Hi guys,

I want to submit application for renovation approval to just build 2 walls with window to cover the open space of the back of my house.

Because this is just destroy wall and build wall, I thought it's just considered interior works which dont require permit.
But let's say I play it safe la just go and apply permit with MBSA, how much does the permit cost?

Thanks

mini orchard
post Sep 2 2021, 03:58 PM

10k Club
********
All Stars
14,511 posts

Joined: Sep 2017
QUOTE(taufoo @ Sep 2 2021, 03:45 PM)
Hi guys,

I want to submit application for renovation approval to just build 2 walls with window  to cover the open space of the back of my house. 

Because this is just destroy wall and build wall, I thought it's just considered interior works which dont require permit.
But let's say I play it safe la just go and apply permit with MBSA, how much does the permit cost?

Thanks
*
You want to demolish old and rebuild ?
TStaufoo
post Sep 2 2021, 04:08 PM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
Just the existing wall because the wall got those decorative gaps.
We want to do full cover wall with window instead.


mini orchard
post Sep 2 2021, 04:25 PM

10k Club
********
All Stars
14,511 posts

Joined: Sep 2017
QUOTE(taufoo @ Sep 2 2021, 04:08 PM)
Just the existing wall because the wall got those decorative gaps.
We want to do full cover wall with window instead.
*
If the existing extension was approved previously, then not necesssry. Otherwise, need to submit plan and pay a fine for the old extension without approval.

Not necessary to demolish the entire wall. The contractor will know what to do. This small job, few days can kaotim unless you are also doing other things.

Unless neighbour complain or if you are unlucky mbsa pass through your area, they will check on your house. If is at back lane area, normally not obvious unless you have a roro bin infront of the house.



TStaufoo
post Sep 2 2021, 04:28 PM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
Oh just some further context.
New house and housing area.

So means need to apply permit I guess.
But what I'm actually really curious about is the permit cost.

Need to know the range so can budget
mini orchard
post Sep 2 2021, 04:41 PM

10k Club
********
All Stars
14,511 posts

Joined: Sep 2017
QUOTE(taufoo @ Sep 2 2021, 04:28 PM)
Oh just some further context.
New house and housing area.

So means need to apply permit I guess.
But what I'm actually really curious about is the permit cost.

Need to know the range so can budget
*
If you are not adding any new wall or structure on empty land, then not necessary. For eg, if just to change the kitchen window, then is not require.

I cant be sure now, but mbsa could have those standard ready plans for inter unit. Buy the plan and ask the contractor to follow. My guess it could cost few hundreds to maybe slightly above a thousand for everything.

A new drawing will cost about 2k+.all in.
Q.V.RK
post Sep 2 2021, 07:33 PM

Getting Started
**
Junior Member
77 posts

Joined: Nov 2018
QUOTE(taufoo @ Sep 2 2021, 03:45 PM)
Hi guys,

I want to submit application for renovation approval to just build 2 walls with window  to cover the open space of the back of my house. 

Because this is just destroy wall and build wall, I thought it's just considered interior works which dont require permit.
But let's say I play it safe la just go and apply permit with MBSA, how much does the permit cost?

Thanks
*
You just need to apply for Permit Bahan Binaan (RM648) and Tong Roro (RM880)

At least need to utilise 1 tong roro (RM220), balance RM660 refundable, request upon completion.

Make an appointment at Jabatan Bangunan, MBSA. Usually 10-12 days after you request for an appointment.
kennykck
post Sep 2 2021, 08:14 PM

!!!~~<((Bankai))>~~!!!
******
Senior Member
1,711 posts

Joined: Sep 2006


QUOTE(taufoo @ Sep 2 2021, 03:45 PM)
Hi guys,

I want to submit application for renovation approval to just build 2 walls with window  to cover the open space of the back of my house. 

Because this is just destroy wall and build wall, I thought it's just considered interior works which dont require permit.
But let's say I play it safe la just go and apply permit with MBSA, how much does the permit cost?

Thanks
*
Should be below RM1000 for permit. you may contact 0123876104 (En Amin) for help.

https://forum.lowyat.net/topic/1898813/all

TStaufoo
post Sep 2 2021, 08:55 PM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
QUOTE(kennykck @ Sep 2 2021, 08:14 PM)
Should be below RM1000 for permit. you may contact 0123876104 (En Amin) for help.

https://forum.lowyat.net/topic/1898813/all
*
Thanks for this. I will contact and see how.
TStaufoo
post Sep 2 2021, 08:56 PM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
QUOTE(Q.V.RK @ Sep 2 2021, 07:33 PM)
You just need to apply for Permit Bahan Binaan (RM648) and Tong Roro (RM880)

At least need to utilise 1 tong roro (RM220), balance RM660 refundable, request upon completion.

