchase a small sub sale unit. Agent asking for 600+ psf. Ok mou?
I've seen their workmanship on SP2.

My concerns are:
- cars parked along roadside SP2
- private park for tenant. Is it true?
- completion date May 2014?
- direct access to Jln Kuching. is it true?

Thank you all in advance.
*
from where u got info about completion date ? May 2014 is still so far sad.gif
a6oon
post Dec 9 2013, 12:54 PM

New Member
*
Junior Member
9 posts

Joined: Nov 2013
Just a wild assumption
May, u get ur land, from MayLand smile.gif

And plus, no sign of the direct access to Jln Kuching which made me think it will be a while more..
TSThenry9999999
post Dec 9 2013, 01:11 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(a6oon @ Dec 9 2013, 12:54 PM)
Just a wild assumption
May, u get ur land, from MayLand smile.gif

And plus, no sign of the direct access to Jln Kuching which made me think it will be a while more..
*
+1
Koshka
post Dec 9 2013, 04:32 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
is there any forum where we can share our concern and thought about royal regent ? If not yet how about we create one ?
I remember royal domain has forum and we buyers discussed all matters related to our property there.
Koshka
post Dec 9 2013, 04:41 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
http://www.flickr.com/photos/73332659@N03/sets/
Here is some recent pictures of Royal Regent i found in open sources.
p.s. Kitchen cabinets looks very cheap. rolleyes.gif

This post has been edited by Koshka: Dec 9 2013, 04:45 PM
ahsoh
post Dec 9 2013, 04:56 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
adil8 is a regular here.
Koshka
post Dec 9 2013, 05:47 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
Well, I'm not a regular here then biggrin.gif )
TSThenry9999999
post Dec 9 2013, 08:03 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(Koshka @ Dec 9 2013, 04:41 PM)
http://www.flickr.com/photos/73332659@N03/sets/
Here is some recent pictures of Royal Regent i found in open sources.
p.s. Kitchen cabinets looks very cheap. rolleyes.gif
*
How to judge expensive or cheap cabinet?
Koshka
post Dec 9 2013, 08:59 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
by outlook perhaps ? thats why i said cabinet "looks" cheap.
sscc
post Dec 12 2013, 09:47 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
Called mayland multiple times, each time they say soon..2 weeks ago, they say late dec or early jan..today, they say before cny..this is frustrating
Koshka
post Dec 12 2013, 11:15 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(sscc @ Dec 12 2013, 09:47 PM)
Called mayland multiple times, each time they say soon..2 weeks ago, they say late dec or early jan..today, they say before cny..this is frustrating
*
May-June next year i think we could get our keys .. Sooner .. don't think so sad.gif
TSThenry9999999
post Dec 13 2013, 01:12 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(sscc @ Dec 12 2013, 09:47 PM)
Called mayland multiple times, each time they say soon..2 weeks ago, they say late dec or early jan..today, they say before cny..this is frustrating
*
Yes. I called them today as well.
And still the same answer : Call them back in two weeks time.

What the heck of this answer?

Is there any buddy there are property agents?
Can share your experience about how to pressure them?
And their answer is waiting government approval, I don't know whether government also have a due date to approve this right?

In fact, I visited Royal Regent project site last weekend. The lobby there still under renovation.
To some extent this Guy - Mayland is a liar, which the actual stopper is themselves, but not government.

a6oon
post Dec 14 2013, 11:16 PM

New Member
*
Junior Member
9 posts

Joined: Nov 2013
Im no expert in housing law. Anyone here have any idea what can be done if developer deliver late?
forever1979
post Dec 15 2013, 07:34 AM

Look at all my stars!!
*******
Senior Member
2,854 posts

Joined: Jul 2013


The developer still have some units yet to sell off. (from their advertisement from newspaper)
That could be trick to delay so that they dont compete with the sub-sale owners ?
airline
post Dec 15 2013, 11:56 AM

7 stars
*******
Senior Member
7,923 posts

Joined: Feb 2007
From: 1 Malaysia
Yup what happened to the access road?
TSThenry9999999
post Dec 17 2013, 12:33 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(airline @ Dec 15 2013, 11:56 AM)
Yup what happened to the access road?
*
Squatters there. Can't build the access.
Heard that got issues to get approval.
a6oon
post Dec 17 2013, 12:35 PM

New Member
*
Junior Member
9 posts

Joined: Nov 2013
QUOTE(Thenry9999999 @ Dec 17 2013, 12:33 AM)
Squatters there. Can't build the access.
Heard that got issues to get approval.
*
I remember same issue for Regalia as well. Big boo-boo on access road. It was on Berita Terkini.
sscc
post Dec 17 2013, 01:44 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(Thenry9999999 @ Dec 17 2013, 12:33 AM)
Squatters there. Can't build the access.
Heard that got issues to get approval.
*
Think it's the access road that's jamming up the ccc..hope it won't be like regalia where it delayed for months
Immortal
post Dec 17 2013, 03:36 PM

Getting Started
**
Junior Member
221 posts

Joined: Sep 2005


QUOTE(pinolam @ Dec 2 2013, 01:56 AM)
also demand explaination: where the heck is the (forgot how many acre) private jogging track / play ground / garden. and query on the second entrance / exit to the main road. its ridiculous if owner require to passby putramas2 before enter the guardhouse.
*
There will be a public 'garden' just outside the condo, on the left before reaching the guard house.

As far as size in concerned, you may expect a quarter acre of green land.
Immortal
post Dec 17 2013, 03:43 PM

Getting Started
**
Junior Member
221 posts

Joined: Sep 2005


QUOTE(pinolam @ Dec 6 2013, 10:33 AM)
extra car park? any possible? anyone experience before?

by the way, not just the lanscape park and another road to town is not ready, suspect the "grand lobby" also not seen.
*
It's very much depend on how you define 'grand'.

If you're talking about the design and material used plus the end result of the overall look, well, I'd say the lobby is outstanding compare to other areas.
pinolam
post Dec 18 2013, 01:09 AM

Getting Started
**
Junior Member
298 posts

Joined: Jan 2003
From: KL
eh somehow i saw they cleaning up the road, the exit is very near to duta/segambut roundabout. the access is visible.
TSThenry9999999
post Dec 18 2013, 11:26 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(pinolam @ Dec 18 2013, 01:09 AM)
eh somehow i saw they cleaning up the road, the exit is very near to duta/segambut roundabout. the access is visible.
*
The cleaned up the road today?
As I know, the access is not yet cleaned up in my recent visits.
windz1984
post Dec 19 2013, 01:11 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Dunno need to wait until when?
TSThenry9999999
post Dec 19 2013, 05:29 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(windz1984 @ Dec 19 2013, 01:11 PM)
Dunno need to wait until when?
*
Only be United, we can bargain with them.
Who wanted to go their office, to seek their explanation?

sscc
post Dec 20 2013, 07:21 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(Thenry9999999 @ Dec 19 2013, 05:29 PM)
Only be United, we can bargain with them.
Who wanted to go their office, to seek their explanation?
*
Called mayland today, they say they are now working towards building the access road. Before CNY, is their latest response.
windz1984
post Dec 20 2013, 09:07 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Any owners received call from property agent asking whether to sell ur unit?
Koshka
post Dec 20 2013, 11:12 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(windz1984 @ Dec 20 2013, 09:07 PM)
Any owners received call from property agent asking whether to sell ur unit?
*
Im having numerous phone calls almost everyday.

This post has been edited by Koshka: Dec 27 2013, 02:09 PM
TSThenry9999999
post Dec 21 2013, 01:02 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(Koshka @ Dec 20 2013, 11:12 PM)
Im having numerous phone calls almost everyday. I not mind to get rid of one or two units but all buyers want to view place before making any deal.
*
For sure la buyers wanted to view first before buy.
TSThenry9999999
post Dec 21 2013, 01:06 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(sscc @ Dec 20 2013, 07:21 PM)
Called mayland today, they say they are now working towards building the access road.  Before CNY, is their latest response.
*
Sigh! What kind of developer is this?
They think buyers are stupid to believe this?
Actually their answer is standard : Next Month.

You can try to call next month : the answer should be February 2014.
When you call on February 2014: the answer maybe is March 2014.

Hopefully they are not referring to before CNY 2015.

This post has been edited by Thenry9999999: Dec 21 2013, 01:07 AM
rumahmurah
post Dec 21 2013, 08:49 AM

Getting Started
**
Junior Member
267 posts

Joined: Aug 2011
Hope no more empty promises after the New Year.
windz1984
post Dec 21 2013, 01:38 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(Koshka @ Dec 20 2013, 11:12 PM)
Im having numerous phone calls almost everyday. I not mind to get rid of one or two units but all buyers want to view place before making any deal.
*
Wow, so laku leh. How is the price offer? Good?
propusers
post Dec 21 2013, 03:58 PM

Look at all my stars!!
*******
Senior Member
2,007 posts

Joined: May 2011
Park51 delay more than half year I think...
Koshka
post Dec 21 2013, 11:47 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(windz1984 @ Dec 21 2013, 01:38 PM)
Wow, so laku leh. How is the price offer? Good?
*
I dont think so ... 460-500 rm per sq/f for now.
Im gonna renovate, possibly furnish, wait till park ready and whack it at 600 rm per sq/f MINIMUM
windz1984
post Dec 22 2013, 06:08 AM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(Koshka @ Dec 21 2013, 11:47 PM)
I dont think so ... 460-500 rm per sq/f for now.
Im gonna renovate, possibly furnish, wait till park ready and whack it at 600 rm per sq/f MINIMUM
*
Serious? 3 years back I bought already RM500psf, still at that price now?
Koshka
post Dec 22 2013, 08:06 AM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(windz1984 @ Dec 22 2013, 06:08 AM)
Serious? 3 years back I bought already RM500psf, still at that price now?
*
my buying price was 408-410 rm per sf

This post has been edited by Koshka: Dec 27 2013, 02:09 PM
TSThenry9999999
post Dec 22 2013, 02:01 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(propusers @ Dec 21 2013, 03:58 PM)
Park51 delay more than half year I think...
*
The landscape park : now a big question mark.
Is there any buyers are with profession as lawyer, property agents/ experts. You all could contribute some ideas on how to put on the pressure to Mr Mayland.

The worry is if they can't build the direct access from Jln Kuching, it will be forever waiting for vp/cf/ccc.

Mr Mayland have to give the answer when they will be granted the approval from Dbkl.

Heard that they are now bring the issues to the court.
How true - don't know!
icemanfx
post Dec 22 2013, 03:48 PM

20k VIP Club
*********
All Stars
21,457 posts

Joined: Jul 2012


QUOTE(pinolam @ Dec 18 2013, 01:09 AM)
eh somehow i saw they cleaning up the road, the exit is very near to duta/segambut roundabout. the access is visible.
*
Access road leading to roundabout is a traffic bottleneck, will create long tailback on Jln Kuching, building a bridge over the railway is a more acceptable solution.

