got a quote from my contractor for my car porch tiles.
Total tiles 310 pieces
Total area 320 Sq ft
Price for workmanship plus cement/glue/sand 6.5 myr per Sq ft.
that do you think? am I paying too much?
Tiles, Cost and Installation
Tiles, Cost and Installation
|
|
Apr 3 2019, 08:52 AM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,274 posts Joined: Jun 2008 |
got a quote from my contractor for my car porch tiles.
Total tiles 310 pieces Total area 320 Sq ft Price for workmanship plus cement/glue/sand 6.5 myr per Sq ft. that do you think? am I paying too much? |
|
|
|
|
|
Apr 3 2019, 09:48 AM
Show posts by this member only | IPv6 | Post
#2302
|
![]() ![]() ![]() ![]() ![]()
Junior Member
733 posts Joined: Nov 2013 |
QUOTE(Avangelice @ Apr 3 2019, 08:52 AM) got a quote from my contractor for my car porch tiles. 320 pieces 1x1 tiles?Total tiles 310 pieces Total area 320 Sq ft Price for workmanship plus cement/glue/sand 6.5 myr per Sq ft. that do you think? am I paying too much? the price macam ok. Got quotation from one of the contractor, labour cost RM3k for smaller than 320sqft. |
|
|
Apr 3 2019, 09:59 AM
Show posts by this member only | IPv6 | Post
#2303
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,274 posts Joined: Jun 2008 |
QUOTE(naqib0307 @ Apr 3 2019, 09:48 AM) 320 pieces 1x1 tiles? it's 2x1 bro. the price macam ok. Got quotation from one of the contractor, labour cost RM3k for smaller than 320sqft. I went to a construction group and found another contractor that quoted me on this. Hi pls find the written quote for your review. 1.Labour of fixing plus materials(cement & cement adhesive) Rm4.20 per Sq ft.. 2. Rescreeding to level the existing floor ( if not level) rm1.80 per Sq ft..materials included ( sand & cement) much cheaper by 50 cents |
|
|
Apr 3 2019, 11:53 AM
|
![]()
Junior Member
14 posts Joined: Dec 2006 |
Hi Guys,
Anyone got any tilling contractors to recommend at Rawang area. I'm having some issue with my tiles in my room, they are expanding upward and almost look like volcano going to erupt. Please pm me the details Thank you. |
|
|
Apr 3 2019, 01:15 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
7,938 posts Joined: Mar 2014 |
QUOTE(xenite @ Apr 3 2019, 11:53 AM) Hi Guys, If involves several tiles only, just fix it yourself.Anyone got any tilling contractors to recommend at Rawang area. I'm having some issue with my tiles in my room, they are expanding upward and almost look like volcano going to erupt. Please pm me the details Thank you. Buy tiles and use epoxy to glue them back |
|
|
Apr 9 2019, 04:10 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,595 posts Joined: Aug 2017 |
My contractor calculate tiles like this
Area 1000sqft 2'x2' = RM17 /pcs Total tile + installation = RM17 x 1000 = RM17,000 wtf |
|
|
|
|
|
Apr 9 2019, 04:24 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,063 posts Joined: Feb 2019 |
|
|
|
Apr 9 2019, 04:28 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,924 posts Joined: Jan 2019 |
QUOTE(sonypshomer @ Apr 9 2019, 04:10 PM) My contractor calculate tiles like this You need a new contractor as when a contractor gives you that type of quotes indirectly he is saying he isn't interested in your business.Area 1000sqft 2'x2' = RM17 /pcs Total tile + installation = RM17 x 1000 = RM17,000 wtf |
|
|
Apr 9 2019, 04:39 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,595 posts Joined: Aug 2017 |
|
|
|
Apr 9 2019, 04:59 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
7,938 posts Joined: Mar 2014 |
|
|
|
Apr 10 2019, 09:45 AM
|
![]() ![]()
Junior Member
185 posts Joined: May 2007 |
|
|
|
Apr 10 2019, 10:02 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,595 posts Joined: Aug 2017 |
|
|
|
Apr 10 2019, 12:23 PM
|
![]() ![]() ![]()
Junior Member
411 posts Joined: Jan 2018 |
QUOTE(sonypshomer @ Apr 9 2019, 04:10 PM) My contractor calculate tiles like this Assuming 17K is inclusive of tiles and cement+workmanshipArea 1000sqft 2'x2' = RM17Â /pcs Total tile + installation = RM17 x 1000 = RM17,000 wtf Here is what I can breakdown: p.s. estimates only... cost of tiles variable depends on quality/design, your contractor may have different rate.. 1000 sq ft /4 (2x2 tile is 4 sq ft each) = 250pcs of tiles say at rm10 (usually grade B tiles) per piece = rm2500 Workmanship is usually between rm6-10 per sq ft for 2x2 tiles (rm 10 usually inclusive of cement and sand) 1000 x 10 = rm10000 your total outlay will be around rm9k to 13k if there is hacking involved add another rm2-3k (rm2-3 per sq ft). This post has been edited by kimzee: Apr 10 2019, 12:28 PM |
|
|
|
|
|
May 14 2019, 06:22 PM
|
![]() ![]()
Junior Member
185 posts Joined: May 2007 |
|
|
|
May 15 2019, 09:06 AM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
7,938 posts Joined: Mar 2014 |
QUOTE(RVN10 @ May 14 2019, 06:22 PM) Guys i am in dilemma between using tile trim/edging or without for my wet kitchen (doing ceiling height tiling) area. Need quick advise on this. TQ Anyway, why is dilemma? I think it should not cost significantly more since it is just plastic |
|
|
May 20 2019, 07:35 PM
Show posts by this member only | IPv6 | Post
#2316
|
![]() ![]() ![]() ![]()
Junior Member
625 posts Joined: Nov 2013 |
if you are looking for contractor to renovate your house, you may pm me as i have a good one to recommend (Indo supervisor worked here for more than 10 years). Most of the contractor did provide one year defect but most of the time they may not entertain you after completed the reno but for my case, i have contacted twice and he did come to fix the defects and hence i will strongly recommend him to you. He has not much work recently and hence i post here to see who is looking for a contractor.
|
|
|
May 27 2019, 12:55 PM
|
![]() ![]()
Junior Member
84 posts Joined: Apr 2019 |
|
|
|
May 27 2019, 04:37 PM
|
![]() ![]()
Junior Member
185 posts Joined: May 2007 |
|
|
|
Jun 10 2019, 05:19 PM
|
![]()
Junior Member
40 posts Joined: Apr 2016 |
QUOTE(snowswc @ May 20 2019, 07:35 PM) if you are looking for contractor to renovate your house, you may pm me as i have a good one to recommend (Indo supervisor worked here for more than 10 years). Most of the contractor did provide one year defect but most of the time they may not entertain you after completed the reno but for my case, i have contacted twice and he did come to fix the defects and hence i will strongly recommend him to you. He has not much work recently and hence i post here to see who is looking for a contractor. Hi,please PM the contact number |
|
|
Jun 15 2019, 03:30 AM
Show posts by this member only | IPv6 | Post
#2320
|
![]()
Newbie
5 posts Joined: Mar 2010 |
QUOTE(snowswc @ May 20 2019, 07:35 PM) if you are looking for contractor to renovate your house, you may pm me as i have a good one to recommend (Indo supervisor worked here for more than 10 years). Most of the contractor did provide one year defect but most of the time they may not entertain you after completed the reno but for my case, i have contacted twice and he did come to fix the defects and hence i will strongly recommend him to you. He has not much work recently and hence i post here to see who is looking for a contractor. Give me contact number |