Hi Everyone,
Welcome New Members
I see a lot of people with a lot of questions...... here's a few answers to your questions:
1. SYABAS WATER METER Syabas is currently installing only 100 meters a day. They can only open the main water tank once all meters are
fixed, because if not the ones that have no meter also will have water pouring out nanti banjirlah....
360 water meters have been fixed so far.... and they still have a balance of about 340 to go.
2. LAD CLAIMS For those who have written to developer to claim LAD, please write to the developer again stating that you are
revoking your original LAD request by resubmitting the request based on the date you have water supplied to your
parcel.
I have attached the sample letter for your use.
Please refer to your S&P Clause 27: Manner of delivery of vacant possession
1. Certificate by vendors architect certifying that the construction of the said parcel, has been duly completed and water and electric supply is ready for connection
the term ready for connection is elaborated in clause 35 - Interpretation
means water and electrical fittings and fixtures have been installed by the developer and tested and commissioned.
Till today, the Developer has only given CF and the certificate that was sign of by the architect which means we can claim for LD until we have the exact date of water connection.
3. CORRECT SPECIFICATIONS We have collected a copy of the master plan. Desmond a committee member will try to get an external architect
to go though and see if the specifications are correct... such as the bathroom height, master bedroom height, front
porch, etc.
4. HOUSE DEFECTS HBA has given us brochures of House Inspectors (its attached)... for a small fee they will come and inspect your
home and findout all the mistakes, etc and give you a written report on it.