This post has been edited by icemanfx: Dec 22 2013, 03:56 PM
TSThenry9999999
post Dec 22 2013, 11:03 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(icemanfx @ Dec 22 2013, 03:48 PM)
Access road leading to roundabout is a traffic bottleneck, will create long tailback on Jln Kuching, building a bridge over the railway is a more acceptable solution.
*
Agree! But maybe delay one year to get the key.
Don't think Mayland will do that.

Maybe that's the reason they can't get the vp.
The funny thing is : Mayland didn't seek for govt approval before the put their ads around to the public about the new access road. - This is really non-sense.

Why only come to final stage, our Dbkl not grant the approval for the new access?

remyadrian
post Dec 23 2013, 02:56 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


my DIBS expiring d..in my case i have to start paying interest effective 7th jan..how bout the rest of you guys?Attached Image
ecin
post Dec 23 2013, 05:51 PM

location
*******
Senior Member
5,857 posts

Joined: Dec 2010
QUOTE(remyadrian @ Dec 23 2013, 02:56 PM)
my DIBS expiring d..in my case i have to start paying interest effective 7th jan..how bout the rest of you guys?Attached Image
*
whichever is earlier ohmy.gif must claim back full LAD
TSThenry9999999
post Dec 24 2013, 12:42 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(remyadrian @ Dec 23 2013, 02:56 PM)
my DIBS expiring d..in my case i have to start paying interest effective 7th jan..how bout the rest of you guys?Attached Image
*
Nope. Not receiving this.
Mayland a sucks.
TSThenry9999999
post Dec 24 2013, 12:49 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
Called Mayland today. New Vp date is Jan 2014.
No hope to get the key this year, less chance before CNY 2014.


This post has been edited by Thenry9999999: Dec 24 2013, 03:09 PM
TSThenry9999999
post Dec 24 2013, 02:19 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
Latest updates from Mayland : Mayland in the midst of applying temporary CCC/ VP exclusive of the direct access from Jalan Kuching.
Expected to handover the Key on Jan/ Feb 2014.

Direct Access from Jalan Kuching : Got issues with the Squatters there, no one knows when it will be built.

Landscape Park : this land heard that is belong to dbkl. Got issues with the Squatters there, no one knows when it will be built.

Those looking forward to move in before CNY 2014 is now impossible.
Plus and Minus the renovations and defect management from the developer, the earlist we can move in to Royal Regent is April 2014.

Is another third class management showns in our county's property management. Advertisement and Flyers cannot be trusted.
And Govt simply not doing their jobs on this.

Last but not least : They said will compensate for those bought more than 3 years ago.

This post has been edited by Thenry9999999: Dec 24 2013, 02:21 PM
kekura
post Dec 24 2013, 04:11 PM

Casual
***
Junior Member
322 posts

Joined: Jan 2003
Squatters are always problem. the 4 lanes road from Segambut to Mont Kiara upgrade has been delayed for about 10 years because of this issue. Until now only the 4 lanes flyover in front of Taman SPPK Segambut has completed but it just end there, right in front of a river not going anywhere.
sscc
post Dec 26 2013, 09:32 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(Thenry9999999 @ Dec 24 2013, 02:19 PM)
Latest updates from Mayland : Mayland in the midst of applying temporary  CCC/ VP exclusive of the direct access from Jalan Kuching.
Expected to handover the Key on Jan/ Feb 2014.

Direct Access from Jalan Kuching : Got issues with the Squatters there, no one knows when it will be built.

Landscape Park : this land heard that is belong to dbkl. Got issues with the Squatters there, no one knows when it will be built.

Those looking forward to move in before CNY 2014 is now impossible.
Plus and Minus the renovations and defect management from the developer, the earlist we can move in to Royal Regent is April 2014.

Is another third class management showns in our county's property management. Advertisement and Flyers cannot be trusted.
And Govt simply not doing their jobs on this.

Last but not least : They said will compensate for those bought more than 3 years ago.
*
Gosh..the park was the highlight of this property..and there's a possibilty the park won't materialize? This is quite bad news..
TSThenry9999999
post Dec 27 2013, 10:46 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(sscc @ Dec 26 2013, 09:32 PM)
Gosh..the park was the highlight of this property..and there's a possibilty the park won't materialize? This is quite bad news..
*
I think alot of buyers feel the same: without park and without direct access from Jln Kuching. This Royal Regent is nothing but an normal condo.

First of all, Mayland have to bear this : The promises in Ads and Flyers have to materialize.
They cannot blame the Dbkl, meaning Mayland aren't doing their job in right way. If they can't guarantee this, don't it in the ads.

Is there any lawyer buyers there?
Do hope so, you all can provide some advices for furthers steps. As this consider as broken promises from Mayland, let alone they can't deliver on time and compensate the buyers with LAD.
Koshka
post Dec 27 2013, 12:38 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(Thenry9999999 @ Dec 27 2013, 10:46 AM)
I think alot of buyers feel the same: without park and without direct access from Jln Kuching. This Royal Regent is nothing but an normal condo.

First of all, Mayland have to bear this : The promises in Ads and Flyers have to materialize.
They cannot blame the Dbkl, meaning Mayland aren't doing their job in right way. If they can't guarantee this, don't it in the ads.

Is there any lawyer buyers there?
Do hope so, you all can provide some advices for furthers steps. As this consider as broken promises from Mayland, let alone they can't deliver on time and compensate the buyers with LAD.
*
Im in. Lets sue them.

This post has been edited by Koshka: Dec 27 2013, 12:39 PM
TSThenry9999999
post Dec 27 2013, 07:38 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(sscc @ Dec 26 2013, 09:32 PM)
Gosh..the park was the highlight of this property..and there's a possibilty the park won't materialize? This is quite bad news..
*
They said will materialize. But, just don't know when.

Showtime747
post Dec 27 2013, 07:47 PM

Look at all my stars!!
*******
Senior Member
4,258 posts

Joined: Nov 2012
What other project are Mayland doing ?
windz1984
post Dec 28 2013, 12:10 AM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Dorsett Residences Bukit Bintang
windz1984
post Jan 5 2014, 10:31 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Got agent inform me current valuation per square feet range from RM600 to RM620. Dunno how true?
TSThenry9999999
post Jan 5 2014, 10:46 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(windz1984 @ Jan 5 2014, 10:31 PM)
Got agent inform me current valuation per square feet range from RM600 to RM620.  Dunno how true?
*
I think is fair price based on current market value in Jln Kuching/ Jalan Ipoh.

Not be surprise, the Boulevard park Jalan Kuching (near to Sri Putramas) is selling at Rm 500++ psf. Which is much lower spec than Royal Regent.

This post has been edited by Thenry9999999: Jan 5 2014, 10:48 PM
Koshka
post Jan 6 2014, 07:23 AM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(windz1984 @ Jan 5 2014, 10:31 PM)
Got agent inform me current valuation per square feet range from RM600 to RM620.  Dunno how true?
*
it depend on size of ur unit. anything below 800sq/f can fetch that price. bigger units r much less expensive.
davidsoonkk
post Jan 6 2014, 12:16 PM

New Member
*
Junior Member
19 posts

Joined: Dec 2013


QUOTE(windz1984 @ Jan 5 2014, 10:31 PM)
Got agent inform me current valuation per square feet range from RM600 to RM620.  Dunno how true?
*
ya is around that price, I check with bank they say around 580, I plan to sell it at 600. hope can sell it
pinolam
post Jan 6 2014, 01:55 PM

Getting Started
**
Junior Member
298 posts

Joined: Jan 2003
From: KL
a fren called developer, developer say got cf already. after cny can vp. they completing their finishing work. but access to jln kuching still not granted.
Koshka
post Jan 6 2014, 05:12 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(pinolam @ Jan 6 2014, 01:55 PM)
a fren called developer, developer say got cf already. after cny can vp. they completing their finishing work. but access to jln kuching still not granted.
*
Great news ! Gonna keep my fingers cross. flex.gif
TSThenry9999999
post Jan 6 2014, 06:29 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(pinolam @ Jan 6 2014, 01:55 PM)
a fren called developer, developer say got cf already. after cny can vp. they completing their finishing work. but access to jln kuching still not granted.
*
Great news. But also proved that they are not really ready while waiting for the cf.

Not trying to be fussy. Their time management not really up to par, as by right everything should be ready when the cf is issued.

Only now they started to build the landscape park.

No more Mayland in the future.
Koshka
post Jan 6 2014, 09:16 PM

New Member
*
Junior Member
21 posts

Joined: Oct 2009
QUOTE(Thenry9999999 @ Jan 6 2014, 06:29 PM)
Great news. But also proved that they are not really ready while waiting for the cf.

Not trying to be fussy. Their time management not really up to par, as by right everything should be ready when the cf is issued.

Only now they started to build the landscape park.

No more Mayland in the future.
*
They started ?

This post has been edited by Koshka: Jan 6 2014, 09:17 PM
TSThenry9999999
post Jan 6 2014, 09:58 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(Koshka @ Jan 6 2014, 09:16 PM)
They started ?
*
Crane is there to clean up the land. Guess is started.
pinolam
post Jan 7 2014, 12:17 AM

Getting Started
**
Junior Member
298 posts

Joined: Jan 2003
From: KL
QUOTE(Thenry9999999 @ Jan 6 2014, 06:29 PM)
Great news. But also proved that they are not really ready while waiting for the cf.

Not trying to be fussy. Their time management not really up to par, as by right everything should be ready when the cf is issued.

Only now they started to build the landscape park.

