UPDATE:
Keys collected: March 2018
DEFECT CHECKING: COST RM750Defect checking: engaged third party defect inspectors, paid RM750 for 2 times inspection (before and after) and full defect report (for submission to developer)
1st defect inspection: end March. Quite a number of defects including hollow/paint spill/hairline crack/ceiling leaking but nothing very major.
Submitted defect list to developer, give spare key for them to repair defect.
2nd defect rectification inspection: June 2018. A number of defect not fully repaired such as hollow on certain areas. New leaking on celing detected.
Joint defect inspection with developer: June 2018. Developer insist that the tiles not hollow because less than 50%.. insist rectification of few areas with hollow tiles. Developer said will repair.
ARKITEK COST: COST RM2500
Plan drawing RM2500, to extend master, family area and bedroom 2 + 3 toilet
MAJLIS APPROVAL: COST RM856
Deposit RM500
Permit cost RM356
Renovation started: 3rd week of June
Master bedroom: hacking of wall, relocate sliding door and window, make bedroom bigger by 6 ft X 12 ft, with red brick wall and concrete slab COST RM8,800
Additional cost: 3ft wall slab accross (30 ft) COST RM1,600
As at 16 July- outer wall, slab done. Debris on porch cleared. In progress refixing the sliding door and casement window.
Family area upstairs: hacking of wall and move sliding door, closed off the balcony to make the family area bigger by 9.5 ft X 5 ft. red brick wall and install same timber flooring as existing COST RM8050
As at 16 July- outer and inner wall done. In progress, smoothing the wall and fixing the new 3 panel casement window.
Back area kitchen: concrete with tiles 30 ft X 10 ft (own tiles), metal alum composite roof and move water pipe to outer wall. COST RM10,700
Own tile guocera 1 ft x 2 ft x 185 pieces RM905
Floor trap tile design x 2 pcs RM76
Hanging lamp x 2 pcs, gate lamp inclusive of LED bulb COST RM230.60
As at 16 July- in progress to apply skirting, sink and pipe not fixed yet. Manhole cover and floor trap not done yet. Lamps not installed yet. Note: forgot to ask for at least one electric point at the back, wonder if it is necessary hmm.
Back wall fencing : 3ft steel fence X 40 ft COST RM3,200
As at 16 July- fence up. Touch up not completed yet
Interior design: RM2500 for a simple design for whole house (no 3D rendering), full spec of measurements and drawing. not done yet, a little slow..
As at 16 July- awfully quiet. I’m getting frustrated with their service and am thinking of just scrapping them and burn the progress payment made so far.
Laminated skylight : 15 ft X 9 ft laminated glass thickness 12.38mm, with aluminium louvers (half) and suspended with steel frame (no beam design). COST RM8,100
Waiting for them to call for site visit.
Shower screen for kids bathroom: 2.5 ft x 6 ft tempered glass (forgot to ask thickness) with aluminium base (to prevent spillage of water out of shower area. COST RM550
Waiting for them to call for site visit
Aircond:
Daikin r32 1HP Non inverter P series inclusive installation COST RM1250
Daikin r32 1HP Inverter Q series inclusive installation COST RM1550
Daikin R410A 1HP basic FFN (mini casette) COST RM1850
Installation early August
Wood deck and pebble wash- finding quotation.
Koi pond with 2 koi fish - COST RM3k
Landscape package (for pond area) - Dracena draco + ficus elastica, white pebble and 4-6 deco concrete slab COST RM700
Installation next week
Artificial grass- finding quotation and still thinking
Philippines grass- finding quotation and still thinking
Plaster ceiling- still thinking
Kitchen cabinet- still thinking
Lighting- still thinking
😂😂 many more still thinking!!
That’s all for updates!
Hi, mind to pm me the contact for the person who help to do the defect rectification?