QUOTE(nck @ Aug 16 2018, 08:23 AM)
Wow...
They claim final 5% n hand over first... Although whole project has yet to be completed.
*
Guess HH is desperate to close the last 5% progressive claim and perform VP to avoid more LD.
However, by looking at the completion status as shown below, HH's appointed architect/consultant declared that as practically completed? bangwall.gif bangwall.gif bangwall.gif

Attached Image
Attached Image
sentulraya
post Aug 19 2018, 02:33 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(nck @ Aug 17 2018, 03:57 PM)
How come "Sentulraya" says he has received the letter and HH says in Sept18.  rclxub.gif  confused.gif
confused...
*
I received letter for last 5% progressive payment notice, not the VP notice ler....that's why I wonder when the VP notice will be sent to owners as the "practically completed" as claimed is not acceptable if the building is not really in completion state.


sentulraya
post Aug 19 2018, 02:35 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(Cocoon @ Aug 18 2018, 07:59 AM)
Vp  now Cf in sept. Sovo  not under residential right ?
*

VP now? Anyone received VP notice? hmm.gif hmm.gif hmm.gif Aurora Sovo is commercial.

How about the shoplots @ AURORA PLACE(3, 4, and 5-storey shop-offices) VP readiness?

This post has been edited by sentulraya: Aug 19 2018, 02:48 AM
sentulraya
post Aug 19 2018, 02:42 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(Chipmunk85 @ Aug 18 2018, 12:30 AM)
Mine is 847sq. Btw do u know when the park sky residence will be completed? Initially they mentioned will be completed after pavillion but doesn't seem so now
*

No idea on the park sky residence completion status leh....but seems the construction progress is fast, when passby Kesas, can see the structure up to top floor already, if not mistaken.

P2 is still far from completion flex.gif flex.gif flex.gif


sentulraya
post Aug 19 2018, 02:52 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(nck @ Aug 18 2018, 08:28 PM)
Thx. All buyers will likely have to wait for another 1-2 months....for this CF or CCC.
*
Let's pray if can get CF/CCC in another 1-2 months....bcoz some projects can drag for months.... notworthy.gif notworthy.gif notworthy.gif
sentulraya
post Aug 20 2018, 01:09 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(nck @ Aug 19 2018, 11:19 AM)
Spoke to my friend who also bought this Park Residence, progress billing claim is fast. This project most likely will be completed by 2019.

Many shoplots here are not occupied.
We are looking forward to the opening of Pavilion Mall by 2020...
*
Pass by the site this evening, below pictures of Park Residence.
Construction ongoing on Sunday also with busy cranes and construction workers.


Attached Image
Attached Image
sentulraya
post Aug 20 2018, 01:21 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


Took some pictures on Sovo construction progress.

HoHup --> This is called "practically completed" and can claim last 5% from purchaser mei ??

VP in September is unlikely. AURORA PLACE(3, 4, and 5-storey shop-offices) also many touch-up not completed yet.

bangwall.gif bangwall.gif bangwall.gif bangwall.gif mad.gif mad.gif mad.gif mad.gif mad.gif


Attached Image
Attached Image
Attached Image
Attached Image
Attached Image
Attached Image
Attached Image
Attached Image
Attached Image

This post has been edited by sentulraya: Aug 20 2018, 01:41 AM
sentulraya
post Aug 20 2018, 01:25 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


Closer look at the construction status........ vmad.gif vmad.gif vmad.gif

The main entrance has no sign of completion at all.

The slap is still not painted, while the HH HQ has painted.

Attached Image

Attached Image

This post has been edited by sentulraya: Aug 20 2018, 01:31 AM
sentulraya
post Aug 20 2018, 10:57 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(Cocoon @ Aug 20 2018, 09:48 AM)
Bro already vp  for those shops. Sovo  I don't know.
Shop is commercial vp without cf.

I have seen worse for high rise residential vp  with ccc ...Whole area like construction site
*
AURORA PLACE(3, 4, and 5-storey shop-offices) VPed? IThose shoplots are not even accessible to the public and still fence up, like that also can VP?

