QUOTE(blinkxox @ Oct 24 2014, 03:08 AM)
i wanna supply construction raw material.

got contacts to share?  brows.gif
*
what material?
TSiwubpreve
post Oct 24 2014, 11:21 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(fondo @ Oct 24 2014, 08:51 AM)
iwubpreve, please enlighten me on loss & expense.

How do I claim this when project delay for years?
*
good question.

loss and expenses (LE) is a sensitive issue. will offend client no doubt biggrin.gif

in order to claim loss and expenses, u have to demonstrate ur entitlement of EOT. to do that u need to have the original baseline (original master programme). then u have to revise the programme by incorporate ur entitlement of EOT inside. by do that ur baseline become baseline 2 (example). then u have to justify ur expenses but putting in the expenses into that period.

example:
1. original rent 5 month of tower crane, now 7 months, u get 2 months.
2. original u pay wages to ur stuff 7 months, now 5 months

bear in mind not all is straight away stuff.

there are few dalays,
culpable delay - contractor fault and therefore not entitle for LE nor EOT
concurrent delay - both contractor and employer contribute to the delay, hence EOT entitle LE not entitle
non culpable delay - employer/architect fault and contractor entitle both EOT and LE
TSiwubpreve
post Oct 24 2014, 03:14 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(fondo @ Oct 24 2014, 01:32 PM)
iwubpreve
1) how do i justify?
By contract prelims? Or actual loss?

2) in terms of claim, what claim are we talking about? Contract ie. Progress claim? Or...

3) what is your point of view in view of the L&E claim practice in construction industry?

4)hehe...
*
1)
u have to justify the programme first. example I demonstrate u the original baseline and revised baseline after 5 month of Extension of Time granted. base on the chart, u entitle 5 months and time, and ur LE have to base on the affected loss and expenses that direct related to the EOT that granted. Example, u granted 5 months EOT, however tower crane just require extra 3 months only and hence u entitle to claim 3 months renting cost of tower crane. however because ur project team still run until the end, so u entitle 5 months wages for ur project team. hence it's not everything automatically get 5 months.

depend on agreement, some contract impose a clause whereby on when come to loss and expense claim, u need to show the actual record (those actual receipt to show that u really spent this amount)

2)
what claim u mean? I don't get u.

3)
L&E is definitely entitle. however as I mention early, this is sensitive issue and client never like this. even contract prohibit u from claiming L&E, some contract impose the clause whereby loss and expense is not allow, however when come to construction work, those changes instructed by client is a variation and in some form, varying the original contract also is a "breach of contract" and remedy automatically come in which is in the form of L&E. not easy thing as a lot of justification require if u want to claim that much.

4)hoho...


Attached thumbnail(s)
Attached Image
TSiwubpreve
post Oct 24 2014, 03:16 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(blinkxox @ Oct 24 2014, 03:10 PM)
need anything from quarry? brows.gif
*
precious quarry have? stone block also is quarry to me. can chop the stone block into precious marble / granite brows.gif
TSiwubpreve
post Oct 27 2014, 11:00 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(z800r @ Oct 26 2014, 09:26 AM)
Im from manufacturing background.. Wanna work in civil eng industry. Can or not? Haha. As site supervisor maybe. Wanna try my luck. Sp setia or any big firm sure wont hire manufacturing grads. Now im working as production supervisor.
*
should be fine. a lot of subcon willing to hire u as site supervisor is really a job without much qualification. work under the hot sun mang.
TSiwubpreve
post Oct 28 2014, 08:31 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(zxic @ Oct 27 2014, 09:17 PM)
How does the crane adjust it's height ? And how does it get on top of tall buildings during construction? Thanks
*
tower crane will climb itself as the building progress reach higher level by adding the mast. after complete, it will lower down itself also by dissemble the mast part by part as it lowering down. in here, most common tower crane we used is hammerhead and luffing crane.

think the video speak louder biggrin.gif

TSiwubpreve
post Oct 28 2014, 08:42 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(seahshiren @ Oct 28 2014, 07:40 AM)
Ok. Pardon my stupid unprofessional and overlly general questions.

1) What is the best developer out there? If I want to buy house.

2) What does an engineer do in the construction industry?

3) What is the green thing around buildings that are in the process of construction?
*
1)
best developer? I think buy property see ur budget since the property price is very much related to its location. in my opinion, those developer that doesn't squeeze the contractor to the max is the best 1. as the contractor get what he want and he build what the developer want. if the developer squeeze all the single cents from the contractor and contractor have no choice but to reduce the quality to comply to the cost. but since u asked, in my opinion the good developer are Selangor Dredging, Symphony Life, UM Land. biggrin.gif

2)
Engineer is consulting engineer where they design the building to suit to requirement of architecture and infrastructure of building.

3)
safety net.
TSiwubpreve
post Oct 28 2014, 08:44 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(futra @ Oct 28 2014, 08:32 AM)
Hi, i'm not sure if this is directly related..

