Overall, every block has its progress with BlkE site most significant...
Observed more than 50+ workers on Sunday afternoon....

This post has been edited by Jagalat: Aug 1 2016, 08:20 PM
Investment EKOCHERAS @ JALAN CHERAS (V4) [MRT PROPERTY] [OT], Where Cheras becomes Mont'Jiulai
|
|
Aug 1 2016, 08:20 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,947 posts Joined: Oct 2013 |
Photos taken on Sunday afternoon...
Overall, every block has its progress with BlkE site most significant... Observed more than 50+ workers on Sunday afternoon.... ![]() This post has been edited by Jagalat: Aug 1 2016, 08:20 PM |
|
|
|
|
|
Aug 1 2016, 08:22 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,947 posts Joined: Oct 2013 |
One note for BlkH buyers, the current tallest steel bars of this building can be observed from Jln Cheras direction to Kajang. (ie from Mutiara Timur) ![]() |
|
|
Aug 1 2016, 08:23 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,947 posts Joined: Oct 2013 |
![]() |
|
|
Aug 1 2016, 08:24 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,947 posts Joined: Oct 2013 |
![]() |
|
|
Aug 2 2016, 03:34 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,428 posts Joined: Sep 2013 |
Jagalat, thanks for yr pixs.
|
|
|
Aug 2 2016, 03:34 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,428 posts Joined: Sep 2013 |
With this progress looks like we cannot collect LAD anymore..
|
|
|
|
|
|
Aug 2 2016, 11:30 AM
|
![]() ![]()
Junior Member
269 posts Joined: Jun 2013 |
Looking at the pictures, i think 3 storey ekocheras shopping mall shall be located from LG, G to L1.
|
|
|
Aug 2 2016, 12:45 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,947 posts Joined: Oct 2013 |
|
|
|
Aug 2 2016, 01:45 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,833 posts Joined: May 2008 |
QUOTE(Jagalat @ Aug 1 2016, 08:20 PM) Photos taken on Sunday afternoon... Thanks for the update Jagalat. Just to compare the progress photo that u took 3 months ago versus today...Overall, every block has its progress with BlkE site most significant... Observed more than 50+ workers on Sunday afternoon.... ![]() 1. From G level currently progressing to L2 on the core lift 2. Slab has some works done till G level. SOHO starts from level 3 onwards. Once they started to construct the SOHO, things will be clearer how would they meet the construction schedule. However looking at the picture, very unlike the mall completion by end of 2017. |
|
|
Aug 2 2016, 02:03 PM
|
![]() ![]()
Junior Member
269 posts Joined: Jun 2013 |
Dont think so they can complete the mall by end of 2017. please note that the other said of the proposed shopping mall still no piling and foundation yet as per the shared pictures.
|
|
|
Aug 2 2016, 09:33 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,947 posts Joined: Oct 2013 |
If they wanna get the mall building completed first, ie all the basement parking levels up to L2 should be constructed and jointed. This required allocation of full resources around the clock in full cruise. So still have slim chance. Yes, the rear part of office building or the Blks L and M site still have yet shown pile caps... My understanding, if I got it right, the Soho, service apartment or the highrise part will continue the construction progress while the mall in operational... |
|
|
Aug 4 2016, 11:14 AM
|
![]()
Junior Member
40 posts Joined: Mar 2010 |
Any SA here ? Interested to buy. PM me.
|
|
|
Aug 4 2016, 12:38 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,936 posts Joined: Oct 2011 From: KL |
|
|
|
|
|
|
Aug 4 2016, 04:47 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,947 posts Joined: Oct 2013 |
|
|
|
Aug 5 2016, 08:40 AM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,936 posts Joined: Oct 2011 From: KL |
|
|
|
Aug 5 2016, 08:40 AM
|
![]() ![]()
Junior Member
75 posts Joined: May 2013 |
QUOTE(Alvelyn @ Jul 15 2015, 09:17 AM) Block J, High Floor, RM 880 psf Buyer deposit kept with lawyer. Buyer can choose any lawyer firmSeller bear interest & risk during construction, contract lawyer fee Buyer pay 10% deposit to lawyer. Transfer upon VP If abandoned, seller bear all the risk, safer than u buy from developer Forummer who does not understand, don't anyhow comment |
|
|
Aug 5 2016, 08:58 AM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,838 posts Joined: Sep 2013 |
|
|
|
Aug 5 2016, 03:30 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
5,947 posts Joined: Oct 2013 |
|
|
|
Aug 5 2016, 03:38 PM
|
![]() ![]()
Junior Member
269 posts Joined: Jun 2013 |
|
|
|
Aug 5 2016, 03:50 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,833 posts Joined: May 2008 |
QUOTE(Alvelyn @ Aug 5 2016, 08:40 AM) Buyer deposit kept with lawyer. Buyer can choose any lawyer firm if developer still has units (which I assume cheaper than yours), how would you sell your unit?If abandoned, seller bear all the risk, safer than u buy from developer Forummer who does not understand, don't anyhow comment |