QUOTE(jolipoli81 @ Apr 11 2015, 10:38 AM)
My subcon did not follow install 2 out of the 3 doors as shown in the photo, saying they were very rush for other job and couldnt get enough lintel at that time.
When or above what height does a lintel be required to be installed? What are the consequences if a lintel is not install like the photo shown?
*
all the door must have lintel. if not soon or later it will sag as the load magnitude toward the top of door frame sweat.gif

regarding and height, that's the lintel when ur brickwall is high. that 1 u a can refer to the "general note" of drawing. but definitely in ur case it has nothing to do with the height. all the door require lintel la. sweat.gif

lintel just cast insitu at site, after cure then only put on top of frame. easy job how come cannot find? sweat.gif of course u need to pay separately so subcon for the lintel he do for u.

This post has been edited by iwubpreve: Apr 11 2015, 01:38 PM
TSiwubpreve
post Apr 11 2015, 01:39 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(RoyalDeviLz @ Apr 8 2015, 11:59 AM)
Do you have company that need KDN approval for construction workers? Foreign workers
*
no. why?
TSiwubpreve
post Apr 11 2015, 01:46 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(poooky @ Mar 13 2015, 03:51 PM)
who makes the most moolah listing 1 to 10?? director of construction company? the subcons? the city officials/authorities?? suppliers?

how much budget tat provided for the big projects is songlap from the top officials to the lowly wager?

how much is actual markup from price of land bought to build house n necessary infrastructure to selling of the lot n building??
*
varies. i can tell u this markup go through many level already. for developer, 25% is profit while 75% is expenses to build the building up.

Out of 75%, 60% is main con and the balance 15% goes to consultant fee, local authority contribution, marketing & advertising, and etc.

Out of 60%, 54% is actual cost given to subcon fixing cost and maincon supervision cost while 6% is main con profit.

out of 54%, 46% is the material and labour subcon use while 8% is subcon profit.

in conclusion, actual material and labour cost to build is just 46% sweat.gif

of course this is different from project to project biggrin.gif
TSiwubpreve
post Apr 11 2015, 01:47 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(AmpBuster @ Mar 13 2015, 08:14 PM)
Dunno if relevant, but how much does it cost to lay 1000 km of fibre?
*
no idea. need basis to estimate. like excavation cost how much per km, then lay of fibre cable how much per km, then how much of backfill and premix tar road per km. the cost times 1000 is the answer. this is how QS estimate the price.
TSiwubpreve
post Apr 11 2015, 01:48 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Runec @ Mar 16 2015, 12:29 AM)
I have a 0.67 acre project in Rungkup, Perak.

Do you have contacts for any civil and structural engineers in near there? Teluk Intan would be the nearest town.

Contacts for sub-contractors would be good also.

Thanks in advance
*
no idea on those remote place 1 sweat.gif
TSiwubpreve
post Apr 11 2015, 01:53 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(jolipoli81 @ Mar 19 2015, 03:30 PM)
say if the structural work already almost complete, then Architect say need windows coping as rain water might splash in. Main con ask subcon to cast the coping.

1. Which method will he use? Using lintel or cast it separately?

2. Subcon want to measure by kongsi kong rather than in meter run, because subcon said cannot cover. How to argue with him?
*
actually there are poly foam coping. light and easy to fix. but of course provided Architect accepted this proposal sweat.gif

look in the contract of variation work clauses. it allow main con to claim in daywork too if the work cannot be measured. but this case u can measure. so cannot claim daywork, but u can convert daywork to meter run. definitely the ordinary process of work is disrupted therefore different price have to be allow to cater such variation. u need to justify this to client. if client say can do at cheap cost, tell him pass u that subcon. u use that subcon and mark up 15% as allow in contract. PAM standard form of contract allow 15% mark up provided the subcon invoice shown to client. of course this best to be done b4 u physically execute the work.
TSiwubpreve
post Apr 11 2015, 01:55 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(memekfalui @ Mar 19 2015, 11:53 PM)
Construction material and tools source from China are at dirt cheap price if buy in bulk, true or false?
*
yes. lot of material is cheap if u can import in bulk quantities. Sanitary wares and fitting, glass, aluminium extrusion, tile, steel bar and etc. quality is on par as well.
TSiwubpreve
post Apr 11 2015, 01:55 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(vin_ann @ Mar 20 2015, 06:50 AM)
Construction materials are GST Standard rated right?

