QUOTE(kabyss87 @ May 23 2016, 03:40 PM)
Greetings
iwubpreveFirst of all, thank you for sharing your expertise with us! i've been following the thread since it was here and now i have a question of my own in need of your expert opinion
Alright, recently i've been in debate with a fellow friend on the basis of how to determine a project's construction progress.
He was telling me that, base on his observation, most apartments should averagely built up between 1 to 1 1/2 Floor per month for a 30+- floor apartment (Regardless of the building size)
IMO, i think it was a bit of layman to measure progress with that way. But that is the only visual confirmation we can get to check the progress of a project.
so my question will be, what is the proper basis the one can use (As a homeowner or construction personnel) to determine the construction progress?
Thanks

QUOTE(WahBiang @ May 29 2016, 07:14 PM)
Would love to know this as well... on average after piling, what is the duration required to complete one floor??
Say if using simple example, SPA mentioned 36 months to complete and total got 36 floors. With this, does it mean that on average that developer need to complete at least 1.5 floor per month so that at least have spare time say half year for painting, furnishing with window etc, garden?
hi, sorry for "abandon" this thread for a while.

actually is like the chart below, i try to put a simple chart so u can understand better. below is a chart for structure work. so for a building, we use the plan view and divide into 2 zone, namely zone A & zone B. if bigger site will divide into more zone. so each floor we have zone A and zone B. so horizontal denote as weeks, vertical is level of building. sequence of work is like this, complete level 1 zone A, only move to level 1 zone B. it look like u need 4 week to complete a floor, but in fact every 2 weeks u complete a floor. reason is because u have 2 team of workers. 1 team only do zone A, another do zone B. so level 1 zone A complete, then they move to level 2 zone a. in construction time is money. so have to plan the work within schedule. the chart only display structure. imagine u have all work included, the chart would be very massive and complex. u have facade, architectural work etc and different work might have different sequence. average there would be about 40 trades of work in each project. imagine this chart show 1 trade, put 40 trade inside would be really complicated. but this is important because it help u to plan the work, and at the same time it can be as a reference of claiming extension of time etc.