No more Mayland in the future.
*
haha dont talk so loud. got fren bought sp1 and complain very much on workmanship say no more mayland. but guess what the appreciation is high and max roi with 10% Discount on dp. after that buy sp2 again and complain late delivery. but sp2 appreciate even more. now buy sp3 and jus keep quiet. after all he just paid 5k and make at least 200k on each MAYLAND sp series.
windz1984
post Jan 7 2014, 12:17 AM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(Thenry9999999 @ Jan 6 2014, 09:58 PM)
Crane is there to clean up the land. Guess is started.
*
Wow..very good news! Looking forward to VP
windz1984
post Jan 7 2014, 12:19 AM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(pinolam @ Jan 7 2014, 12:17 AM)
haha dont talk so loud. got fren bought sp1 and complain very much on workmanship say no more mayland. but guess what the appreciation is high and max roi with 10% Discount on dp. after that buy sp2 again and complain late delivery. but sp2 appreciate even more. now buy sp3 and jus keep quiet. after all he just paid 5k and make at least 200k on each MAYLAND sp series.
*
So lucky your fren, got SP1 to SP3 collection. Most probably with SP4 too in future. Haha whistling.gif
Helius
post Jan 7 2014, 12:29 AM

Regular
******
Senior Member
1,423 posts

Joined: Aug 2012
From: Kuala Lumpur


When VP is expected?
BAWOTP2012
post Jan 8 2014, 10:56 PM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(Helius @ Jan 7 2014, 12:29 AM)
When VP is expected?
*
If you believe ML, it should be this month - January 2014. Well, that what ML said in a newspaper advertisement. Personally, I don't believe ML. It also advertised that Cheras Sentral would be opened for business by November 2013 but it never did. Instead, only a handful of shops (foods) opened in mid December 2013 and >70% of the interior of the mall still not completed. icon_rolleyes.gif

This post has been edited by BAWOTP2012: Jan 8 2014, 10:58 PM
pinolam
post Jan 9 2014, 10:47 AM

Getting Started
**
Junior Member
298 posts

Joined: Jan 2003
From: KL
QUOTE(windz1984 @ Jan 7 2014, 12:19 AM)
So lucky your fren, got SP1 to SP3 collection. Most probably with SP4 too in future. Haha whistling.gif
*
yeah quite lucky though. he bought sp2 230k and sold last year 580k. bought sp3 with 10% standard discount 2% early bird 1% repeat buyer = 13% discount. just rm5000 booking and refundable upon vp. sp4? hmm not sure if his loan still can approve blink.gif
AaIto
post Jan 9 2014, 10:55 AM

Getting Started
**
Junior Member
202 posts

Joined: Jul 2011
QUOTE(Thenry9999999 @ Jan 6 2014, 06:29 PM)
Great news. But also proved that they are not really ready while waiting for the cf.

Not trying to be fussy. Their time management not really up to par, as by right everything should be ready when the cf is issued.

Only now they started to build the landscape park.

No more Mayland in the future.
*
I almost bought from Mayland. Royal Regent. Luckily loan din get thru.... Phew!!!!
JamesPond
post Jan 9 2014, 10:55 AM

Look at all my stars!!
*******
Senior Member
4,526 posts

Joined: Mar 2006
what is SP1?
twilight81
post Jan 9 2014, 11:07 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(AaIto @ Jan 9 2014, 10:55 AM)
I almost bought from Mayland. Royal Regent. Luckily loan din get thru.... Phew!!!!
*
shocking.gif Well... maybe u can call that lucky... but u cant denied that ROI from every SP series by Mayland make the buyers fat fat.... its not because of Mayland good reputation but its because they hold the strategic land.... So u can call them watever u wan and curse them to hell... but u also happy of the return of investment when u sell ur unit later on... I guess this is a kind of love/hate relationship rclxub.gif

Anyway... I personally feel lucky that my loan get approved... I plan to rent it out or keep it for own stay for another 2 years... after that when no more RPGT.... I will sell it... who knows how much i can gain by then... thumbup.gif thumbup.gif

Thank You Mayland for make me pocket fat ya... hope ur workmanship is not that bad sad.gif
AaIto
post Jan 9 2014, 11:33 AM

Getting Started
**
Junior Member
202 posts

Joined: Jul 2011
QUOTE(twilight81 @ Jan 9 2014, 11:07 AM)
shocking.gif  Well... maybe u can call that lucky... but u cant denied that ROI from every SP series by Mayland make the buyers fat fat.... its not because of Mayland good reputation but its because they hold the strategic land.... So u can call them watever u wan and curse them to hell... but u also happy of the return of investment when u sell ur unit later on... I guess this is a kind of love/hate relationship  rclxub.gif

Anyway... I personally feel lucky that my loan get approved... I plan to rent it out or keep it for own stay for another 2 years... after that when no more RPGT.... I will sell it... who knows how much i can gain by then...  thumbup.gif  thumbup.gif

Thank You Mayland for make me pocket fat ya... hope ur workmanship is not that bad sad.gif
*
Agreed totally. Its just the buying process, delay and workmanship thats attempting to kill the interests...., if buyer can bear, Mayland stil bring fat pft.... nod.gif
Glcotan
post Jan 9 2014, 11:46 AM


*******
Senior Member
3,334 posts

Joined: Mar 2011
QUOTE(JamesPond @ Jan 9 2014, 10:55 AM)
what is SP1?
*
sri putramas
Building.Up
post Jan 9 2014, 12:15 PM

Getting Started
**
Junior Member
61 posts

Joined: Nov 2013


QUOTE(twilight81 @ Jan 9 2014, 12:07 PM)
shocking.gif  Well... maybe u can call that lucky... but u cant denied that ROI from every SP series by Mayland make the buyers fat fat.... its not because of Mayland good reputation but its because they hold the strategic land.... So u can call them watever u wan and curse them to hell... but u also happy of the return of investment when u sell ur unit later on... I guess this is a kind of love/hate relationship  rclxub.gif

Anyway... I personally feel lucky that my loan get approved... I plan to rent it out or keep it for own stay for another 2 years... after that when no more RPGT.... I will sell it... who knows how much i can gain by then...  thumbup.gif  thumbup.gif

Thank You Mayland for make me pocket fat ya... hope ur workmanship is not that bad sad.gif
*
The developer may not be the best but the location is very strategic indeed. no matter how bad the reputation of the developer is , the property value will still go up as I believe there will be a lot of demand for it. Initial buyers would have benefited as the property price here have increase a lot from the original purchase price. Will only just continue to go up in coming years.... congrats to those that have bought the property earlier and don't worry too much bout the delay as the developer have a good track record in late delivery.
TSThenry9999999
post Jan 9 2014, 02:02 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(Building.Up @ Jan 9 2014, 12:15 PM)
The developer may not be the best but the location is very strategic indeed. no matter how bad the reputation of the developer is , the property value will still go up as I believe there will be a lot of demand for it. Initial buyers would have benefited as the property price here have increase a lot from the original purchase price. Will only just continue to go up in coming years....  congrats to those that have bought the property earlier and don't worry too much bout the delay as the developer have a good track record in late delivery.
*
Actually it's depends.
For investment purposes : +1
For location : +1

But in general KL property has increased since 2008.
I'm not agree that only Mayland property will make you rich. Rivercity, Sang Suria, etc also increases the same time as Sp1, Sp2.

You still have also much other choices in Jln Ipoh, Sentul, Dutamas.
twilight81
post Jan 10 2014, 03:11 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(Thenry9999999 @ Jan 9 2014, 02:02 PM)
Actually it's depends.
For investment purposes : +1
For location : +1

But in general KL property has increased since 2008.
I'm not agree that only Mayland property will make you rich. Rivercity, Sang Suria, etc also increases the same time as Sp1, Sp2.

You still have also much other choices in Jln Ipoh, Sentul, Dutamas.
*
Actually what Bro Building.Up and I mean is SP series will make the buyers rich... I didnt say only Mayland developer will make the buyers rich... I understand that there are few other choices.... SP series have the advantages just purely because of its strategic locations... nothing more... Yes the developer is sucks but atleast they provide the end result nonetheless... I dont know whats the market rate now as I dont plan to sell it rite away... thats why I am not angry or frustrated at all when it was delayed... I just hope they dont deliver a crappy workmanship at the end of the day.

I actually have good feeling for Royal regent... based on some of the latest photo and comment on those who been there... the workmanship is rather good compare to their previous development... just keep my finger cross and hope for the best rolleyes.gif
kekura
post Jan 10 2014, 04:15 PM

Casual
***
Junior Member
322 posts

Joined: Jan 2003
I have been staying at SP2 and I'm not sure where the statement 'bad workmanship' comes from. For SP1 yes, but for SP2 I totally disagreed.

There were some minor defects during VP but after submitted defect list, they fixed everything in no time. After that, my unit was perfect with absolutely zero defect.

To me SP series has the best location because its in the middle of DUKE, PLUS and SPRINT entry point. It also has easy access because beside the main road (Jalan Kuching). So during peak hour, the residents don't need to waste 15-30min just to get out from Dutamas area to Jalan Kuching.

The downside is it uses Jalan Kuching address instead of Dutamas, hence Dutamas properties are easier to get popular.
twilight81
post Jan 10 2014, 04:47 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(kekura @ Jan 10 2014, 04:15 PM)
I have been staying at SP2 and I'm not sure where the statement 'bad workmanship' comes from. For SP1 yes, but for SP2 I totally disagreed.

There were some minor defects during VP but after submitted defect list, they fixed everything in no time. After that, my unit was perfect with absolutely zero defect.

To me SP series has the best location because its in the middle of DUKE, PLUS and SPRINT entry point. It also has easy access because beside the main road (Jalan Kuching). So during peak hour, the residents don't need to waste 15-30min just to get out from Dutamas area to Jalan Kuching.

The downside is it uses Jalan Kuching address instead of Dutamas, hence Dutamas properties are easier to get popular.
*
And I heard they try to improved their reputation, thats why they put a lot of effort on Royal Regent... I guess we are the lucky one?? hmm.gif
TSThenry9999999
post Jan 11 2014, 09:31 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
Good news. ML start planting the grass, and developing the landscape park. Hopefully the park is ready when they handover the key
windz1984
post Jan 13 2014, 08:35 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Wow, really received alots of call from agents asking want to sell
TSThenry9999999
post Jan 13 2014, 09:10 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(windz1984 @ Jan 13 2014, 08:35 PM)
Wow, really received alots of call from agents asking want to sell
*
so hot! Good.
windz1984
post Jan 14 2014, 01:45 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(Thenry9999999 @ Jan 13 2014, 09:10 PM)
so hot! Good.
*
Looking to rent out first, perhaps wait until RPGT expire first only consider sell
hasec
post Jan 14 2014, 02:02 PM

Getting Started
**
Junior Member
202 posts

Joined: Dec 2012
One simple advice, never buy from Empire and Maryland
windz1984
post Jan 14 2014, 09:53 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(hasec @ Jan 14 2014, 02:02 PM)
One simple advice, never buy from Empire and Maryland
*
Yaya, thks for your advice
TSThenry9999999
post Jan 14 2014, 11:57 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(hasec @ Jan 14 2014, 02:02 PM)
One simple advice, never buy from Empire and Maryland
*
Mayland has the track record of late delivery : but no action from our govt.
At the end, buyers bear the consequences.
Is the increase of rpgt can help to improve the workmanship, on time delivery?