Make an appointment at Jabatan Bangunan, MBSA. Usually 10-12 days after you request for an appointment.
*
Okay thanks for this. Will be a reference budget.
TStaufoo
post Sep 8 2021, 04:02 PM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
I want to submit an appointment schedule with MBSA but wah lau this form, which option.. hmm

For house renovation.

user posted image


This post has been edited by taufoo: Sep 8 2021, 04:03 PM
Q.V.RK
post Sep 8 2021, 07:48 PM

Getting Started
**
Junior Member
77 posts

Joined: Nov 2018
QUOTE(taufoo @ Sep 8 2021, 04:02 PM)
I want to submit an appointment schedule with MBSA but wah lau this form, which option.. hmm

For house renovation.

user posted image
*
As mentioned in my post, Jabatan Bangunan. Nowadays, will easily take 10 days before you receive any email or call to notify your appointment.

KLKN_Views
post Sep 9 2021, 10:36 AM

Getting Started
**
Junior Member
116 posts

Joined: Sep 2021
QUOTE(Q.V.RK @ Sep 8 2021, 07:48 PM)
As mentioned in my post, Jabatan Bangunan. Nowadays, will easily take 10 days before you receive any email or call to notify your appointment.
*
We've been waiting for more than 14 days now, no email or sms. When we checked with MBSA again, they said have to wait since its a long queue - sigh
JasonTheGreat
post Oct 15 2021, 11:08 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
Want to ask if anyone experienced kena saman by MBSA for reno exceeding anjakan. For example apply for RC Gutter but built GI gutter and thereafter exceed 1 ft from the max wall.

Heard it’s 20x which is Rm6000 saman. Will they let you keep the desig after or ask to roboh.
dlttdltt
post Oct 16 2021, 10:45 AM

On my way
****
Junior Member
558 posts

Joined: Jul 2017


If change floor tiles, change window frame, change front security door and paint the whole house, do we still need to apply for Mbsa permit ? Maybe will also wall between hall and dry kitchen.
knight_hawk
post Oct 16 2021, 10:57 AM

Getting Started
**
Junior Member
191 posts

Joined: Aug 2009


Majlis kuala langat charged me almost RM5k for permit to extend kitchen. Both neighbour already got wall, mine is just one wall also kena 5k. Need to engage their consultant only can. If not their consultant, will drag like crazy.
utellme
post Oct 16 2021, 03:06 PM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(JasonTheGreat @ Oct 15 2021, 11:08 PM)
Want to ask if anyone experienced kena saman by MBSA for reno exceeding anjakan. For example apply for RC Gutter but built GI gutter and thereafter exceed 1 ft from the max wall.

Heard it’s 20x which is Rm6000 saman. Will they let you keep the desig after or ask to roboh.
*
More than 80% of the home backyard or kitchen extension at my neighborhood didn't compliant to the mbsa guidelines. For me I will go for RC gutter option with flat roof cover with roof tile on top. In case, there is regularly water disruption in future, I will install addition water tank on the this concrete roof.


utellme
post Oct 16 2021, 03:14 PM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(dlttdltt @ Oct 16 2021, 10:45 AM)
If change floor tiles, change window frame, change front security door and paint the whole house, do we still need to apply for Mbsa permit ? Maybe will also wall between hall and dry kitchen.
*
Unless you do any house extension, I don't think you need permit to repaint your house or repairing wear & tear of your house door and windows.

This post has been edited by utellme: Oct 16 2021, 03:17 PM
utellme
post Oct 16 2021, 03:31 PM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(JasonTheGreat @ Oct 15 2021, 11:08 PM)
Want to ask if anyone experienced kena saman by MBSA for reno exceeding anjakan. For example apply for RC Gutter but built GI gutter and thereafter exceed 1 ft from the max wall.

Heard it’s 20x which is Rm6000 saman. Will they let you keep the desig after or ask to roboh.
*
Related to the Saman, when I submiting my setara plan last week, the officer asked me why I didn't tambah the bahagian tepi with the new architect plan and he said the fine is based on the buildup area. Example, if I want to extend the side of my house with a new wet kitchen with area size of 33sm then I have to pay Saman 20x (33*7)= RM 4k+
soulred777
post Oct 16 2021, 07:56 PM

Enthusiast
*****
Junior Member
803 posts

Joined: Aug 2019
QUOTE(knight_hawk @ Oct 16 2021, 10:57 AM)
Majlis kuala langat charged me almost RM5k for permit to extend kitchen. Both neighbour already got wall, mine is just one wall also kena 5k. Need to engage their consultant only can. If not their consultant, will drag like crazy.
*
Consultant as in architect?
personaforever6789
post Oct 16 2021, 08:09 PM

Casual
***
Junior Member
475 posts

Joined: Mar 2008
QUOTE(mini orchard @ Sep 2 2021, 04:25 PM)
If the existing extension was approved previously, then not necesssry. Otherwise, need to submit plan and pay a fine for the old extension without approval.

