Outline ·
[ Standard ] ·
Linear+
Home Defect Rectification Checklist, After vacant posession! Update With Pics
|
peri peri
|
Oct 14 2013, 08:42 AM
|
|
QUOTE(petlu28 @ Oct 12 2013, 09:52 PM) Today have go check my new house. They already done crack tiles & wall but some wall didn't touch up properly. Then seen those hollow tiles they didn't change. That guy told me nowaday all developer also didn't change hollow tiles. He say within 1 years if the tiles pull out just inform them they will come fix it. Peri Kor is it true? Nope, hollow tiles is consider as defect. Write a letter to the Architect regarding your dissatisfaction. Remember, remark at their defect forms as hollow tiles not done. Dont sign off their defect form. Insist Architect drop by to verify and instruct.
|
|
|
|
|
|
petlu28
|
Oct 14 2013, 08:53 AM
|
|
Are i can find any website regarding this issue? I think print out then show them. QUOTE(peri peri @ Oct 14 2013, 08:42 AM) Nope, hollow tiles is consider as defect. Write a letter to the Architect regarding your dissatisfaction. Remember, remark at their defect forms as hollow tiles not done. Dont sign off their defect form. Insist Architect drop by to verify and instruct.
|
|
|
|
|
|
peri peri
|
Oct 14 2013, 09:58 AM
|
|
QUOTE(petlu28 @ Oct 14 2013, 08:53 AM) Are i can find any website regarding this issue? I think print out then show them. http://www.starproperty.my/index.php/artic...ing-developers/
|
|
|
|
|
|
petlu28
|
Oct 14 2013, 10:08 AM
|
|
Thanks Peri Kor. QUOTE(peri peri @ Oct 14 2013, 09:58 AM)
|
|
|
|
|
|
chrixho
|
Oct 24 2013, 08:07 AM
|
New Member
|
If the house purchase from 1st puchaser (subsales) before the CF issued and 1st purchaser even not yet get the key, do we still can claim from developer if any defect found on the house? Thanks
|
|
|
|
|
|
vjeyamahla
|
Oct 24 2013, 12:35 PM
|
Getting Started

|
Sifus, I have a question. I was informed by the developer to collect the key but no renovation is allowed until CCC. Should I collect the key and check for defect first or wait until CCC . Thanks.
|
|
|
|
|
|
talkpropertytalk
|
Nov 1 2013, 07:55 PM
|
New Member
|
sharing some defects in my unit... which are reallly unacceptable! wall tiles are even covered by paint n plaster!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! painting was done by a low grade painter! door frames/window frame and window glass all covered by paint... floor also paint marks... cracksss cracks here n there should i get a building inspector ? hmmmmmmmmmmmmmm Attached thumbnail(s)
|
|
|
|
|
|
talkpropertytalk
|
Nov 1 2013, 07:56 PM
|
New Member
|
|
|
|
|
|
|
nova_freak
|
Nov 2 2013, 07:41 PM
|
Getting Started

|
QUOTE(talkpropertytalk @ Nov 1 2013, 07:55 PM) sharing some defects in my unit... which are reallly unacceptable!
wall tiles are even covered by paint n plaster!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! painting was done by a low grade painter! door frames/window frame and window glass all covered by paint...
floor also paint marks... cracksss cracks here n there
should i get a building inspector ?
hmmmmmmmmmmmmmm
If got crack, what can we/developer do? My house also got crack after I inspect today..
|
|
|
|
|
|
peri peri
|
Nov 4 2013, 02:35 PM
|
|
QUOTE(nova_freak @ Nov 2 2013, 07:41 PM) If got crack, what can we/developer do? My house also got crack after I inspect today.. check id it is hairline cracks or structural cracks. It make huge different.
|
|
|
|
|
|
ericlaiys
|
Nov 4 2013, 02:43 PM
|
|
QUOTE(talkpropertytalk @ Nov 1 2013, 07:56 PM) really poor workmanship. Which developer?
|
|
|
|
|
|
Zina
|
Nov 5 2013, 12:58 PM
|
New Member
|
QUOTE(talkpropertytalk @ Nov 1 2013, 07:56 PM) My house more worst I bought a house 5 years ago. Now found roof major structural defects. Before this wall crack, ceiling crack , repair and crack , again repair and crack. So we found contractor to look over the roof top.. We get this big news: maybe and suspect of roof collapse . Can I claim this to developer? Can anyone give me guide. Pleaseeeeeeee.
|
|
|
|
|
|
ericlaiys
|
Nov 7 2013, 12:40 PM
|
|
QUOTE(Zina @ Nov 5 2013, 12:58 PM) My house more worst I bought a house 5 years ago. Now found roof major structural defects. Before this wall crack, ceiling crack , repair and crack , again repair and crack. So we found contractor to look over the roof top.. We get this big news: maybe and suspect of roof collapse . Can I claim this to developer? Can anyone give me guide. Pleaseeeeeeee. You can try but they may not bother as it has over warranty. Unless collapse and injured people. may be they will cover it up by fixing it
|
|
|
|
|
|
jiro1986
|
Dec 10 2013, 06:58 PM
|
|
how the warranty work?
will the warranty void once the 1st purchaser sell off the unit?
|
|
|
|
|
|
1282009
|
Dec 10 2013, 11:19 PM
|
|
Deleted since no reply.