This post has been edited by Thenry9999999: Jan 15 2014, 12:08 AM
twilight81
post Jan 15 2014, 10:52 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(Thenry9999999 @ Jan 14 2014, 11:57 PM)
Mayland has the track record of late delivery : but no action from our govt.
At the end, buyers bear the consequences.
Is the increase of rpgt can help to improve the workmanship, on time delivery?
*
RPGT only benefit the government leh... wont improve shit....
twilight81
post Jan 15 2014, 10:54 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(hasec @ Jan 14 2014, 02:02 PM)
One simple advice, never buy from Empire and Maryland
*
yayaya...really thanks for ur simple advised rclxms.gif
but I only eat fried chicken Maryland.... never heard a developer call Maryland before... icon_idea.gif
Sorry for being sarcastic... notworthy.gif
TSThenry9999999
post Jan 15 2014, 06:31 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(twilight81 @ Jan 15 2014, 10:52 AM)
RPGT only benefit the government leh... wont improve shit....
*
Yeah, that's reason there alot of shit developers in Malaysia. Buy at your own risk.
windz1984
post Jan 16 2014, 08:50 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Anyone start instalment already?
BAWOTP2012
post Jan 17 2014, 10:13 PM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(windz1984 @ Jan 16 2014, 08:50 PM)
Anyone start instalment already?
*
Better to jump ship to this thread on Royal Regent:

https://forum.lowyat.net/index.php?showtopi...hl=royal+regent

No. I haven't heard from ML as yet but no hurry as my DIBS still have 2 yrs to go. rolleyes.gif
twilight81
post Jan 18 2014, 05:01 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
Guys,
I received the VP letter de... but they date it at 31/12/2013 and below they write a statement stated that they wont entertain any complain defect of our unit after 14 days of the VP letter issuance date... now already 18/1/2014... Can they do that? This is really unbelievable... anyone of u received the letter sooner?
windz1984
post Jan 18 2014, 05:27 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(twilight81 @ Jan 18 2014, 05:01 PM)
Guys,
I received the VP letter de... but they date it at 31/12/2013 and below they write a statement stated that they wont entertain any complain defect of our unit after 14 days of the VP letter issuance date... now already 18/1/2014... Can they do that? This is really unbelievable... anyone of u received the letter sooner?
*
Not received yet leh, how can they do that? Need to give people's time to check defects leh
kekura
post Jan 18 2014, 05:34 PM

Casual
***
Junior Member
322 posts

Joined: Jan 2003
Defects should be under warranty. They must entertain, cannot say no. SP2 was given 18 mths warranty, anytime can submit defect.
rumahmurah
post Jan 18 2014, 06:26 PM

Getting Started
**
Junior Member
267 posts

Joined: Aug 2011
Defect liability period..... Refer to yor SPA.

This post has been edited by rumahmurah: Jan 18 2014, 06:31 PM
sscc
post Jan 18 2014, 08:19 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(twilight81 @ Jan 18 2014, 05:01 PM)
Guys,
I received the VP letter de... but they date it at 31/12/2013 and below they write a statement stated that they wont entertain any complain defect of our unit after 14 days of the VP letter issuance date... now already 18/1/2014... Can they do that? This is really unbelievable... anyone of u received the letter sooner?
*
Yeah. Envelope was dated 14 Jan 2014 by Pos Malaysia. There's no way they can assume we received delivery of possession already when we just received the letter of notice
BAWOTP2012
post Jan 19 2014, 11:54 PM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(sscc @ Jan 18 2014, 08:19 PM)
Yeah.  Envelope was dated 14 Jan 2014 by Pos Malaysia.  There's no way they can assume we received delivery of possession already when we just received the letter of notice
*
Warranty = defect liability period. The 14-day deadline is invalid in law. You can claim warranty even on the day before the defect liability period expires. I think this is more on LAD calculation which ends on the date of VP. Keep your envelop safely. You may need it at the Tribunal later. vmad.gif
ahsoh
post Jan 20 2014, 10:11 AM

Casual
***
Junior Member
471 posts

Joined: May 2010
Received the letter too. Call Mayland this morning but they told me I cant get the key now as my bank havent release the last payment to them, then I call my banker and was told Mayland lawyer havent even sent letter to bank to ask for payment. Probably every buyers have to wait til after CNY holiday. By then, definitely over 14 days period.
mIssfROGY
post Jan 20 2014, 10:15 AM

Look at all my stars!!
*******
Senior Member
2,155 posts

Joined: May 2005


ya mayland quite evil in this way....and everyway...after u get your units and any complains on your condo environment, structure, etc etc...they will taichi here n there...end up no news and gone with the wind...

But if unit got problem they still fix la...at least for my case is ok but then again my unit wasnt giving me much problem anyway....just small stuffs....

and this is mayland la....but good thing is their props quite hot ...haha sigh...

This post has been edited by mIssfROGY: Jan 20 2014, 10:17 AM
twilight81
post Jan 20 2014, 10:30 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
Guys,
So do we need to start to service the installment for the month of January? Since we cant get the Key yet, we suppose to skip this month of installment rite? I think they try to avoid another month of bank interest by date the letter as 31/12/2013.... very evil thought in deed... Can we counter this issues? Cause as I know bank interest for the month of January is not settle yet...
windz1984
post Jan 20 2014, 10:44 AM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(mIssfROGY @ Jan 20 2014, 10:15 AM)
ya mayland quite evil in this way....and everyway...after u get your units and any complains on your condo environment, structure, etc etc...they will taichi here n there...end up no news  and gone with the wind...

But if unit got problem they still fix la...at least for my case is ok but then again my unit wasnt giving me much problem anyway....just small stuffs....

and this is mayland la....but good thing is their props quite hot ...haha sigh...
*
Bro, you viewed your unit already? How to go in?

twilight81
post Jan 20 2014, 11:12 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
They dont even allowed us to go in unless we settle all the loan and payment... I call Mayland this morning... they say once all payment is settle only call them for a clearance letter... worse part is we need start pay bank progressing interest start January no matter wat... so if the bank late realease the final loan amount... we need to keep on pay interest even we didnt get the key yet... money wasted...
mIssfROGY
post Jan 20 2014, 11:40 AM

Look at all my stars!!
*******
Senior Member
2,155 posts

Joined: May 2005


QUOTE(windz1984 @ Jan 20 2014, 10:44 AM)
Bro, you viewed your unit already? How to go in?
*
no la...mine is putramas2. i m just sharing my experience with mayland..other than that its a nice place to live smile.gif
n the view at nite dem nice so enjoy!!
mIssfROGY
post Jan 20 2014, 11:50 AM

Look at all my stars!!
*******
Senior Member
2,155 posts

Joined: May 2005


QUOTE(twilight81 @ Jan 20 2014, 10:30 AM)
Guys,
So do we need to start to service the installment for the month of January? Since we cant get the Key yet, we suppose to skip this month of installment rite? I think they try to avoid another month of bank interest by date the letter as 31/12/2013.... very evil thought in deed... Can we counter this issues? Cause as I know bank interest for the month of January is not settle yet...
*
bank interest need to pay....bank is bank, developer is developer..(unless this is dibs??)

mIssfROGY
post Jan 20 2014, 11:53 AM

Look at all my stars!!
*******
Senior Member
2,155 posts

Joined: May 2005


QUOTE(ahsoh @ Jan 20 2014, 10:11 AM)
Received the letter too. Call Mayland this morning but they told me I cant get the key now as my bank havent release the last payment to them, then I call my banker and was told Mayland lawyer havent even sent letter to bank to ask for payment. Probably every buyers have to wait til after CNY holiday. By then, definitely over 14 days period.
*
the last time mayland did this to me......really farked up!!
MAYLAND charged me interest for their mistakes (bank mlate payment to them) and didnt wanna waive it off summore...
but in the end i paid up coz they didnt wanna release my keys if i dun pay up....argh!
i will never forget this hate and love relationship with them ever nod.gif
ahsoh
post Jan 20 2014, 04:19 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
The maintenance is suppose to be 0.30psf right? Why they bill me 0.35/psf?
ahsoh
post Jan 20 2014, 04:20 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
Can other buyers confirm please? I remember 0.30/psf.
twilight81
post Jan 20 2014, 04:38 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
I feel been rip off... actually I call and say its not fair that they put VP at 31/12 but letter arrived at 18/1 but they say it does not matter...its based on the VP date... I was like WTF...but no point argue with the small potatoes answering the phone cause they are told wat to say to us anyway... so I feel there is no point argue.... same goes to the maintenance fees... I feel they will just answer us based on the script given to them...
ahsoh
post Jan 20 2014, 04:44 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
Ya, they told me they are the account dept, they only wanna make sure that we pay all the bill before we can get the keys. If I'm not happy can complain to the maintenance office later. WTF!
twilight81
post Jan 20 2014, 05:19 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
ahsoh, did ur bank make all the necessary payment?
ahsoh
post Jan 20 2014, 05:22 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
yes but still haven't release the last payment as Mayland lawyer haven't issue any advice to them.
twilight81
post Jan 20 2014, 05:26 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
thats the funny thing...and they even dare to put the VP date as 31/12/2013... really unbelievable!!
windz1984
post Jan 20 2014, 06:21 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(twilight81 @ Jan 20 2014, 05:26 PM)
thats the funny thing...and they even dare to put the VP date as 31/12/2013... really unbelievable!!
*
Twilight bro, so how much we need to pay them in order to get the key?
Helius
post Jan 21 2014, 09:10 AM

Regular
******
Senior Member
1,423 posts

Joined: Aug 2012
From: Kuala Lumpur


QUOTE(ahsoh @ Jan 20 2014, 04:19 PM)
The maintenance is suppose to be 0.30psf right? Why they bill me 0.35/psf?
*
30 cents is maintenance fee excluding the sinking fund...
twilight81
post Jan 21 2014, 10:40 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(windz1984 @ Jan 20 2014, 06:21 PM)
Twilight bro, so how much we need to pay them in order to get the key?
*
Excluding the amount owe from the bank... i think we need to fork out around 2k ++ depending on the size of ur unit... cause need 4 months advance maintenance and sinking fund payment plus all the miscellaneous payment... correct me if I am wrong...
Helius
post Jan 21 2014, 11:12 AM

Regular
******
Senior Member
1,423 posts

Joined: Aug 2012
From: Kuala Lumpur


QUOTE(twilight81 @ Jan 21 2014, 10:40 AM)
Excluding the amount owe from the bank... i think we need to fork out around 2k ++ depending on the size of ur unit... cause need 4 months advance maintenance and sinking fund payment plus all the miscellaneous payment... correct me if I am wrong...
*
You are right...
ahsoh
post Jan 21 2014, 12:27 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
QUOTE(Helius @ Jan 21 2014, 09:10 AM)
30 cents is maintenance fee excluding the sinking fund...
*
Their bill 0.32 + sinking fund 0.03 = 0.35
sscc
post Jan 21 2014, 12:35 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(ahsoh @ Jan 21 2014, 12:27 PM)
Their bill 0.32 + sinking fund 0.03 = 0.35
*
Correct. That's the same for me
windz1984
post Jan 21 2014, 05:47 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(twilight81 @ Jan 21 2014, 10:40 AM)
Excluding the amount owe from the bank... i think we need to fork out around 2k ++ depending on the size of ur unit... cause need 4 months advance maintenance and sinking fund payment plus all the miscellaneous payment... correct me if I am wrong...
*
But last time we paid RM5,000 during booking, the SA told that sum of money can treat as advance maintenance fees..
pinolam
post Jan 22 2014, 04:03 PM

