QUOTE(leaF @ Mar 18 2015, 11:00 AM)
It is only my honest opinion as I was involved with both side construction project. I will say EM has done faster job in finishing up their (infra) roads, landscape , guard house , roundabouts and fencing.
Thanks for your opinion though I am totally disagree with it.
I am working in Semenyih and I withness the progress of the site through my own eyes.
The site clearing for SEH started on Q3/Q4 2012 and the launching is on October 2013. Only after about 2.5 years, SEH already in the "almost-VP" mode, from a bare 700+ acres palm oil farm. They have been taking about a year for the preparation for site clearing, building up the show houses and welcome center, completing the PARC and guard house, finishing the building of tarred road/roundabout to connect Jalan Semenyih to the Welcome center and most importantly, already started the construction of Ecohill link in Sungai Purun area.
The site clearing for EM started on Q4 2013 and the launching is on May 2014. EM show village officially opened in Dec 2014, the connecting road directly from Jalan Semenyih (east gate) and North gate are completed, show houses and welcome center completed, swan lake completed, Lekas interchange on the other hand just started the piling.
Perhaps the time taken by EM for launching is faster than SEH, but don't forget that SEH launch with show units but EM don't. EM also taking about 1 year to complete their show village. Furthermore, EM only prepare 10 show houses, SEH was completing 14 show units during the launching.
So, for me I really can't differentiate either EM or SEH is progress faster, for me, they are really on par...