This post has been edited by 1282009: Dec 22 2013, 11:27 PM
|
|
|
|
|
|
adwan
|
Dec 11 2013, 07:42 PM
|
|
I just got key from the develop after it was VP about 2 weeks ago. Want to ask: 1) Is it appropriate for developer to hand over the house without water connection? Already make payment to syabus related to water but still not connected yet; 2) The developer also failed to clean up the rubbish and cut the long grass in the garden area....Why they need to wait for the buyer to complaint? Isn't it obvious they should cut all the long grass away before handover? 3) Spot quite a number of defects - gate is rusty and difficult to close, walls and door were tainted by the paints, stains on the platform, cracks etc...The developer don't have QA team to check their product before handover one meh???! 4) The developer project staff give me honour feedback that they will normally take more than a month to rectify all these defects (if I am lucky).... Sifu here, please help.....Is that something normal for the Malaysian developer? This post has been edited by adwan: Dec 11 2013, 08:10 PM
|
|
|
|
|
|
ericlaiys
|
Dec 11 2013, 09:34 PM
|
|
QUOTE(adwan @ Dec 11 2013, 07:42 PM) I just got key from the develop after it was VP about 2 weeks ago. Want to ask: 1) Is it appropriate for developer to hand over the house without water connection? Already make payment to syabus related to water but still not connected yet; 2) The developer also failed to clean up the rubbish and cut the long grass in the garden area....Why they need to wait for the buyer to complaint? Isn't it obvious they should cut all the long grass away before handover? 3) Spot quite a number of defects - gate is rusty and difficult to close, walls and door were tainted by the paints, stains on the platform, cracks etc...The developer don't have QA team to check their product before handover one meh???! 4) The developer project staff give me honour feedback that they will normally take more than a month to rectify all these defects (if I am lucky).... Sifu here, please help.....Is that something normal for the Malaysian developer?  it is normal. Just fill up the issue on defect form and ask them to fix it. Expect more than a month. I gave my developer 1 month. they still cannot finish. they only manage to fix some. So i start renovation where the part not on the defect list. during renovation, developer still take it own sweet time to fix it. My renovation completed after a month but till now my defect still some unresolved. But they did solve some major one and some defect just submitted along the way. Dont expect to move in fast. Give at least 3- 4 month period. Like mine, almost 3 month. Expect to move in by christmas while wait for them to fix some minor defect.
|
|
|
|
|
|
adwan
|
Dec 11 2013, 11:18 PM
|
|
QUOTE(ericlaiys @ Dec 11 2013, 09:34 PM) it is normal. Just fill up the issue on defect form and ask them to fix it. Expect more than a month. I gave my developer 1 month. they still cannot finish. they only manage to fix some. So i start renovation where the part not on the defect list. during renovation, developer still take it own sweet time to fix it. My renovation completed after a month but till now my defect still some unresolved. But they did solve some major one and some defect just submitted along the way. Dont expect to move in fast. Give at least 3- 4 month period. Like mine, almost 3 month. Expect to move in by christmas while wait for them to fix some minor defect. 1) So it is normal that no water supply upon vp? I have made some payment to Syabus before vp? 2) My house defects are at all corner of the house. Cannot say renovated one part and don't renovate the other.....Luckily I did not notice any major structural cracks, may be they already plaster it out to cover it. 3) 3 to 4 months waiting period for them to fix up the defects is  and  to me.
|
|
|
|
|
|
ericlaiys
|
Dec 11 2013, 11:24 PM
|
|
QUOTE(adwan @ Dec 11 2013, 11:18 PM) 1) So it is normal that no water supply upon vp? I have made some payment to Syabus before vp? 2) My house defects are at all corner of the house. Cannot say renovated one part and don't renovate the other.....Luckily I did not notice any major structural cracks, may be they already plaster it out to cover it. 3) 3 to 4 months waiting period for them to fix up the defects is  and  to me. my reply:- 1. Yes. Some of my neighbour dont have water supply when get key. 2. Give them a month to totally fix. In S & P doc got mentioned after 30 days. You can send reminder and notice for 14 days with other contractor quote if they fail to fix. Check your S & P if got. If landed, should have. 3. Trust me. Last time, i only buffer 1 month- developer fix, 1 month -renovation. I end up need to give 1 month. So after 3 month only can see light to move in. For them, your warranty is 24 month (depend on s & p). So they dont get penalty when give key . Consider early deliver. No clause say must fix your defect within 1 days. It is mentioned 30 days.
|
|
|
|
|
|
adwan
|
Dec 11 2013, 11:34 PM
|
|
QUOTE(ericlaiys @ Dec 11 2013, 11:24 PM) my reply:- 1. Yes. Some of my neighbour dont have water supply when get key. 2. Give them a month to totally fix. In S & P doc got mentioned after 30 days. You can send reminder and notice for 14 days with other contractor quote if they fail to fix. Check your S & P if got. If landed, should have. 3. Trust me. Last time, i only buffer 1 month- developer fix, 1 month -renovation. I end up need to give 1 month. So after 3 month only can see light to move in. For them, your warranty is 24 month (depend on s & p). So they dont get penalty when give key . Consider early deliver. No clause say must fix your defect within 1 days. It is mentioned 30 days. Ok. Will check my S&P.
|
|
|
|
|