Getting Started
**
Junior Member
298 posts

Joined: Jan 2003
From: KL
QUOTE(windz1984 @ Jan 21 2014, 05:47 PM)
But last time we paid RM5,000 during booking, the SA told that sum of money can treat as advance maintenance fees..
*
yes. still valid.
remyadrian
post Jan 22 2014, 11:24 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


I've received the letter too..what rubbish 14 days when clearly stated there on the envelope stamped by pos malaysia the date is 16th jan..but the letter by mayland is dated 31 dec..con ppl..I bet it's one of their tricks put that date but purposely send out the letter late so it will past the 14 days period by the time all of us receive the letter..so anyone has any luck settling the payments n getting their keys yet?would be nice if someone can share their progressive experience from getting the letter of VP to getting their keys..cheers guys!
BAWOTP2012
post Jan 23 2014, 12:30 AM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(remyadrian @ Jan 22 2014, 11:24 PM)
I've received the letter too..what rubbish 14 days when clearly stated there on the envelope stamped by pos malaysia the date is 16th jan..but the letter by mayland is dated 31 dec..con ppl..I bet it's one of their tricks put that date but purposely send out the letter late so it will past the 14 days period by the time all of us receive the letter..so anyone has any luck settling the payments n getting their keys yet?would be nice if someone can share their progressive experience from getting the letter of VP to getting their keys..cheers guys!
*
Looks like everyone is in the same boat - letter dd 31/12/13 but post marked 16/1/2014 and received 20/1/2014. We should follow Windsor Tower owners example to take class action against ML - after dust settled down. Were you charged a huge late payment interest? I am charged closed to $7,000 from nowhere as the statement of account shows no outstanding sum since Oct 2013. rclxub.gif
sscc
post Jan 23 2014, 09:31 AM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(BAWOTP2012 @ Jan 23 2014, 12:30 AM)
Looks like everyone is in the same boat - letter dd 31/12/13 but post marked 16/1/2014 and received 20/1/2014. We should follow Windsor Tower owners example to take class action against ML - after dust settled down.  Were you charged a huge late payment interest? I am charged closed to $7,000 from nowhere as the statement of account shows no outstanding sum since Oct 2013. rclxub.gif
*
Yes. Was also charged late payment interest, of which we have already complained back in 2011 when it first happened. Plus, it was not even our mistake that the payment was late.
Now just waiting for the bank to disburse the remaining balance. Hopefully this can be settled before CNY.
twilight81
post Jan 23 2014, 10:47 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
Yes... I was charge for late payment interest too...which I already make complain... but they dont care and deduct the interest from my 5K booking fees anyway... cause from the letter they sent me, I can clearly see my 5K gets deduct till 3k ++ from all the miscellaneous charges and the late payment charges.... they dont give a damn to all our complain actually... My guess is if we wanna charge them for LAD payment or ask for the release of our 5K booking deposit, they will drag until end of the world... but when they wan their money, "GIVE IT or no Key" policy.... its a classic chinaman company... they wont afraid of us unless we join together to form a committee and hire a lawyer or something to F**KING sue them!!!
twilight81
post Jan 23 2014, 10:52 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(BAWOTP2012 @ Jan 23 2014, 12:30 AM)
Looks like everyone is in the same boat - letter dd 31/12/13 but post marked 16/1/2014 and received 20/1/2014. We should follow Windsor Tower owners example to take class action against ML - after dust settled down.  Were you charged a huge late payment interest? I am charged closed to $7,000 from nowhere as the statement of account shows no outstanding sum since Oct 2013. rclxub.gif
*
Bro,
7K is a lot man... its the letter stated wat kind of charges they wan from u that can accumulate to 7K?? I think u better check properly before make any payment... and better do it fast as they wont release the key to u unless u clear all payment... bear in mind that we will start the installment on january which is already end of the month now...and we still not have the key and bank still not received the letter from the developer!!!
windz1984
post Jan 23 2014, 12:16 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(twilight81 @ Jan 23 2014, 10:47 AM)
Yes... I was charge for late payment interest too...which I already make complain... but they dont care and deduct the interest from my 5K booking fees anyway... cause from the letter they sent me, I can clearly see my 5K gets deduct till 3k ++ from all the miscellaneous charges and the late payment charges.... they dont give a damn to all our complain actually... My guess is if we wanna charge them for LAD payment or ask for the release of our 5K booking deposit, they will drag until end of the world... but when they wan their money, "GIVE IT or no Key" policy.... its a classic chinaman company... they wont afraid of us unless we join together to form a committee and hire a lawyer or something to F**KING sue them!!!
*
Why got late payment interest? This project is under DIBS mah. I thought only when we got the key then only start instalment? rclxub.gif
sscc
post Jan 23 2014, 12:54 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(windz1984 @ Jan 23 2014, 12:16 PM)
Why got late payment interest? This project is under DIBS mah. I thought only when we got the key then only start instalment? rclxub.gif
*
They are charging interest on late payment from bank in making the disbursement to mayland.
Just a question, this month's progressive interest is ours to pay? Coz I've checked with the bank and mayland has not cleared it yet. So, now considered VP or not? Quite blur now.
twilight81
post Jan 23 2014, 02:28 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(sscc @ Jan 23 2014, 12:54 PM)
They are charging interest on late payment from bank in making the disbursement to mayland.
Just a question, this month's progressive interest is ours to pay?  Coz I've checked with the bank and mayland has not cleared it yet.  So, now considered VP or not? Quite blur now.
*
Yeap... ur correct... Mayland are too tricky... they purposely try to avoid the January progress interest installment... Thats why they put VP date as 31/12/2013 when they not even release letter to bank to release the money for them...damn cunning vmad.gif

This post has been edited by twilight81: Jan 23 2014, 02:29 PM
windz1984
post Jan 23 2014, 03:59 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Sigh, what are we supposed to do now? So many hiccup. Better avoid their project next time.
ahsoh
post Jan 23 2014, 04:05 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
Call Mayland 3 time today. Pass my line around end up no person in charge answer my phone. sigh.
windz1984
post Jan 23 2014, 10:46 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(ahsoh @ Jan 23 2014, 04:05 PM)
Call Mayland 3 time today. Pass my line around end up no person in charge answer my phone. sigh.
*
Seems like they dun bother
TSThenry9999999
post Jan 23 2014, 10:54 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(twilight81 @ Jan 23 2014, 02:28 PM)
Yeap... ur correct... Mayland are too tricky... they purposely try to avoid the January progress interest installment... Thats why they put VP date as 31/12/2013 when they not even release letter to bank to release the money for them...damn cunning vmad.gif
*
Yes. Cunning company.
Maybe we take action against them after key Handover.
My bank haven't disburse the final payment to them.
remyadrian
post Jan 24 2014, 12:00 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


Anyone gotten their keys yet?my bank(ambank) haven't release the final disbursement either..hope they release it soon..called Mayland and the lady said the 4months advance maintenance fees and misc fees can be offset from the 5k initial booking fees so no need to fork out additional..so only left bank disbursement now..waiting for them then can go collect clearance letter from Mayland..
windz1984
post Jan 24 2014, 08:14 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Ya, I checked my bank (Ambank) also yet to release final disbursement. Wat can we do now?
adli8
post Jan 24 2014, 09:39 PM

Getting Started
**
Junior Member
128 posts

Joined: Dec 2008
QUOTE(windz1984 @ Jan 24 2014, 08:14 PM)
Ya, I checked my bank (Ambank) also yet to release final disbursement. Wat can we do now?
*
Similar to Affin Bank. Not release yet. affin bank still waiting the relevant documents from Mayland for the past two weeks..

BAWOTP2012
post Jan 26 2014, 10:54 PM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(Thenry9999999 @ Jan 23 2014, 10:54 PM)
Yes. Cunning company.
Maybe we take action against them after key Handover.
My bank haven't disburse the final payment to them.
*
Agree. We have at least 3 years to claim back what is ours. So, get the key first. Just some cashflow problem but look at it this way, we can charge them interest at 10% pa. Better than FD rate! So, better starts keeping evidence. Envelop with post mark utmost important. Gather name of fellow victims handy as they can be your witnesses. Take action against ML does not necessarily mean expensive: see link:

http://www.starproperty.my/index.php/artic...-late-delivery/

rclxm9.gif
ProX
post Jan 27 2014, 11:37 PM

Casual
***
Junior Member
316 posts

Joined: Aug 2006
From: KL


mine only 4 months advance maintenance + 4 months sinking fee, followed by the standard deposit for electricity meter / water meter and also quit rent. How come some of us here got bill up to 7k?
windz1984
post Jan 28 2014, 12:57 AM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(ProX @ Jan 27 2014, 11:37 PM)
mine only 4 months advance maintenance + 4 months sinking fee, followed by the standard deposit for electricity meter / water meter and also quit rent. How come some of us here got bill up to 7k?
*
Bro, you got ur key already?
sscc
post Jan 28 2014, 10:58 AM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
On a separate note, since we have quite a few owners active here, anyone interested with creating a fb group so that we can pull all the owners/residents together to discuss any issues etc?
ProX
post Jan 28 2014, 01:03 PM

Casual
***
Junior Member
316 posts

Joined: Aug 2006
From: KL


@windz1984 - nope, not yet. I just got the letter couple days ago. Not exactly in rush to do anything with the unit but since they are asking for payment, I am checking on next course of action required.

@sscc - good idea. How do we go about doing that?
twilight81
post Jan 28 2014, 01:52 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
I give a call to my bank (AMBANK) this morning and they inform me that the last payment have been transfer to Mayland... So I guess I can get the KEY soon... but wats the next course or action should I do... go to Mayland office to get the approval letter? With this CNY week... I dont think the office will open too... might be after CNY only can get Key I suppose.
remyadrian
post Jan 28 2014, 02:04 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


QUOTE(twilight81 @ Jan 28 2014, 01:52 PM)
I give a call to my bank (AMBANK) this morning and they inform me that the last payment have been transfer to Mayland... So I guess I can get the KEY soon... but wats the next course or action should I do... go to Mayland office to get the approval letter? With this CNY week... I dont think the office will open too... might be after CNY only can get Key I suppose.
*
Did you call Mayland to ask them if they have received the payment?
ahsoh
post Jan 28 2014, 02:46 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
I call Mayland, they confirm that they recieved the cheque from my bank but they also told me my unit is not ready. WTF!
remyadrian
post Jan 28 2014, 02:55 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


What block and floor is your unit?
sscc
post Jan 28 2014, 03:03 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(twilight81 @ Jan 28 2014, 01:52 PM)
I give a call to my bank (AMBANK) this morning and they inform me that the last payment have been transfer to Mayland... So I guess I can get the KEY soon... but wats the next course or action should I do... go to Mayland office to get the approval letter? With this CNY week... I dont think the office will open too... might be after CNY only can get Key I suppose.
*
This is good news! But mayland will call you once they are ready (that's what I was told)
Chances is after CNY given their efficiency level. The place looks like still have quite a bit to tidy up and the park is still flat.
sscc
post Jan 28 2014, 03:05 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(ProX @ Jan 28 2014, 01:03 PM)
@windz1984 - nope, not yet. I just got the letter couple days ago. Not exactly in rush to do anything with the unit but since they are asking for payment, I am checking on next course of action required.