Not necessary to demolish the entire wall. The contractor will know what to do. This small job, few days can kaotim unless you are also doing other things.

Unless neighbour complain or if you are unlucky mbsa pass through your area, they will check on your house. If is at back lane area, normally not obvious unless you have a roro bin infront of the house.
*
still need

This post has been edited by personaforever6789: Sep 8 2023, 01:08 PM
JasonTheGreat
post Oct 16 2021, 08:12 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
QUOTE(utellme @ Oct 16 2021, 03:31 PM)
Related to the Saman, when I submiting my setara plan last week, the officer asked me why I didn't tambah the bahagian tepi with the new architect plan and he said the fine is based on the buildup area. Example, if I want to extend the side of my house with a new wet kitchen with area size of 33sm then I have to pay Saman 20x (33*7)= RM 4k+
*
I see that you multiply by 7. How is that calculated?
I was told that the plan is rm300. So fine 20x 300 of did not follow
haturaya
post Oct 16 2021, 08:22 PM

Look at all my stars!!
Group Icon
Elite
2,554 posts

Joined: Jan 2003
QUOTE(dlttdltt @ Oct 16 2021, 10:45 AM)
If change floor tiles, change window frame, change front security door and paint the whole house, do we still need to apply for Mbsa permit ? Maybe will also wall between hall and dry kitchen.
*
Nope. whistling.gif
utellme
post Oct 17 2021, 01:27 AM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(JasonTheGreat @ Oct 16 2021, 08:12 PM)
I see that you multiply by 7. How is that calculated?
I was told that the plan is rm300. So fine 20x 300 of did not follow
*
Processing fee is RM7 per sqm, minimum processing must not less RM70. But the processing fee setara plan is RM300 for each section. my extension is front section 1st floor and back section ground floor therefore total cost is RM2128. (300+300+648+880). Not sure I can claim back the RM648 after renovation completed because in the receipts, the payment rm648 is called bayaran permit plan bangunan and RM 600 is called bayaran process plan.
JasonTheGreat
post Oct 18 2021, 12:23 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
QUOTE(utellme @ Oct 17 2021, 01:27 AM)
Processing fee is RM7 per sqm, minimum processing must not less RM70. But the processing fee setara plan is RM300 for each section. my extension is front section 1st  floor and back section ground floor therefore total cost is RM2128. (300+300+648+880). Not sure I can claim back the RM648 after renovation completed because in the receipts, the payment rm648 is called bayaran permit plan bangunan and RM 600 is called bayaran process plan.
*
Finally submitted my Pelan Setara at MBSA. Forced my self to prepare all the documents yesterday as I expect to be less crowded today due to the public holiday tomorrow.

I paid 648 Bayaran Process Pelan, 300 permit pelan rear extension and 880 for tong Roro. Tong roro can claim back if did not utilised. But not sure either for 648. If cannot take back then I made a mistake where i removed my awning installation in this submission. If next time resubmit will be another 648+300
utellme
post Oct 18 2021, 05:59 PM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(JasonTheGreat @ Oct 18 2021, 12:23 PM)
Finally submitted my Pelan Setara at MBSA. Forced my self to prepare all the documents yesterday as I expect to be less crowded today due to the public holiday tomorrow.

I paid 648 Bayaran Process Pelan, 300 permit pelan rear extension and 880 for tong Roro. Tong roro can claim back if did not utilised. But not sure either for 648. If cannot take back then I made a mistake where i removed my awning installation in this submission. If next time resubmit will be another 648+300
*
yes, for me, I reached MBSA before 7.45am when I did my plan submission, still there are 2 renovation runner ahead of me and complete my plan submission around 9:30am . For permit collection, appointment time is set from 2:30pm to 4:00pm and reached there 2:20pm and still 4 people ahead of me and finally collected the permit at 3:30pm.
JasonTheGreat
post Oct 19 2021, 09:00 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
QUOTE(utellme @ Oct 18 2021, 05:59 PM)
yes, for me, I reached MBSA before 7.45am when I did my plan submission, still there are 2 renovation runner ahead of me and  complete  my plan submission around 9:30am . For permit collection, appointment time is set from 2:30pm to 4:00pm and reached there 2:20pm and still 4 people ahead of me and finally collected the permit at 3:30pm.
*
How many days to wait for the approval? From their website it say 1 hr. But after I submit they asked me to go home and wait.
utellme
post Oct 19 2021, 09:10 PM

Enthusiast
*****
Senior Member
919 posts

Joined: May 2005
QUOTE(JasonTheGreat @ Oct 19 2021, 09:00 PM)
How many days to wait for the approval? From their website it say 1 hr. But after I submit they asked me to go home and wait.
*
Didn't they give you a pink permit collection appointment form after plan submission. I only paid the fee when I collect my permit and its 1 week. For me, submit on 8 Oct and permit collection is 15 Oct.

