advertisement for the Capella tower is quite aggressive on FB, Iproperty and almost everywhere, wondering why after so long still not yet sold out?

pricing too expensive or the developer reputation no good?
Investor12
post Aug 22 2016, 12:39 PM

Getting Started
**
Junior Member
72 posts

Joined: Jul 2016
Hi All, what is your view on the Capella tower? The sales seem slow for this project.

The location and price should be okay in this area, so why no one seem interested? I am seriously consider buying
TSHaoYuan
post Aug 22 2016, 09:20 PM

Kai Qi Baby
******
Senior Member
1,401 posts

Joined: Oct 2008
From: Bandar Sunway



QUOTE(Investor12 @ Aug 22 2016, 12:39 PM)
Hi All, what is your view on the Capella tower? The sales seem slow for this project.

The location and price should be okay in this area, so why no one seem interested? I am seriously consider buying
*
honestly the area is good, just that the development progress is very slow.
SUSempatTan
post Aug 22 2016, 09:44 PM

Regular
******
Senior Member
1,678 posts

Joined: Mar 2016


QUOTE(Investor12 @ Aug 22 2016, 12:39 PM)
Hi All, what is your view on the Capella tower? The sales seem slow for this project.

The location and price should be okay in this area, so why no one seem interested? I am seriously consider buying
*
Just buy it. This part is d future of PJ.
Investor12
post Aug 22 2016, 10:33 PM

Getting Started
**
Junior Member
72 posts

Joined: Jul 2016
Thats what i thought too, the location is not bad, pricing also quite close to is neighbour Jaya One sub-sales and the newly launch Biji at s17, so what is the reason behind the slow sales? After two years of launching, only a handful has been sold, this make me wondering whats wrong with this project
TSHaoYuan
post Aug 25 2016, 02:48 PM

Kai Qi Baby
******
Senior Member
1,401 posts

Joined: Oct 2008
From: Bandar Sunway



This is a large mixed development project, all small unit (Block D&E) already sold. currently only left with Block C, the price is quite exp (750K++), that's the reason why the sales is slow (just my opinion).
myproblem
post Aug 25 2016, 03:56 PM

Casual
***
Junior Member
363 posts

Joined: Jul 2011
When u see netting around means no end..... could be forever.

Once they dismantle the netting and with painting (exterior) means they will need another 1.5 to 2 years

Once they packed everything as in cleared the site they will need another 6-8 months
Wazzzap
post Sep 20 2016, 04:03 PM

On my way
****
Junior Member
506 posts

Joined: Jan 2003



i signed S & P with them since 2011, any advice what action should be taken? it is supposed to be completed by end of 2014 as stated in the agreement before implementation of GST. Now we kena charge GST.

and the f8cking bank disburse the amount to them already because they claimed external plastering whereby now it is still covered with green netting.

This post has been edited by Wazzzap: Sep 20 2016, 04:04 PM
TSHaoYuan
post Sep 20 2016, 06:23 PM

Kai Qi Baby
******
Senior Member
1,401 posts

Joined: Oct 2008
From: Bandar Sunway



QUOTE(Wazzzap @ Sep 20 2016, 04:03 PM)
i signed S & P with them since 2011, any advice what action should be taken? it is supposed to be completed by end of 2014 as stated in the agreement before implementation of GST. Now we kena charge GST.

and the f8cking bank disburse the amount to them already because they claimed external plastering whereby now it is still covered with green netting.
*
You SPA mention to be complete by Dec 2014? i tot they already put in S&P 4 years time?
inviyee
post Nov 6 2016, 09:55 AM

New Member
*
Newbie
3 posts

Joined: Dec 2012
Mine's signed on the May 2013 and indicated 48 months (4 years). So i guess they have to deliver it by May 2017. If not by then, I guess we all can do something about it.
TSHaoYuan
post Nov 9 2016, 01:44 PM

Kai Qi Baby
******
Senior Member
1,401 posts

Joined: Oct 2008
From: Bandar Sunway



QUOTE(inviyee @ Nov 6 2016, 09:55 AM)
Mine's signed on the May 2013 and indicated 48 months (4 years). So i guess they have to deliver it by May 2017. If not by then, I guess we all can do something about it.
*
According to SPA, the developer need to compensate the purchaser 10% p.a interest based on the Purchase price if they failed to deliver the property on time. But looking at the progress of the development, it is likely to delay.
TSHaoYuan
post Jan 25 2017, 10:00 PM

Kai Qi Baby
******
Senior Member
1,401 posts

Joined: Oct 2008
From: Bandar Sunway



Any other updates on this project?
Poh Smith
post Mar 16 2017, 11:30 PM

New Member
*
Newbie
2 posts

Joined: Mar 2017
Last call, developer just release few unit , interesting package, who is interest ? Please PM me.
ZzZzz...
post Mar 19 2017, 11:21 AM

Art of Sleeping
******
Senior Member
1,787 posts

Joined: Nov 2008


Block capella is commercial or residential title?
Angel On Fire
post Mar 27 2017, 04:45 PM

Getting Started
**
Junior Member
77 posts

Joined: Mar 2006
From: PeeJay


What happened??? Progress seems very slow. Pacific 63 and Pacific Star supposed to VP this year?
TSHaoYuan
post Mar 27 2017, 08:15 PM

Kai Qi Baby
******
Senior Member
1,401 posts

Joined: Oct 2008
From: Bandar Sunway



QUOTE(Angel On Fire @ Mar 27 2017, 04:45 PM)
What happened???  Progress seems very slow. Pacific 63 and Pacific Star supposed to VP this year?
*
I think they going to delay in handover the property to us.
Based on contact they need to pay us 10% of the property price as our compensation.
Looking for lawyer to find out more about this.


AWhite
post Apr 11 2017, 03:40 PM

New Member
*
Junior Member
13 posts

Joined: Dec 2011
Parking.

Don't understand why so slow for this development.

TSHaoYuan
post Apr 11 2017, 09:15 PM

Kai Qi Baby
******
Senior Member
1,401 posts

Joined: Oct 2008
From: Bandar Sunway



QUOTE(AWhite @ Apr 11 2017, 03:40 PM)
Parking.

Don't understand why so slow for this development.
*
When u purchase? We can claim the developer 10% per annum if they delay in handover the house to us right
intoxicat
post Apr 12 2017, 09:50 AM

Getting Started
**
Junior Member
115 posts

Joined: Mar 2017
QUOTE(AWhite @ Apr 11 2017, 03:40 PM)
Parking.

Don't understand why so slow for this development.
*
Reason? Simple....sl aka $
Inv 3699
post Apr 14 2017, 03:08 PM

On my way
****
Senior Member
502 posts

Joined: Oct 2012


QUOTE(Angel On Fire @ Mar 27 2017, 04:45 PM)
What happened???  Progress seems very slow. Pacific 63 and Pacific Star supposed to VP this year?
*
I bought the pacific 63 in Dec 2011, til last Dec 2016...

Is was ald 5 FULL years...

It was ald over the rgpt period....

But still, not yet completed... funny.. yawn.gif

the pic said "should be" vp by Feb then delay to April then....maybe June or July now...