@sscc - good idea. How do we go about doing that?
*
Good question. Let me have a go at it and see how to go about. Anyone out there who has any idea?
ahsoh
post Jan 28 2014, 08:33 PM

Casual
***
Junior Member
471 posts

Joined: May 2010
QUOTE(remyadrian @ Jan 28 2014, 02:55 PM)
What block and floor is your unit?
*
C2 7 floor

This post has been edited by ahsoh: Jan 28 2014, 08:33 PM
windz1984
post Jan 28 2014, 08:50 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(sscc @ Jan 28 2014, 03:05 PM)
Good question.  Let me have a go at it and see how to go about.  Anyone out there who has any idea?
*
Ya, good idea to form a Facebook group but how are we gonna verify the genuine owners to join the group?
windz1984
post Jan 28 2014, 08:55 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(twilight81 @ Jan 28 2014, 01:52 PM)
I give a call to my bank (AMBANK) this morning and they inform me that the last payment have been transfer to Mayland... So I guess I can get the KEY soon... but wats the next course or action should I do... go to Mayland office to get the approval letter? With this CNY week... I dont think the office will open too... might be after CNY only can get Key I suppose.
*
Good bro rclxms.gif I have checked with Ambank also, they just released the final payment to Mayland as well. Can't wait to get the keys drool.gif
TSThenry9999999
post Jan 29 2014, 07:39 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(ahsoh @ Jan 28 2014, 02:46 PM)
I call Mayland, they confirm that they recieved the cheque from my bank but they also told me my unit is not ready. WTF!
*
Not surprise because ML don't have intention to give key before CNY
I can still see workers touch up the building.

Their staff complaining them as well. You can check in their Facebook.
remyadrian
post Jan 29 2014, 04:02 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


Went to Mayland office today after making appointment with them yesterday,and managed to get letter of clearance and will be heading to Royal Regent on 7/02/14 to collect keys..apparently the woman I dealt with,Vijaya said the first appointment to collect keys from the site is on the 5th of Feb..

P/s: Kong Hei Fatt Choy and Happy CNY to everyone celebrating smile.gif
twilight81
post Jan 29 2014, 05:06 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
Do the office open on sat? cause I am working on weekday... Mmmm
twilight81
post Jan 29 2014, 05:08 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(remyadrian @ Jan 29 2014, 04:02 PM)
Went to Mayland office today after making appointment with them yesterday,and managed to get letter of clearance and will be heading to Royal Regent on 7/02/14 to collect keys..apparently the woman I dealt with,Vijaya said the first appointment to collect keys from the site is on the 5th of Feb..

P/s: Kong Hei Fatt Choy and Happy CNY to everyone celebrating smile.gif
*
Bro,

How u pay the miscellaneous payment and the maintenance and the sinking fund? You ask them to deduct from your 5K booking fees or u pay cash upfront?
remyadrian
post Jan 29 2014, 05:18 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


They deducted from the 5k and after minus everything still have some excess which they will refund to me apparently within two months from today..office open Monday-Friday from 9.30am-5.30pm..good luck!
twilight81
post Jan 29 2014, 05:25 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(remyadrian @ Jan 29 2014, 05:18 PM)
They deducted from the 5k and after minus everything still have some excess which they will refund to me apparently within two months from today..office open Monday-Friday from 9.30am-5.30pm..good luck!
*
Thanks bro for the info.... As expected... wanna get money from us... its easy... but wanna return money to us... wait 2 months.... sigh... mad.gif vmad.gif
sscc
post Jan 29 2014, 05:44 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(twilight81 @ Jan 29 2014, 05:25 PM)
Thanks bro for the info.... As expected... wanna get money from us... its easy... but wanna return money to us... wait 2 months.... sigh...  mad.gif  vmad.gif
*
Most important get key first. So, can't collect key from tomolo?
windz1984
post Jan 29 2014, 05:59 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(remyadrian @ Jan 29 2014, 04:02 PM)
Went to Mayland office today after making appointment with them yesterday,and managed to get letter of clearance and will be heading to Royal Regent on 7/02/14 to collect keys..apparently the woman I dealt with,Vijaya said the first appointment to collect keys from the site is on the 5th of Feb..

P/s: Kong Hei Fatt Choy and Happy CNY to everyone celebrating smile.gif
*
The clearance letter we must collect from their office or they can mail to us? If not can we collect the clearance letter and the keys on the same day?

Happy CNY to everyone. Cheers!
remyadrian
post Jan 29 2014, 06:12 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


Collect clearance letter from their HQ in Jalan Munshi Abdullah because need to settle any payments owing to them or not..once the checklist is cleared,you sign off then they'll issue you the clearance letter to collect the keys and also to set up the appointment date to go collect the keys..I'm not sure if can collect same day because in the letter of clearance it says that need at least 3 working days in advance to make appointment to go collect keys.

This post has been edited by remyadrian: Jan 29 2014, 11:05 PM
TSThenry9999999
post Jan 29 2014, 11:59 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(remyadrian @ Jan 29 2014, 05:18 PM)
They deducted from the 5k and after minus everything still have some excess which they will refund to me apparently within two months from today..office open Monday-Friday from 9.30am-5.30pm..good luck!
*
Thanks friend
propking88
post Jan 30 2014, 09:01 AM

New Member
*
Junior Member
9 posts

Joined: Sep 2010


So do we start paying the bank interest now or not? Can someone please advise?
twilight81
post Jan 30 2014, 10:51 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(remyadrian @ Jan 29 2014, 06:12 PM)
Collect clearance letter from their HQ in Jalan Munshi Abdullah because need to settle any payments owing to them or not..once the checklist is cleared,you sign off then they'll issue you the clearance letter to collect the keys and also to set up the appointment date to go collect the keys..I'm not sure if can collect same day because in the letter of clearance it says that need at least 3 working days in advance to make appointment to go collect keys.
*
Bro,

Where is their HQ in Jalan Munshi Abdullah? Is it near Menara AIA? I cant locate Menara May in google Map. Can give me some landmark near their HQ? Cause I am working on weekday...so i jut take some time off and go there... wanna save some time and dont wanna get lost otw there...
twilight81
post Jan 30 2014, 10:54 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(propking88 @ Jan 30 2014, 09:01 AM)
So do we start paying the bank interest now or not? Can someone please advise?
*
Yes... we start pay for the month of January... if u didnt pay yet, better pay up as there will be interest charges for late payment... and they will call u if u not been pating for 2 months... HAPPY CNY
sscc
post Jan 30 2014, 11:34 AM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(twilight81 @ Jan 30 2014, 10:51 AM)
Bro,

Where is their HQ in Jalan Munshi Abdullah? Is it near Menara AIA? I cant locate Menara May in google Map. Can give me some landmark near their HQ? Cause I am working on weekday...so i jut take some time off and go there... wanna save some time and dont wanna get lost otw there...
*
It's maytower building. Google map will show it. It's opposite cap square.
remyadrian
post Jan 30 2014, 01:07 PM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


Yeah maytower building,ground floor lobby..
TSThenry9999999
post Jan 30 2014, 05:18 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(twilight81 @ Jan 30 2014, 10:54 AM)
Yes... we start pay for the month of January... if u didnt pay yet, better pay up as there will be interest charges for late payment... and they will call u if u not been pating for 2 months... HAPPY CNY
*
The entrance bit tricky. Have to go thru the front door of the services residences, and turn left.
1282009
post Jan 31 2014, 04:20 PM

Look at all my stars!!
*******
Senior Member
4,230 posts

Joined: Jan 2009
Is PYS the contractor for RR? How's the workmanship?


sscc
post Jan 31 2014, 04:58 PM

New Member
*
Junior Member
14 posts

Joined: Dec 2013
QUOTE(sscc @ Jan 28 2014, 10:58 AM)
On a separate note, since we have quite a few owners active here, anyone interested with creating a fb group so that we can pull all the owners/residents together to discuss any issues etc?
*
Hi All,

Firstly, Happy CNY!

Next is, I've already set up a Facebook group for all Royal Regent owners/residents. Please visit Royal Regent Owners & Residents

Thank you biggrin.gif
BAWOTP2012
post Jan 31 2014, 07:22 PM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(twilight81 @ Jan 30 2014, 10:54 AM)
Yes... we start pay for the month of January... if u didnt pay yet, better pay up as there will be interest charges for late payment... and they will call u if u not been pating for 2 months... HAPPY CNY
*
My financier already informed me that DIBS ended 31.12.2013 and asked to pay Jan interest. mad.gif
TSThenry9999999
post Feb 1 2014, 10:13 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(BAWOTP2012 @ Jan 31 2014, 07:22 PM)
My financier already informed me that DIBS ended 31.12.2013 and asked to pay Jan interest. mad.gif
*
Me too.
Tsuto
post Feb 1 2014, 09:25 PM

Regular
******
Senior Member
1,220 posts

Joined: Mar 2006
Everyone happy with their lads payment? And the maintenance fee seem to be higher than what they promised...
BAWOTP2012
post Feb 2 2014, 01:07 PM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(Tsuto @ Feb 1 2014, 09:25 PM)
Everyone happy with their lads payment? And the maintenance fee seem to be higher than what they promised...
*
ML had unilaterally increased the MF from 30c to 32c citing increase in cost as the reason. sad.gif
TSThenry9999999
post Feb 2 2014, 02:47 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(BAWOTP2012 @ Feb 2 2014, 01:07 PM)
ML had unilaterally increased the MF from 30c to 32c citing increase in cost as the reason. sad.gif
*
Anyway after we settle down all the things, we have stand together to ask them explain item by item.
ML have lot of things not managed in proper.
For example, we didn't able to move in, but start to pay MF.