This post has been edited by utellme: Oct 19 2021, 09:11 PM
SUSceo684
post Oct 19 2021, 09:35 PM

Component Burner
********
All Stars
11,667 posts

Joined: Jan 2003
From: Klang/Subang




QUOTE(dlttdltt @ Oct 16 2021, 10:45 AM)
If change floor tiles, change window frame, change front security door and paint the whole house, do we still need to apply for Mbsa permit ? Maybe will also wall between hall and dry kitchen.
*
Structurally never changed no need permit.
Add or delete structural component like wall/extensions/roof incl awning need.
JasonTheGreat
post Oct 19 2021, 09:51 PM

Enthusiast
*****
Junior Member
832 posts

Joined: Jul 2016
QUOTE(utellme @ Oct 19 2021, 09:10 PM)
Didn't they give you a pink permit collection appointment form after plan submission. I only paid the fee when I collect my permit and its 1 week. For me,  submit on 8 Oct and permit collection is 15 Oct.
*
No. I paid. They gave me a receipt of Rm18xx and tell me to go home and wait. No pink slip 🙁
incredibless
post Dec 5 2021, 01:32 PM

Casual
***
Junior Member
437 posts

Joined: Jun 2012
Hi.since this thread is latest. Would like to check for those applied permit already and once your reno work like extension already complete. What is the next step? Inform Mbsa? Or dont need? When inform will they come n check? Or just refund you the deposits?🤔
TStaufoo
post Dec 5 2021, 01:36 PM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
From what I understand, they don't check and you don't have to inform them you complete the renovation.
The validity of the permit is 1 year from date of approval.

The deposit u get back is from the tong roro.
utellme_6376
post Dec 5 2021, 04:08 PM

Getting Started
**
Junior Member
106 posts

Joined: Nov 2021


QUOTE(taufoo @ Dec 5 2021, 01:36 PM)
From what I understand, they don't check and you don't have to inform them you complete the renovation.
The validity of the permit is 1 year from date of approval.

The deposit u get back is from the tong roro.
*
Yes, this is what I understand too.
TStaufoo
post Dec 7 2021, 09:12 AM

Getting Started
**
Junior Member
147 posts

Joined: May 2007
Guys, just update.even after MBSA approval and sticker placed on front door, the worker received two "visitors" yesterday.

They claim to be officers but in normal clothing.
Take some photos and say this wall cannot la that wall cannot la.

Contractor say is most likely come anyway to ask for duit kopi. But the worker didn't ask if from majlis or construction board (CI**)

Damn troublesome seriously. Apply or not also got ppl come kacau.
soulred777
post Dec 7 2021, 10:50 PM

Enthusiast
*****
Junior Member
803 posts

Joined: Aug 2019
QUOTE(taufoo @ Dec 7 2021, 09:12 AM)
Guys, just update.even after MBSA approval and sticker placed on front door, the worker received two "visitors" yesterday.

They claim to be officers but in normal clothing.
Take some photos and say this wall cannot la that wall cannot la.

Contractor say is most likely come anyway to ask for duit kopi. But the worker didn't ask if from majlis or construction board (CI**)

Damn troublesome seriously. Apply or not also got ppl come kacau.
*
Next time report to cops.
getfromme
post Oct 2 2022, 10:32 PM

New Member
*
Junior Member
29 posts

Joined: Jun 2009


QUOTE(kennykck @ Sep 2 2021, 08:14 PM)
Should be below RM1000 for permit. you may contact 0123876104 (En Amin) for help.

https://forum.lowyat.net/topic/1898813/all
*
En Amin is your friend working inside MBSA?
kennykck
post Oct 3 2022, 12:04 PM

!!!~~<((Bankai))>~~!!!
******
Senior Member
1,711 posts

Joined: Sep 2006


QUOTE(getfromme @ Oct 2 2022, 10:32 PM)
En Amin is your friend working inside MBSA?
*
Found his contact from online. He will help settle and advice based on what you need

 