 MBSA Renovation Permit, want to just ask estimate cost

views
     
personaforever6789
post Oct 16 2021, 08:09 PM

Casual
***
Junior Member
475 posts

Joined: Mar 2008
QUOTE(mini orchard @ Sep 2 2021, 04:25 PM)
If the existing extension was approved previously, then not necesssry. Otherwise, need to submit plan and pay a fine for the old extension without approval.

Not necessary to demolish the entire wall. The contractor will know what to do. This small job, few days can kaotim unless you are also doing other things.

Unless neighbour complain or if you are unlucky mbsa pass through your area, they will check on your house. If is at back lane area, normally not obvious unless you have a roro bin infront of the house.
*
still need

This post has been edited by personaforever6789: Sep 8 2023, 01:08 PM
JasonTheGreat
post Oct 16 2021, 08:12 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
QUOTE(utellme @ Oct 16 2021, 03:31 PM)
Related to the Saman, when I submiting my setara plan last week, the officer asked me why I didn't tambah the bahagian tepi with the new architect plan and he said the fine is based on the buildup area. Example, if I want to extend the side of my house with a new wet kitchen with area size of 33sm then I have to pay Saman 20x (33*7)= RM 4k+
*
I see that you multiply by 7. How is that calculated?
I was told that the plan is rm300. So fine 20x 300 of did not follow
haturaya
post Oct 16 2021, 08:22 PM

Look at all my stars!!
Group Icon
Elite
2,554 posts

Joined: Jan 2003
QUOTE(dlttdltt @ Oct 16 2021, 10:45 AM)
If change floor tiles, change window frame, change front security door and paint the whole house, do we still need to apply for Mbsa permit ? Maybe will also wall between hall and dry kitchen.
*
Nope. whistling.gif
utellme
post Oct 17 2021, 01:27 AM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(JasonTheGreat @ Oct 16 2021, 08:12 PM)
I see that you multiply by 7. How is that calculated?
I was told that the plan is rm300. So fine 20x 300 of did not follow
*
Processing fee is RM7 per sqm, minimum processing must not less RM70. But the processing fee setara plan is RM300 for each section. my extension is front section 1st floor and back section ground floor therefore total cost is RM2128. (300+300+648+880). Not sure I can claim back the RM648 after renovation completed because in the receipts, the payment rm648 is called bayaran permit plan bangunan and RM 600 is called bayaran process plan.
JasonTheGreat
post Oct 18 2021, 12:23 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
QUOTE(utellme @ Oct 17 2021, 01:27 AM)
Processing fee is RM7 per sqm, minimum processing must not less RM70. But the processing fee setara plan is RM300 for each section. my extension is front section 1st  floor and back section ground floor therefore total cost is RM2128. (300+300+648+880). Not sure I can claim back the RM648 after renovation completed because in the receipts, the payment rm648 is called bayaran permit plan bangunan and RM 600 is called bayaran process plan.
*
Finally submitted my Pelan Setara at MBSA. Forced my self to prepare all the documents yesterday as I expect to be less crowded today due to the public holiday tomorrow.

I paid 648 Bayaran Process Pelan, 300 permit pelan rear extension and 880 for tong Roro. Tong roro can claim back if did not utilised. But not sure either for 648. If cannot take back then I made a mistake where i removed my awning installation in this submission. If next time resubmit will be another 648+300
utellme
post Oct 18 2021, 05:59 PM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(JasonTheGreat @ Oct 18 2021, 12:23 PM)
Finally submitted my Pelan Setara at MBSA. Forced my self to prepare all the documents yesterday as I expect to be less crowded today due to the public holiday tomorrow.

I paid 648 Bayaran Process Pelan, 300 permit pelan rear extension and 880 for tong Roro. Tong roro can claim back if did not utilised. But not sure either for 648. If cannot take back then I made a mistake where i removed my awning installation in this submission. If next time resubmit will be another 648+300
*
yes, for me, I reached MBSA before 7.45am when I did my plan submission, still there are 2 renovation runner ahead of me and complete my plan submission around 9:30am . For permit collection, appointment time is set from 2:30pm to 4:00pm and reached there 2:20pm and still 4 people ahead of me and finally collected the permit at 3:30pm.
JasonTheGreat
post Oct 19 2021, 09:00 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
QUOTE(utellme @ Oct 18 2021, 05:59 PM)
yes, for me, I reached MBSA before 7.45am when I did my plan submission, still there are 2 renovation runner ahead of me and  complete  my plan submission around 9:30am . For permit collection, appointment time is set from 2:30pm to 4:00pm and reached there 2:20pm and still 4 people ahead of me and finally collected the permit at 3:30pm.
*
How many days to wait for the approval? From their website it say 1 hr. But after I submit they asked me to go home and wait.
utellme
post Oct 19 2021, 09:10 PM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(JasonTheGreat @ Oct 19 2021, 09:00 PM)
How many days to wait for the approval? From their website it say 1 hr. But after I submit they asked me to go home and wait.
*
Didn't they give you a pink permit collection appointment form after plan submission. I only paid the fee when I collect my permit and its 1 week. For me, submit on 8 Oct and permit collection is 15 Oct.

