Outline ·
[ Standard ] ·
Linear+
Windows On The Park • WOTP @ Cheras South (V2), By Selangor Dredging Berhad
|
TSHELLO HELLO
|
Feb 15 2015, 12:15 PM
|
|
Neighbor lumiere land masih use as football field. Sibeh Jialat lor. Ocr Please start work fast fast.
Yeah!! access baru from Wotp to hap seng star.
Woh saw the link bridge between gym room and function room.
This post has been edited by HELLO HELLO: Feb 15 2015, 12:16 PM
|
|
|
|
|
|
SalvationArmy
|
Feb 15 2015, 01:04 PM
|
|
QUOTE(HELLO HELLO @ Feb 15 2015, 12:15 PM) Neighbor lumiere land masih use as football field. Sibeh Jialat lor. Ocr Please start work fast fast. Yeah!! access baru from Wotp to hap seng star. Woh saw the link bridge between gym room and function room. Whoa, well spotted on the bridge between gym and function room! I'm not sure when OCR is thinking of starting their pilling work. Probably they are still waiting for a better take up rate before they ground break. As I understand, the financing banks will only release a certain % of funds to the developer based on confirmed sales to date. I think everyone living in WOTP will be affected with the sound and probably cracks on the wall once the work starts. This post has been edited by SalvationArmy: Feb 15 2015, 01:09 PM
|
|
|
|
|
|
SalvationArmy
|
Feb 15 2015, 01:09 PM
|
|
QUOTE(crystal_kit85 @ Feb 15 2015, 11:47 AM) I can't help. It noticed the planted trees are drying up. Given the uncertainty of weather conditions. Hope that by the time of completion, everything would be perfect. When we were there yesterday, the whole area was very dusty due to the ongoing construction. In fact, I'm surprised the trees planted near the gym area survived at all.
|
|
|
|
|
|
felixmask
|
Feb 15 2015, 02:58 PM
|
|
QUOTE(SalvationArmy @ Feb 15 2015, 01:09 PM) When we were there yesterday, the whole area was very dusty due to the ongoing construction. In fact, I'm surprised the trees planted near the gym area survived at all.  Last month raining season. During draught season, we pray someone will water the poor plant.
|
|
|
|
|
|
danielisme
|
Feb 15 2015, 10:29 PM
|
|
Piling sound still ok . Construction pouring concrete at until 3am more worst . The cement mixture sound .
|
|
|
|
|
|
planc
|
Feb 16 2015, 11:07 AM
|
|
QUOTE(SalvationArmy @ Feb 15 2015, 12:04 PM) Whoa, well spotted on the bridge between gym and function room! I'm not sure when OCR is thinking of starting their pilling work. Probably they are still waiting for a better take up rate before they ground break. As I understand, the financing banks will only release a certain % of funds to the developer based on confirmed sales to date. I think everyone living in WOTP will be affected with the sound and probably cracks on the wall once the work starts.  Cracks on wall for the landed next to casagreen last time.
|
|
|
|
|
|
TSHELLO HELLO
|
Feb 17 2015, 09:17 AM
|
|
From Balakong Hakka village can see Wotp block A and B.
From lake valley only can see block A.
Block c brick work almost done. Very soon can start cementing exterior and painting.....
New shops lot near block C looks like vp soon.
This post has been edited by HELLO HELLO: Feb 17 2015, 09:18 AM
|
|
|
|
|
|
WilberSc
|
Feb 17 2015, 01:26 PM
|
|
QUOTE(HELLO HELLO @ Feb 17 2015, 09:17 AM) From Balakong Hakka village can see Wotp block A and B. From lake valley only can see block A. Block c brick work almost done. Very soon can start cementing exterior and painting..... New shops lot near block C looks like vp soon. New shop lot near block C? Do you mean the shop lots at Taman Sutera?
|
|
|
|
|
|
TSHELLO HELLO
|
Feb 17 2015, 08:55 PM
|
|
QUOTE(WilberSc @ Feb 17 2015, 01:26 PM) New shop lot near block C? Do you mean the shop lots at Taman Sutera? Yes
|
|
|
|
|
|
starex80
|
Feb 18 2015, 01:21 AM
|
|
passby taman sutera at night. quiet till scary.
The shoplot beside the 2.5 storey link house almost 1 year no open...
|
|
|
|
|
|
TSHELLO HELLO
|
Mar 12 2015, 05:49 PM
|
|
finally all 3 blocks reach to the top liao.
Block C all brick works done liao. now cementing.
block A & B, now can see the shape of the penthouse liao.
This post has been edited by HELLO HELLO: Mar 12 2015, 05:49 PM
|
|
|
|
|
|
arries
|
Mar 12 2015, 10:18 PM
|
New Member
|
|
|
|
|
|
|
ahmai2332
|
Mar 13 2015, 09:53 AM
|
|
Look like slow down.
November need to complete. Can make it?
|
|
|
|
|
|
peri peri
|
Mar 13 2015, 10:16 AM
|
|
QUOTE(ahmai2332 @ Mar 13 2015, 09:53 AM) Look like slow down. November need to complete. Can make it? partial handling over for block C, possible
|
|
|
|
|
|
calvin989898
|
Mar 13 2015, 10:26 AM
|
|
QUOTE(ahmai2332 @ Mar 13 2015, 09:53 AM) Look like slow down. November need to complete. Can make it? As of now , they still target to handover in Nov. In May or June soon they will have show unit at block b.
|
|
|
|
|
|
felixmask
|
Mar 13 2015, 11:35 AM
|
|
QUOTE(calvin989898 @ Mar 13 2015, 10:26 AM) As of now , they still target to handover in Nov. In May or June soon they will have show unit at block b. You mean mock unit ? Only buyer can can see, outsider can go in to see?
|
|
|
|
|
|
TSHELLO HELLO
|
Mar 13 2015, 11:58 AM
|
|
QUOTE(felixmask @ Mar 13 2015, 11:35 AM) You mean mock unit ? Only buyer can can see, outsider can go in to see? Masih ada unit for sale. Should be open for public 6c.
|
|
|
|
|
|
calvin989898
|
Mar 13 2015, 03:15 PM
|
|
Preview of the landskape.. 3 layers ... Attached thumbnail(s)
|
|
|
|
|
|
HarpArtist
|
Mar 13 2015, 03:24 PM
|
|
QUOTE(HELLO HELLO @ Mar 13 2015, 11:58 AM) Masih ada unit for sale. Should be open for public 6c. Any idea what's developer price and package now?
|
|
|
|
|