Stand together and we can tussle with them.
twilight81
post Feb 4 2014, 11:14 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(Thenry9999999 @ Feb 2 2014, 02:47 PM)
Anyway after we settle down all the things, we have stand together to ask them explain item by item.
ML have lot of things not managed in proper.
For example, we didn't able to move in, but start to pay MF.

Stand together and we can tussle with them.
*
Exactly!!!!
TSThenry9999999
post Feb 4 2014, 05:51 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(twilight81 @ Feb 4 2014, 11:14 AM)
Exactly!!!!
*
+1
twilight81
post Feb 7 2014, 10:50 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
So anyone get the key yet? If have any latest photo of the interior please post it here. Hope the quality is good considering all the fuss and delay in collecting the key...
TSThenry9999999
post Feb 7 2014, 07:36 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(twilight81 @ Feb 7 2014, 10:50 AM)
So anyone get the key yet? If have any latest photo of the interior please post it here. Hope the quality is good considering all the fuss and delay in collecting the key...
*
Yes. You are right.
Tsuto
post Feb 7 2014, 07:55 PM

Regular
******
Senior Member
1,220 posts

Joined: Mar 2006
I got the key today and went up to inspect my unit. No major defect from what i see ...
windz1984
post Feb 8 2014, 12:41 AM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(Tsuto @ Feb 7 2014, 07:55 PM)
I got the key today and went up to inspect my unit. No major defect from what i see ...
*
Wow, congrats! How is thr workmanship?
TSThenry9999999
post Feb 8 2014, 09:29 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(windz1984 @ Feb 8 2014, 12:41 AM)
Wow, congrats! How is thr workmanship?
*
Congratulations!
remyadrian
post Feb 8 2014, 10:31 AM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


Yeah got the keys yesterday too and workmanship not too bad just minor defects here and there like tile chip,toilet bowl seat cover crack and aircond leaking.but overall quite satisfied..
remyadrian
post Feb 8 2014, 10:37 AM

New Member
*
Junior Member
19 posts

Joined: May 2005
From: KL,Malaysia


Attached Image Attached Image Attached Image Attached Image Attached Image Attached Image
Tsuto
post Feb 8 2014, 11:13 AM

Regular
******
Senior Member
1,220 posts

Joined: Mar 2006
QUOTE(windz1984 @ Feb 8 2014, 12:41 AM)
Wow, congrats! How is thr workmanship?
*
Not bad I would say
Wiredx
post Feb 8 2014, 11:53 AM

On my way
****
Senior Member
592 posts

Joined: May 2010
Not bad. How much was it?
windz1984
post Feb 8 2014, 02:16 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


QUOTE(remyadrian @ Feb 8 2014, 10:37 AM)
Attached Image Attached Image Attached Image Attached Image Attached Image Attached Image
*
Seems like really not bad leh
TSThenry9999999
post Feb 8 2014, 02:43 PM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(remyadrian @ Feb 8 2014, 10:37 AM)
*
Congratulations, Remy

This post has been edited by Thenry9999999: Feb 8 2014, 02:44 PM
windz1984
post Feb 8 2014, 04:40 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Bros, I just received the VP letter today which dated 31/12/2013 from Mayland. I haven't collected the key yet and my bank call me the January 2014 instalment is due, so I need to pay or developer to pay?
1282009
post Feb 8 2014, 08:41 PM

Look at all my stars!!
*******
Senior Member
4,230 posts

Joined: Jan 2009
QUOTE(remyadrian @ Feb 8 2014, 10:37 AM)
Attached Image Attached Image Attached Image Attached Image Attached Image Attached Image
*
Not bad at all. Perhaps the VP delay is a blessing in disguise.


twilight81
post Feb 10 2014, 11:03 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(remyadrian @ Feb 8 2014, 10:37 AM)
Attached Image Attached Image Attached Image Attached Image Attached Image Attached Image
*
Good for u Remy... I will go there to collect key this friday... hope its as good as urs...
twilight81
post Feb 10 2014, 11:06 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(windz1984 @ Feb 8 2014, 04:40 PM)
Bros, I just received the VP letter today which dated 31/12/2013 from Mayland.  I haven't collected the key yet and my bank call me the January 2014 instalment is due, so I need to pay or developer to pay?
*
Bro,
For now I guess u have to pay the interest service to avoid further penalty... I guess we can join force to make a complain to Mayland for the delayed and stuff... cause we all need to pay for january maintenance fees although we only can get the key after CNY which is February... we might need to teach this blood sucker a lesson or two... but this can only be done if we join force... else its a waste of time if we shoot them individually... they just treat us as ant!!! blink.gif
TSThenry9999999
post Feb 11 2014, 12:06 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(twilight81 @ Feb 10 2014, 11:06 AM)
Bro,
For now I guess u have to pay the interest service to avoid further penalty... I guess we can join force to make a complain to Mayland for the delayed and stuff... cause we all need to pay for january maintenance fees although we only can get the key after CNY which is February... we might need to teach this blood sucker a lesson or two... but this can only be done if we join force... else its a waste of time if we shoot them individually... they just treat us as ant!!!  blink.gif
*
Count me in.
BAWOTP2012
post Feb 11 2014, 12:27 AM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(Thenry9999999 @ Feb 11 2014, 12:06 AM)
Count me in.
*
Suggest you join the Owners Group on Facebook if you have not already done so. Click on the link in post #208 by SSCC. smile.gif
yoong81
post Feb 11 2014, 04:31 PM

Getting Started
**
Junior Member
242 posts

Joined: Jul 2012


i tink mayland is one of the most problematic developers around.

regalia jalan sultan ismail - cf issue.

dorsett waterfront - cancelled because permit issue.

royal regent - delay.

but they really good at choosing strategic development location.
so their projects all have potential to appreciate.
windz1984
post Feb 11 2014, 06:47 PM

Getting Started
**
Junior Member
87 posts

Joined: Nov 2013


Ya, agreed. Really so many problems need to endure by purchasers.
weiming_chong
post Feb 18 2014, 09:06 PM

New Member
*
Junior Member
16 posts

Joined: Jun 2013
QUOTE(remyadrian @ Feb 8 2014, 10:37 AM)
Attached Image Attached Image Attached Image Attached Image Attached Image Attached Image
*
how many sf is this unit? have bath tub somemore
Pre-Loved
post Feb 18 2014, 09:11 PM

New Member
*
Junior Member
35 posts

Joined: Nov 2013
Th overall is still bad workmanship, for internal and external. U can expect some internal walls were wavvy and exterior patching works was not patching up !! Especially the outdoor compressor slabs area!!!
JINGLEC
post Feb 21 2014, 12:34 PM

New Member
*
Newbie
3 posts

Joined: Feb 2014
Anyone has claim for late delivery ?

Mayland offer me maximum 70% only.
ecin
post Feb 21 2014, 05:36 PM

location
*******
Senior Member
5,857 posts

Joined: Dec 2010
QUOTE(JINGLEC @ Feb 21 2014, 12:34 PM)
Anyone has claim for late delivery ?

Mayland offer me maximum 70% only.
*
group together go tribunal court
airline
post Feb 21 2014, 08:05 PM

7 stars
*******
Senior Member
7,923 posts

Joined: Feb 2007
From: 1 Malaysia
QUOTE(JINGLEC @ Feb 21 2014, 12:34 PM)
Anyone has claim for late delivery ?

Mayland offer me maximum 70% only.
*
Better open ur mouth to ask for lad
This developer if u no ask, they not going to pay

All 70 percent they offer
speedyhorse
post Feb 28 2014, 11:19 AM

New Member
*
Newbie
4 posts

Joined: Feb 2014
Dear Royal Regent Owners,

I would like to know any of you out there keen to join me to file a legal claim for LAD payment?

Please reply soonest.

Thanks

speedyhorse
post Feb 28 2014, 11:37 AM

New Member
*
Newbie
4 posts

Joined: Feb 2014
Anybody out there wants to form a group and sue Mayland for LAD?
speedyhorse
post Feb 28 2014, 11:47 AM

New Member
*
Newbie
4 posts

Joined: Feb 2014
To All Owners of Royal Regent Condo

I believe many of you by now have received your apartment keys. I collect my keys 2 weeks ago and currently waiting to sort out with the developer on the LAD (Late delivery penalty).

I face with a branch of people trying to short change me and giving all sort of excuses not to pay up.

I have decided to take legal action and get a full refund. Normally, more people co-operating in a group and filing legal action together has a stronger voice and also cheaper legal fees.

If you are interested please contact me by email soonest.

Thanks

speedy

BAWOTP2012
post Feb 28 2014, 11:57 PM

New Member
*
Junior Member
28 posts

Joined: Mar 2013
QUOTE(speedyhorse @ Feb 28 2014, 11:47 AM)
To All Owners of Royal Regent Condo

I believe many of you by now have received your apartment keys. I collect my keys 2 weeks ago and currently waiting to sort out with the developer on the LAD (Late delivery penalty).

I face with a branch of people trying to short change me and giving all sort of excuses not to pay up.

I have decided to take legal action and get a full refund. Normally, more people co-operating in a group and filing legal action together has a stronger voice and also cheaper legal fees.

If you are interested please contact me by email soonest.

Thanks

speedy
*
There are many people wanted to get what they entitled in FULL from ML. You may wish to join the owners group in facebook. Link to facebook is in earlier post. You would have noted that CTCT already filed his claims against ML with Housing Tribunal. And many of the owners will take that route. Simply, it costs little in terms of actual outlay as no lawyers are allowed in this type of proceedings. You just fill up forms and present your case to the Tribunal. It is also very fast - CTCT got the hearing within 1 month from filing. Unless you have plenty of cash to spend, and time to wait, Housing Tribunal is the way to go.
JINGLEC
post Mar 12 2014, 04:25 PM

New Member
*
Newbie
3 posts

Joined: Feb 2014
I have filed the claim with Housing Tribunal and get the hearing date less than a month.

The process is super simple and wont take you more than 10 minutes to file a claim, and the fees is just RM 10.00.

ML just pretend do not have LAD when i first collect the key and until i ask they offer 50% and then max 70%, which this is based on discounted price. They do not pay for the LAD on common facility.

After checked with my friend, we can actually claim based on the S&P price and include additional of 14 days after Vacant Possesion. Also, we can claim for the LAD for common facility too, 20% x 10% x Purchase Price x Number of days late (additional of 14 days) / 365 days.