As mentioned, HH sent out last 5% progressive claim for my Sovo unit, but not VP notice yet.

sentulraya
post Aug 20 2018, 11:06 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(Cocoon @ Aug 20 2018, 09:46 AM)
Hehe... have to be heavily compensated with price...
*
According to my SPA schedule, delayed VP and LD kick-in starting mid of Aug....let's see if HH will compensate 10% LD whistling.gif whistling.gif whistling.gif
sentulraya
post Aug 21 2018, 01:09 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(Cocoon @ Aug 20 2018, 04:28 PM)
yup. they will VP it before the due date.

but if you amount is substantial there is a way for this case....  biggrin.gif  it is different from other cases...  bruce.gif  bruce.gif
*
I believe may purchasers will get delayed VP, thus can form a group to proceed for sue case as the grouped amount of LAD will be substantial.

If kucing satu dua making noise....then can forget about it la.
sentulraya
post Aug 21 2018, 01:12 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(BEANCOUNTER @ Aug 20 2018, 12:23 PM)
For non schedule spa, good luck in getting LAD.
*
There is no law in Malaysia? vmad.gif vmad.gif vmad.gif


sentulraya
post Aug 22 2018, 12:46 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(BEANCOUNTER @ Aug 21 2018, 10:15 AM)
got law.

law favours developer more than buyers.
*
It's stated in SPA, delayed VP will be subjected to 10% LAD penalty, very clear cut.
sentulraya
post Aug 22 2018, 12:51 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(gks @ Aug 21 2018, 10:29 AM)
Willing buyer willing seller. The buyers have to ask themselves why agree with lopsided agreement. Just like AES agreement.
*
It's stated in SPA, delayed VP will be subjected to 10% LAD penalty, very clear cut.

The buyers have to ask themselves why agree with "lopsided agreement" which is comparable with AES agreement? hmm.gif hmm.gif hmm.gif



sentulraya
post Aug 22 2018, 01:01 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(nck @ Aug 21 2018, 11:10 AM)
Frankly speaking, we did not receive HH's final 5% progress billing.... biggrin.gif
How come your unit's claim is faster?  hmm.gif  hmm.gif
*
Here you go, HH claim the 5% start from the lower floor 1st. Due date is 24 Aug, damn it. vmad.gif vmad.gif vmad.gif

Attached Image

This post has been edited by sentulraya: Aug 22 2018, 01:03 AM
sentulraya
post Aug 22 2018, 01:59 PM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(BEANCOUNTER @ Aug 22 2018, 08:28 AM)
Non schedule spa is not governed by hda and its non standard. Developers can draft the spa to their advantages and nothing u can do.

Yes if delay they are subjected to pay you LAD
But
They can vped the unit without completing it. How do you clain LAD?
*
Non schedule spa is not governed by hda and its non standard - but it's govern by law, right?

The delayed VP started to kick-in this month for my case, let's see if HH is low class enuf to VP their Sovo with current completion status. How to claim LAD, just follow the law... devil.gif devil.gif devil.gif


sentulraya
post Aug 22 2018, 02:01 PM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(GreenHulk555 @ Aug 22 2018, 07:57 AM)
🤔 bila mau issue ccc ni? tarak ccc tak boleh duduk leh.
For non HDA product, SPA always pro to developer side. And for this case, as usual, developer is not liable for any delay in the issuance of Certificate of Completion and Compliance (CCC)...
*
Ya, it's stated clearly in SPA whereby developer is not liable for any delay in issuance of Certificate of Completion and Compliance (CCC)... vmad.gif vmad.gif vmad.gif
sentulraya
post Aug 23 2018, 11:37 PM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


Any whatsapp group for Sovo, Revo?

Pls share if any.
sentulraya
post Aug 26 2018, 12:26 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(nck @ Aug 25 2018, 04:16 PM)
Thx. We received the AR mail yesterday. HH claims 4 floors from level 8th-11th.  doh.gif  sweat.gif
Therefore, VP wont be so soon since progress is so slow...  shakehead.gif
*
As mentioned by some of the members here whereby under non-schedule SPA, the developer can declare VP like any time as they wish?

I am not sure since this is my 1st commercial property, signed SPA since 2014 Apr and till now no sign of completion.... vmad.gif vmad.gif vmad.gif

Let's hope HH will obey agreement on delayed VP and compensate 10% LAD. notworthy.gif notworthy.gif notworthy.gif



sentulraya
post Sep 15 2018, 12:56 AM

Getting Started
**
Junior Member
89 posts

Joined: Mar 2010


QUOTE(nck @ Sep 7 2018, 09:04 AM)
K

HH is taking it's sweet time to complete this project....
*
Dont know it's sweet time or hard time to complete this project la....they way I see is HH is really pokai until they need to charge the last 5% progressive payment so early with so called "practically completed" ranting.gif ranting.gif ranting.gif ranting.gif