This post has been edited by utellme: Oct 19 2021, 09:11 PM
SUSceo684
post Oct 19 2021, 09:35 PM

Component Burner
********
All Stars
11,667 posts

Joined: Jan 2003
From: Klang/Subang




QUOTE(dlttdltt @ Oct 16 2021, 10:45 AM)
If change floor tiles, change window frame, change front security door and paint the whole house, do we still need to apply for Mbsa permit ? Maybe will also wall between hall and dry kitchen.
*
Structurally never changed no need permit.
Add or delete structural component like wall/extensions/roof incl awning need.
JasonTheGreat
post Oct 19 2021, 09:51 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
QUOTE(utellme @ Oct 19 2021, 09:10 PM)
Didn't they give you a pink permit collection appointment form after plan submission. I only paid the fee when I collect my permit and its 1 week. For me,  submit on 8 Oct and permit collection is 15 Oct.
*
No. I paid. They gave me a receipt of Rm18xx and tell me to go home and wait. No pink slip 🙁
incredibless
post Dec 5 2021, 01:32 PM

Casual
***
Junior Member
437 posts

Joined: Jun 2012
Hi.since this thread is latest. Would like to check for those applied permit already and once your reno work like extension already complete. What is the next step? Inform Mbsa? Or dont need? When inform will they come n check? Or just refund you the deposits?🤔
TStaufoo
post Dec 5 2021, 01:36 PM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
From what I understand, they don't check and you don't have to inform them you complete the renovation.
The validity of the permit is 1 year from date of approval.

The deposit u get back is from the tong roro.
utellme_6376
post Dec 5 2021, 04:08 PM

Getting Started
**
Junior Member
106 posts

Joined: Nov 2021


QUOTE(taufoo @ Dec 5 2021, 01:36 PM)
From what I understand, they don't check and you don't have to inform them you complete the renovation.
The validity of the permit is 1 year from date of approval.

The deposit u get back is from the tong roro.
*
Yes, this is what I understand too.
TStaufoo
post Dec 7 2021, 09:12 AM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
Guys, just update.even after MBSA approval and sticker placed on front door, the worker received two "visitors" yesterday.

They claim to be officers but in normal clothing.
Take some photos and say this wall cannot la that wall cannot la.

Contractor say is most likely come anyway to ask for duit kopi. But the worker didn't ask if from majlis or construction board (CI**)

Damn troublesome seriously. Apply or not also got ppl come kacau.
soulred777
post Dec 7 2021, 10:50 PM

Enthusiast
*****
Junior Member
803 posts

Joined: Aug 2019
QUOTE(taufoo @ Dec 7 2021, 09:12 AM)
Guys, just update.even after MBSA approval and sticker placed on front door, the worker received two "visitors" yesterday.

They claim to be officers but in normal clothing.
Take some photos and say this wall cannot la that wall cannot la.

Contractor say is most likely come anyway to ask for duit kopi. But the worker didn't ask if from majlis or construction board (CI**)

Damn troublesome seriously. Apply or not also got ppl come kacau.
*
Next time report to cops.
getfromme
post Oct 2 2022, 10:32 PM

New Member
*
Junior Member
29 posts

Joined: Jun 2009


QUOTE(kennykck @ Sep 2 2021, 08:14 PM)
Should be below RM1000 for permit. you may contact 0123876104 (En Amin) for help.

https://forum.lowyat.net/topic/1898813/all
*
En Amin is your friend working inside MBSA?
kennykck
post Oct 3 2022, 12:04 PM

!!!~~<((Bankai))>~~!!!
******
Senior Member
1,711 posts

Joined: Sep 2006


QUOTE(getfromme @ Oct 2 2022, 10:32 PM)
En Amin is your friend working inside MBSA?
*
Found his contact from online. He will help settle and advice based on what you need

 

Change to:
| Lo-Fi Version
0.0200sec    0.53    5 queries    GZIP Disabled
Time is now: 13th December 2025 - 12:14 AM