Will keep you guys update, once i complete the hearing by end of this month.






bb68
post Mar 12 2014, 05:15 PM

Enthusiast
*****
Senior Member
718 posts

Joined: Oct 2013
Wa that is lot of money. ML in trouble...
nixnix
post Mar 12 2014, 05:28 PM

New Member
*
Junior Member
18 posts

Joined: Jan 2003


HI guys,

How do we follow up on the defeat? it has been a month already. pls help!
twilight81
post Apr 29 2014, 11:36 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
Hi guys... anyone get the booking fees back yet?
I try to call them and they keep on ask me find this william guy who never at office... wtf I am so damn piss... its not much but its still our money... anyone of u guys able to get back the money? Shit this bugger when wan money from us...will hold our keys...but when we want our own money back... they keep delaying... really dont wanna curse them but really WTF!!
TSThenry9999999
post May 7 2014, 12:13 AM

Getting Started
**
Junior Member
101 posts

Joined: Sep 2013
QUOTE(twilight81 @ Apr 29 2014, 11:36 AM)
Hi guys... anyone get the booking fees back yet?
I try to call them and they keep on ask me find this william guy who never at office... wtf I am so damn piss... its not much but its still our money... anyone of u guys able to get back the money? Shit this bugger when wan money from us...will hold our keys...but when we want our own money back... they keep delaying... really dont wanna curse them but really WTF!!
*
Have u collected you key?
If not, just go directly to their office and get to see anyone of themin charge of RR face to face.
Else they will keep yours in low priority.

The key handover is pretty fast, but you will face another low class management in their defect handling.
Say no to Mayland next time. Really troublesome! Sigh!
alexwks
post May 11 2014, 01:59 PM

New Member
*
Junior Member
19 posts

Joined: Jun 2009


hi all, I noticed that some of you have filed and win the tribunal case against ML (and I am one of them), do you know that ML is actually disregarding the tribunal file and would proceed to high court? In other words they want us to hire lawyer to fight them. Is anyone here planning on a class action or any group complaints to lodge against them?
Siao_Lang
post May 12 2014, 11:38 PM

Casual
***
Junior Member
454 posts

Joined: Aug 2013
QUOTE(alexwks @ May 11 2014, 01:59 PM)
hi all, I noticed that some of you have filed and win the tribunal case against ML (and I am one of them), do you know that ML is actually disregarding the tribunal file and would proceed to high court? In other words they want us to hire lawyer to fight them. Is anyone here planning on a class action or any group complaints to lodge against them?
*
MAYLAND is the worst developer ever..

They tend to disregard responsibilities..

Please dont buy their project in the future.. Should boycott them.. Let them suffer..

Worst staffs, worst workmanship, worst reputation, worst customer satisfaction!!

They only want profit, and that's it! vmad.gif
icemanfx
post May 13 2014, 12:32 AM

20k VIP Club
*********
All Stars
21,457 posts

Joined: Jul 2012


QUOTE(Siao_Lang @ May 12 2014, 11:38 PM)
MAYLAND is the worst developer ever..

They tend to disregard responsibilities..

Please dont buy their project in the future.. Should boycott them.. Let them suffer..

Worst staffs, worst workmanship, worst reputation, worst customer satisfaction!!

They only want profit, and that's it! vmad.gif
*
"There's a sucker born every minute"

This is not their first project nor their last.


Wiredx
post May 13 2014, 08:06 AM

On my way
****
Senior Member
592 posts

Joined: May 2010
QUOTE(icemanfx @ May 13 2014, 12:32 AM)
"There's a sucker born every minute"

This is not their first project nor their last.
*
Lol
The mantra is always "things will be different this time"
alexwks
post May 13 2014, 01:25 PM

New Member
*
Junior Member
19 posts

Joined: Jun 2009


sad.gif gave them a call, asking them if they gonna pay up after losing the tribunal court case against me. But they refused and told me that they will take this to the high court (meaning he wants me to hire a lawyer against them)

obviously as individual, it's not worth it because the costs is going to be hefty, however if we start a class action, I believe it will be a different ball game.
SnowLady
post Jun 4 2014, 12:27 AM

Getting Started
**
Junior Member
146 posts

Joined: Jul 2013
Any direct owner who wants to sell a unit?

Please PM me.

Thanks
rumahmurah
post Jun 4 2014, 01:38 PM

Getting Started
**
Junior Member
267 posts

Joined: Aug 2011
QUOTE(alexwks @ May 13 2014, 01:25 PM)
sad.gif gave them a call, asking them if they gonna pay up after losing the tribunal court case against me. But they refused and told me that they will take this to the high court (meaning he wants me to hire a lawyer against them)

obviously as individual, it's not worth it because the costs is going to be hefty, however if we start a class action, I believe it will be a different ball game.
*
Get back to the Tribunal and lodge a complaint
And this is the procedure: Jika responden enggan mematuhi Award, penuntut perlu mebuat aduan ingkar kepada Tribunal serta lampirkan satu salinan surat kepada Bahagian Penguatkuasaan, KKBPKT.
Aglora3257
post Jun 5 2014, 01:32 PM

New Member
*
Junior Member
18 posts

Joined: Jun 2014


QUOTE(SnowLady @ Jun 4 2014, 12:27 AM)
Any direct owner who wants to sell a unit?

Please PM me.

Thanks
*
Hi all. Whats up!

SnowLady, i've pm you.

twilight81
post Jun 13 2014, 11:11 AM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(alexwks @ May 13 2014, 01:25 PM)
sad.gif gave them a call, asking them if they gonna pay up after losing the tribunal court case against me. But they refused and told me that they will take this to the high court (meaning he wants me to hire a lawyer against them)

obviously as individual, it's not worth it because the costs is going to be hefty, however if we start a class action, I believe it will be a different ball game.
*
If I not mistaken... they will pay for the LAD but will not pay in full... I heard they only will pay us around 70% of the LAD... so if its 10K... u will only get 7K....
well...I guess its better than nothing rite? sad.gif
SUSgogo2
post Jun 13 2014, 11:16 AM

gogo2
********
All Stars
18,672 posts

Joined: Jan 2003
From: Penang


QUOTE(alexwks @ May 13 2014, 01:25 PM)
sad.gif gave them a call, asking them if they gonna pay up after losing the tribunal court case against me. But they refused and told me that they will take this to the high court (meaning he wants me to hire a lawyer against them)

obviously as individual, it's not worth it because the costs is going to be hefty, however if we start a class action, I believe it will be a different ball game.
*
Housing Tribunal is final. I don't think they can bring it to highcourt.

They just scaring you because once you think that you need to hire a lawyer, you will back off because lawyer is expensive..

This post has been edited by gogo2: Jun 13 2014, 11:17 AM
cfa28
post Jun 13 2014, 11:26 AM

Look at all my stars!!
*******
Senior Member
4,830 posts

Joined: Jan 2012


QUOTE(alexwks @ May 11 2014, 01:59 PM)
hi all, I noticed that some of you have filed and win the tribunal case against ML (and I am one of them), do you know that ML is actually disregarding the tribunal file and would proceed to high court? In other words they want us to hire lawyer to fight them. Is anyone here planning on a class action or any group complaints to lodge against them?
*
if this happens, please seek National House Buyers Association for Help.

website is www.hba.org.my

e-mail to info@hba.org.my

HBA has lobbied that the AG Chambers appears for House Buyers / Housing Tribnunal when Developers appeals to High Court.

Please seek their advice, HBA also has team of volunteer lawyers
twilight81
post Oct 2 2014, 12:12 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
Hi to all Royal Regent owner... does anyone get their cukai taksiran (assessment) from DBKL yet?
How much is the bill??

WannaGetBuffed
post Oct 3 2014, 10:21 AM

Enthusiast
*****
Senior Member
983 posts

Joined: Jul 2008
QUOTE(twilight81 @ Oct 2 2014, 12:12 PM)
Hi to all Royal Regent owner... does anyone get their cukai taksiran (assessment) from DBKL yet?
How much is the bill??
*
Did you manage to get your LAD?
twilight81
post Oct 3 2014, 04:19 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(WannaGetBuffed @ Oct 3 2014, 10:21 AM)
Did you manage to get your LAD?
*
yeah...with discount...around 25% discount... ;(
puchongite
post Oct 3 2014, 04:23 PM

20k VIP Club
*********
All Stars
33,714 posts

Joined: May 2008
QUOTE(twilight81 @ Oct 3 2014, 04:19 PM)
yeah...with discount...around 25% discount... ;(
*
Nobody consulted a lawyer to see if can get the amount in full ?
twilight81
post Oct 3 2014, 04:25 PM

Getting Started
**
Junior Member
50 posts

Joined: Dec 2013
QUOTE(puchongite @ Oct 3 2014, 04:23 PM)
Nobody consulted a lawyer to see if can get the amount in full ?
*
i heard can... but they will drag it... so its up to each individual owners... how bout u? get any LAD?
puchongite
post Oct 3 2014, 04:27 PM

20k VIP Club
*********
All Stars
33,714 posts

Joined: May 2008
QUOTE(twilight81 @ Oct 3 2014, 04:25 PM)
i heard can... but they will drag it... so its up to each individual owners... how bout u? get any LAD?
*
I am not a buyer. I am just keh poh here.
WannaGetBuffed
post Oct 3 2014, 04:38 PM

Enthusiast
*****
Senior Member
983 posts

Joined: Jul 2008
QUOTE(twilight81 @ Oct 3 2014, 04:19 PM)
yeah...with discount...around 25% discount... ;(
*
At least they pay. I had a case with another famous dev last time. Tribunal awarded but don't want to pay. Sister company prefer to go bust and liquidate. 1 sen also tak ada.

Name already busuk until cannot develop properties. but i believe they still have lands around though.


rumahmurah
post Oct 3 2014, 05:04 PM

Getting Started
**
Junior Member
267 posts

Joined: Aug 2011
QUOTE(twilight81 @ Oct 3 2014, 04:19 PM)
yeah...with discount...around 25% discount... ;(
*
Good and move on. I hope the payment was in a lump sum.
kaweng88
post Jan 18 2019, 04:36 PM

New Member
*
Newbie
16 posts

Joined: Nov 2017


QUOTE(speedyhorse @ Feb 28 2014, 11:47 AM)
To All Owners of Royal Regent Condo

I believe many of you by now have received your apartment keys. I collect my keys 2 weeks ago and currently waiting to sort out with the developer on the LAD (Late delivery penalty).

I face with a branch of people trying to short change me and giving all sort of excuses not to pay up.

I have decided to take legal action and get a full refund. Normally, more people co-operating in a group and filing legal action together has a stronger voice and also cheaper legal fees.

If you are interested please contact me by email soonest.

Thanks

speedy
*
Hi, just curious of the outcome of this. Currently me together with 40+ buyers of Dorsett Residence Hartamas been waiting for handover since Dec2017. Most of us only signed SPA in mid 2017 so contractually they are to deliver within 36 months from SPA, but most of us signed the SPA when the whole building was 75% completed so we were given the assurance it would be completed by 2017. So until now, no news on the VP.
sh3nst3r
post Nov 23 2023, 09:13 PM

New Member
*
Newbie
14 posts

Joined: Sep 2016
What happened in the end? Did Mayland pay up?

 