Outline ·
[ Standard ] ·
Linear+
Investment EKOCHERAS @ JALAN CHERAS (V4) [MRT PROPERTY] [OT], Where Cheras becomes Mont'Jiulai
|
Jagalat
|
Oct 18 2015, 12:16 AM
|
|
QUOTE(Babizz @ Oct 17 2015, 06:46 PM) Did they indicate when 2a complete lately? december can? At this stage n pace if completed its jus how many months or yrs LAD.. actually u cn ask to speak to d technical ppl frm d office u know.. Jagalat kor why no pics ah?
Kindly inform if the pictures of previous page is not viewable. : --)
|
|
|
|
|
|
takezhiro
|
Oct 18 2015, 09:50 AM
|
Getting Started

|
Slowly better haha... Mrt hasn't completed yet
|
|
|
|
|
|
Jagalat
|
Oct 18 2015, 01:44 PM
|
|
A few months back, l was informed by a sub con personal working on the basement. He indicated that the EKC engineer(s) enforced strict requirements in casting the concrete. Thorough checking has been conducted by EKC engineer(s). Redo / rework would be imposed if mistake were found. I have no further details beyond this.
|
|
|
|
|
|
Jagalat
|
Oct 18 2015, 04:54 PM
|
|
What are all these EKC/EKV labeled barricades doing at the entrence of Tesco Midah? Earlier l tot the barricades were borrowed for MRT construction. Now it seems that the land in front of Tesco Midah (facing MRR2) is being cleared. Construction of the Uturn flyover?
|
|
|
|
|
|
deschan100
|
Oct 18 2015, 06:43 PM
|
Getting Started

|
QUOTE(Jagalat @ Oct 18 2015, 04:54 PM) What are all these EKC/EKV labeled barricades doing at the entrence of Tesco Midah? Earlier l tot the barricades were borrowed for MRT construction. Now it seems that the land in front of Tesco Midah (facing MRR2) is being cleared. Construction of the Uturn flyover?  correct, this is U turn fly over...heading to MRR2
|
|
|
|
|
|
ekorjiulai
|
Oct 18 2015, 10:50 PM
|
Getting Started

|
Anyone with any details on the next 10% payment please share alright... I think at this rate, seems like it works out better for those who didn't opt for the DIBS route (i.e. less interest charged when bank drawdown has been delayed).
|
|
|
|
|
|
8brian4
|
Oct 20 2015, 12:08 AM
|
Getting Started

|
dear guys, are EKOcheras units all sold out ? This post has been edited by 8brian4: Oct 20 2015, 12:15 AM
|
|
|
|
|
|
ryan@chua
|
Oct 20 2015, 12:13 AM
|
|
How's the site progress, any photos?
|
|
|
|
|
|
8brian4
|
Oct 20 2015, 12:22 AM
|
Getting Started

|
QUOTE(deschan100 @ Oct 18 2015, 06:43 PM) correct, this is U turn fly over...heading to MRR2 i do pass by this point. saw a piece of green land has been demolish. feel sad after looking at few old trees have been destroy. wondering our construction company why can't they adopt win-win situation by building u-turn and retain those trees..
|
|
|
|
|
|
Jagalat
|
Oct 20 2015, 12:26 AM
|
|
QUOTE(ryan@chua @ Oct 20 2015, 01:13 AM) How's the site progress, any photos? The latest photos were taken on 11-Oct, two pages back ....
|
|
|
|
|
|
ryan@chua
|
Oct 20 2015, 12:28 AM
|
|
QUOTE(Jagalat @ Oct 20 2015, 01:26 AM) The latest photos were taken on 11-Oct, two pages back .... Really slow. Cash background not strong enough
|
|
|
|
|
|
Jagalat
|
Oct 20 2015, 12:37 AM
|
|
QUOTE(8brian4 @ Oct 20 2015, 01:22 AM) i do pass by this point. saw a piece of green land has been demolish. feel sad after looking at few old trees have been destroy. wondering our construction company why can't they adopt win-win situation by building u-turn and retain those trees..  Was also wondering how this Uturn flyover will be... Will it allow cars from this flyover to enter Tesco Midah?
|
|
|
|
|
|
8brian4
|
Oct 20 2015, 12:53 AM
|
Getting Started

|
QUOTE(Jagalat @ Oct 20 2015, 12:37 AM) Was also wondering how this Uturn flyover will be... Will it allow cars from this flyover to enter Tesco Midah? hm..i don't think it will enter tesco midah, but surely will affect small road traffic beside tesco...unless need to clarify with EKOcheras somemore that MRR2 is down slope.quite dangerous..imagine..cars from MRR2 meet cars from Uturn flyover and cars from taman midah.. anyway..hopefully the company and DBKL or JKR plan the road with responsible This post has been edited by 8brian4: Oct 20 2015, 01:01 AM
|
|
|
|
|
|
restful increase
|
Oct 20 2015, 01:54 AM
|
|
QUOTE(8brian4 @ Oct 20 2015, 12:08 AM) dear guys, are EKOcheras units all sold out ?  Call Joe Wong at 0127073050 if u wanna buy. Joe is Ekochereas head of marketing.
|
|
|
|
|
|
mybenz
|
Oct 20 2015, 08:48 AM
|
|
the progress billing coming soon for block J...
|
|
|
|
|
|
mybenz
|
Oct 20 2015, 08:49 AM
|
|
QUOTE(8brian4 @ Oct 20 2015, 12:08 AM) dear guys, are EKOcheras units all sold out ?  not sold out..got bumi units ma
|
|
|
|
|
|
zugzwang
|
Oct 20 2015, 09:40 AM
|
Getting Started

|
QUOTE(mybenz @ Oct 20 2015, 08:49 AM) not sold out..got bumi units ma Are the bumi lots open for sales?
|
|
|
|
|
|
mybenz
|
Oct 20 2015, 10:08 AM
|
|
QUOTE(zugzwang @ Oct 20 2015, 09:40 AM) Are the bumi lots open for sales? not yet .. even if developer sell.. it will be higher price . that is for sure This post has been edited by mybenz: Oct 20 2015, 10:09 AM
|
|
|
|
|
|
GC 2014
|
Oct 20 2015, 02:28 PM
|
|
are you sure ? i am not that optimistic, at least on par with their initial launching price likely. QUOTE(mybenz @ Oct 20 2015, 10:08 AM) not yet .. even if developer sell.. it will be higher price . that is for sure
|
|
|
|
|
|
syarehey
|
Oct 20 2015, 04:28 PM
|
|
QUOTE(restful increase @ Oct 20 2015, 01:54 AM) Call Joe Wong at 0127073050 if u wanna buy. Joe is Ekochereas head of marketing. Dialed this number but it wasnt Joe Wong. wrong number
|
|
|
|
|