When developer unable to charge gst to house buyer, they will build in gst cost into the house price.

This will happens right?
*
developer won't make rugi business. for sure they factor in the GST in the selling price la sweat.gif
TSiwubpreve
post Apr 11 2015, 01:56 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Slyp @ Mar 23 2015, 03:03 PM)
is construction industry a better career development when compared to accounting/finance?
*
think account / finance is better career. imagine work at bank bonus 10 months, this will never happen at contractor sweat.gif
TSiwubpreve
post Apr 11 2015, 01:57 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(twins9 @ Mar 24 2015, 11:57 AM)
Mech engineer, 5 years experience, pay rm42k a year, is that a lot lower than civil engineer with similar 5 years experience?
*
bro, fresh engineer get RM2.6k at consultant. if contractor RM3k for fresh graduate is easy la sweat.gif got degree in mechanical engineering right?
TSiwubpreve
post Apr 11 2015, 01:59 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(timizama @ Mar 25 2015, 03:48 PM)
how much does it cost to make a swimming pool
about 1.6m deep, 12m long 6m wide?
plus the generator, filter mechanism and others
Quote me the cheapest price to highest?
*
better get a contractor to quote u. it involve various of specialist. sand filter, water pump supplier, swimming pool builder, M&E contractor fixing the thing and etc.
TSiwubpreve
post Apr 11 2015, 01:59 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Protagonist @ Mar 26 2015, 07:21 PM)
Boy, I pm you later  brows.gif
*
bro, what kang tao u have? do let me know brows.gif
TSiwubpreve
post Apr 11 2015, 02:01 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(blek @ Apr 5 2015, 09:56 PM)
How to become safety officers?
How to get the license?
Any requirement needed?
*
go attend seminar. obtain the green book. if not mistaken is niosh department. but nowadays they require degree in ESH would be a good stepping stone. Environment, safety and health.
TSiwubpreve
post Apr 13 2015, 12:40 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(soulmate @ Apr 13 2015, 11:47 AM)
my friend took this QS course in uni

how good is job prospect for a QS in construction industry, any recommendation for which comp. or kind of related job for a fresh grad QS to apply?

thanks
*
Langdon Seah, KPK. for gain experience.

This post has been edited by iwubpreve: Apr 13 2015, 12:40 PM
TSiwubpreve
post Jul 13 2015, 10:36 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
long time didn't reply in this thread. will reply as much as I can sweat.gif
TSiwubpreve
post Jul 13 2015, 10:38 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(metaldragon @ Jul 13 2015, 02:20 AM)
O-ring chop for the ramp in my building are done badly.. not in alligned.. any way to rectify this problem?
*
the only way to do is to hack and redo bro. not worth it. the o-ring groove for better wheel gripping so if u don't mind abt the appearance, just leave it there smile.gif
TSiwubpreve
post Jul 13 2015, 11:01 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(rickyro @ Jul 10 2015, 03:29 PM)
Till today... I can't really differentiate an Air Valve, Sluice Valve, Scour Valve... Can someone explain it to me in layman terms please ~~ Thanks
*
ic. I no idea either. but these are more on gas and plumbing trade smile.gif
TSiwubpreve
post Jul 13 2015, 11:02 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Tavia88 @ Jun 20 2015, 10:17 PM)
Hi, TS.

Are you an X developer or Project manager? biggrin.gif
*
what mean X developer?
TSiwubpreve
post Jul 13 2015, 11:08 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Soft Rice King @ Jun 12 2015, 10:00 AM)
is it true that 1 ton of raw steel cost price is only RM1.5k?
*
QUOTE(HibikiYoh @ Jun 12 2015, 10:06 AM)
I have a batch of T10 bars looking for buyers. What is the market rate now?
*
about RM1,950 per tonne bro (supply and deliver only)
TSiwubpreve
post Jul 13 2015, 11:10 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Petre @ Jun 11 2015, 05:12 PM)
i know an architect friend, then another friend with a few lands

how can i setup something, like a mini developer thing...
*
oic. u need investor bro. got land but no money also cannot develop. and beside that, u need a 1stop contractor. that he can help u do submission and etc. Architect basically alone cannot do much because this is not just about architect, u also need engineer & planner. all these can get through "1stop contractor"