Pacific Star Section 13, Star Head office moving here
|
Investor12
|
Aug 14 2016, 02:59 AM
|
Getting Started

|
advertisement for the Capella tower is quite aggressive on FB, Iproperty and almost everywhere, wondering why after so long still not yet sold out?
pricing too expensive or the developer reputation no good?
|
|
|
|
|
|
Investor12
|
Aug 22 2016, 12:39 PM
|
Getting Started

|
Hi All, what is your view on the Capella tower? The sales seem slow for this project.
The location and price should be okay in this area, so why no one seem interested? I am seriously consider buying
|
|
|
|
|
|
TSHaoYuan
|
Aug 22 2016, 09:20 PM
|
|
QUOTE(Investor12 @ Aug 22 2016, 12:39 PM) Hi All, what is your view on the Capella tower? The sales seem slow for this project. The location and price should be okay in this area, so why no one seem interested? I am seriously consider buying honestly the area is good, just that the development progress is very slow.
|
|
|
|
|
|
SUSempatTan
|
Aug 22 2016, 09:44 PM
|
|
QUOTE(Investor12 @ Aug 22 2016, 12:39 PM) Hi All, what is your view on the Capella tower? The sales seem slow for this project. The location and price should be okay in this area, so why no one seem interested? I am seriously consider buying Just buy it. This part is d future of PJ.
|
|
|
|
|
|
Investor12
|
Aug 22 2016, 10:33 PM
|
Getting Started

|
Thats what i thought too, the location is not bad, pricing also quite close to is neighbour Jaya One sub-sales and the newly launch Biji at s17, so what is the reason behind the slow sales? After two years of launching, only a handful has been sold, this make me wondering whats wrong with this project
|
|
|
|
|
|
TSHaoYuan
|
Aug 25 2016, 02:48 PM
|
|
This is a large mixed development project, all small unit (Block D&E) already sold. currently only left with Block C, the price is quite exp (750K++), that's the reason why the sales is slow (just my opinion).
|
|
|
|
|
|
myproblem
|
Aug 25 2016, 03:56 PM
|
|
When u see netting around means no end..... could be forever.
Once they dismantle the netting and with painting (exterior) means they will need another 1.5 to 2 years
Once they packed everything as in cleared the site they will need another 6-8 months
|
|
|
|
|
|
Wazzzap
|
Sep 20 2016, 04:03 PM
|
|
i signed S & P with them since 2011, any advice what action should be taken? it is supposed to be completed by end of 2014 as stated in the agreement before implementation of GST. Now we kena charge GST.
and the f8cking bank disburse the amount to them already because they claimed external plastering whereby now it is still covered with green netting.
This post has been edited by Wazzzap: Sep 20 2016, 04:04 PM
|
|
|
|
|
|
TSHaoYuan
|
Sep 20 2016, 06:23 PM
|
|
QUOTE(Wazzzap @ Sep 20 2016, 04:03 PM) i signed S & P with them since 2011, any advice what action should be taken? it is supposed to be completed by end of 2014 as stated in the agreement before implementation of GST. Now we kena charge GST. and the f8cking bank disburse the amount to them already because they claimed external plastering whereby now it is still covered with green netting. You SPA mention to be complete by Dec 2014? i tot they already put in S&P 4 years time?
|
|
|
|
|
|
inviyee
|
Nov 6 2016, 09:55 AM
|
New Member
|
Mine's signed on the May 2013 and indicated 48 months (4 years). So i guess they have to deliver it by May 2017. If not by then, I guess we all can do something about it.
|
|
|
|
|
|
TSHaoYuan
|
Nov 9 2016, 01:44 PM
|
|
QUOTE(inviyee @ Nov 6 2016, 09:55 AM) Mine's signed on the May 2013 and indicated 48 months (4 years). So i guess they have to deliver it by May 2017. If not by then, I guess we all can do something about it. According to SPA, the developer need to compensate the purchaser 10% p.a interest based on the Purchase price if they failed to deliver the property on time. But looking at the progress of the development, it is likely to delay.
|
|
|
|
|
|
TSHaoYuan
|
Jan 25 2017, 10:00 PM
|
|
Any other updates on this project?
|
|
|
|
|
|
Poh Smith
|
Mar 16 2017, 11:30 PM
|
New Member
|
Last call, developer just release few unit , interesting package, who is interest ? Please PM me.
|
|
|
|
|
|
ZzZzz...
|
Mar 19 2017, 11:21 AM
|
|
Block capella is commercial or residential title?
|
|
|
|
|
|
Angel On Fire
|
Mar 27 2017, 04:45 PM
|
Getting Started

|
What happened??? Progress seems very slow. Pacific 63 and Pacific Star supposed to VP this year?
|
|
|
|
|
|
TSHaoYuan
|
Mar 27 2017, 08:15 PM
|
|
QUOTE(Angel On Fire @ Mar 27 2017, 04:45 PM) What happened??? Progress seems very slow. Pacific 63 and Pacific Star supposed to VP this year? I think they going to delay in handover the property to us. Based on contact they need to pay us 10% of the property price as our compensation. Looking for lawyer to find out more about this.
|
|
|
|
|
|
AWhite
|
Apr 11 2017, 03:40 PM
|
New Member
|
Parking.
Don't understand why so slow for this development.
|
|
|
|
|
|
TSHaoYuan
|
Apr 11 2017, 09:15 PM
|
|
QUOTE(AWhite @ Apr 11 2017, 03:40 PM) Parking. Don't understand why so slow for this development. When u purchase? We can claim the developer 10% per annum if they delay in handover the house to us right
|
|
|
|
|
|
intoxicat
|
Apr 12 2017, 09:50 AM
|
Getting Started

|
QUOTE(AWhite @ Apr 11 2017, 03:40 PM) Parking. Don't understand why so slow for this development. Reason? Simple....sl aka $
|
|
|
|
|
|
Inv 3699
|
Apr 14 2017, 03:08 PM
|
|
QUOTE(Angel On Fire @ Mar 27 2017, 04:45 PM) What happened??? Progress seems very slow. Pacific 63 and Pacific Star supposed to VP this year? I bought the pacific 63 in Dec 2011, til last Dec 2016... Is was ald 5 FULL years... It was ald over the rgpt period.... But still, not yet completed... funny.. the pic said "should be" vp by Feb then delay to April then....maybe June or July now...
|
|
|
|
|