MBSA Renovation Permit, want to just ask estimate cost
|
TStaufoo
|
Sep 2 2021, 03:45 PM, updated 5y ago
|
Getting Started

|
Hi guys,
I want to submit application for renovation approval to just build 2 walls with window to cover the open space of the back of my house.
Because this is just destroy wall and build wall, I thought it's just considered interior works which dont require permit. But let's say I play it safe la just go and apply permit with MBSA, how much does the permit cost?
Thanks
|
|
|
|
|
|
TStaufoo
|
Sep 2 2021, 04:08 PM
|
Getting Started

|
Just the existing wall because the wall got those decorative gaps. We want to do full cover wall with window instead.
|
|
|
|
|
|
TStaufoo
|
Sep 2 2021, 04:28 PM
|
Getting Started

|
Oh just some further context. New house and housing area.
So means need to apply permit I guess. But what I'm actually really curious about is the permit cost.
Need to know the range so can budget
|
|
|
|
|
|
TStaufoo
|
Sep 2 2021, 08:55 PM
|
Getting Started

|
QUOTE(kennykck @ Sep 2 2021, 08:14 PM) Should be below RM1000 for permit. you may contact 0123876104 (En Amin) for help. https://forum.lowyat.net/topic/1898813/allThanks for this. I will contact and see how.
|
|
|
|
|
|
TStaufoo
|
Sep 2 2021, 08:56 PM
|
Getting Started

|
QUOTE(Q.V.RK @ Sep 2 2021, 07:33 PM) You just need to apply for Permit Bahan Binaan (RM648) and Tong Roro (RM880) At least need to utilise 1 tong roro (RM220), balance RM660 refundable, request upon completion. Make an appointment at Jabatan Bangunan, MBSA. Usually 10-12 days after you request for an appointment. Okay thanks for this. Will be a reference budget.
|
|
|
|
|
|
TStaufoo
|
Sep 8 2021, 04:02 PM
|
Getting Started

|
I want to submit an appointment schedule with MBSA but wah lau this form, which option.. hmm For house renovation. This post has been edited by taufoo: Sep 8 2021, 04:03 PM
|
|
|
|
|
|
TStaufoo
|
Dec 5 2021, 01:36 PM
|
Getting Started

|
From what I understand, they don't check and you don't have to inform them you complete the renovation. The validity of the permit is 1 year from date of approval.
The deposit u get back is from the tong roro.
|
|
|
|
|
|
TStaufoo
|
Dec 7 2021, 09:12 AM
|
Getting Started

|
Guys, just update.even after MBSA approval and sticker placed on front door, the worker received two "visitors" yesterday.
They claim to be officers but in normal clothing. Take some photos and say this wall cannot la that wall cannot la.
Contractor say is most likely come anyway to ask for duit kopi. But the worker didn't ask if from majlis or construction board (CI**)
Damn troublesome seriously. Apply or not also got ppl come kacau.
|
|
|
|
|