How does one apply the position for Safety Officer @ SO? What qualifications/background needed? Thanks.
*
attend a course conducted by niosh. u need to have green book to call urself as certified competent safety officer.
TSiwubpreve
post Oct 28 2014, 09:02 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(futra @ Oct 28 2014, 08:45 AM)
Ok, really appreciate it. Thanks  smile.gif  R u an SO, if u dun mind me asking?
*
can't reveal abt my identity tongue.gif
TSiwubpreve
post Oct 28 2014, 09:10 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(jeffvip @ Oct 28 2014, 08:47 AM)
How to solve a water leaking issue on a previously cold joint area?
*
different measure will be taken depend on how severe the water leaking are and what kind of exposure of the surface. normally, they will just do pressure grout injection at the water leaking zone with each point for injection is very close to each other in order to fill in the water capillary within the slab.
TSiwubpreve
post Oct 28 2014, 09:36 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(stupiak07 @ Oct 28 2014, 09:19 AM)
what the permit process needed for building a container house?
*
container house seems like a trend now sweat.gif to be honest I have no idea what are the jurisdiction out there whether container to be undergo the same process like building a house.
TSiwubpreve
post Oct 31 2014, 08:30 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(fondo @ Oct 30 2014, 08:01 PM)
Whose fault normally when we are talking about water leaking from the above slab normally around lift core?

I am confuse about cold joint, normally between lift core and floor slab? Lift core constructed, then only cast slab, then cold joint might occur?

Or, the logistic problem which there is delay in the ready mix concrete truck and affected the pouring of the concrete which eventually resulted to new and old joint and resulted to cold joint? How? How la?

iwubpreve
*
yes, but no wet area would be around lift core. so it shouldn't have any water leaking issue la. which also mean they will not consider any water proofing work at there.

poor concrete quality will result those honeycomb and etc but not likely cold joint. usually they will have quality control over concrete. when concrete truck arrive, they will do the slump test on the spot, if acceptable then only start to pour the concrete. cold joint arise because of no good treatment on the joint prior casting la. eg. such as bonding of hardened concrete and new concrete, proper reinforcement.
TSiwubpreve
post Oct 31 2014, 08:32 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(BlackPen @ Oct 30 2014, 11:40 PM)
why qs job overloaded and underpaid..please answer me
*
because u didn't ask for more. if u capable, a lot of people willing to hire u 1. perhaps ur employer willing to keep u from jumping ship by counter offer if u can make money for company. plus now shortage of manpower, can demand even more for QS I think. after all, QS is directly dealing with figure, hence ur salary will be higher as the figure is always the thing ur boss wanted to know. ur boss will very likely always in touch v u. biggrin.gif
TSiwubpreve
post Oct 31 2014, 11:20 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(BlackPen @ Oct 31 2014, 11:18 AM)
the market price is underpaid ..what to do  doh.gif a bit regret to study QS  sweat.gif
*
starting is like that 1 la. need to gai a bit 1. too many took up QS course. in TAR college, course with most student is Accouting, second is QS.
TSiwubpreve
post Oct 31 2014, 03:41 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(stargamer @ Oct 31 2014, 03:28 PM)
how much money need to build a big mansion?
*
175/sqft. do your maths.
TSiwubpreve
post Oct 31 2014, 03:42 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(BlackPen @ Oct 31 2014, 11:29 AM)
last time i study at tarc..starting 300+ end up 200+

most of them when to SG work..and some of  them not work as QS..

Now study at Taylor's starting 90+. Now only 62 students left  laugh.gif

I don't see all students will work as QS laugh.gif overloaded job/underpaid job/boring job..

what i see is QS require:- 1/3 of Lawyer, 1/3 of Engineer, and 1/3 of Accounting  laugh.gif
*
depend la. a good QS usually will not work as QS la. more on management. QS oversee a lot of thing. after all, construction is about money. everything related to money.
TSiwubpreve
post Nov 1 2014, 11:55 AM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Pugface @ Nov 1 2014, 10:50 AM)
TS, I've recently bought a house. To be exact, it's emira residence by OSK group. Developer is ribuan ekuiti. I've heard many words around saying OSK work are always so-so and usually will have defects..

I am new to this. It's for own stay. What should I do and what should I look out for when I receive the new house? How do I run my own inspection to make sure there aren't any defect common people like me can't detect? Please enlighten me!

notworthy.gif notworthy.gif
*
ic. can let me know ur property price and the total build up area? different tier need to have different measure when come to inspect the house smile.gif
TSiwubpreve
post Nov 1 2014, 12:23 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Pugface @ Nov 1 2014, 12:05 PM)
Abt 350k.
614sq ft.  smile.gif
*
oic, about RM570 per sqft. seems like a 2nd tier property in klang valley so can't be fussy as if it's 1st tier quality la tongue.gif

just check about the functionality of those thing ok already. ironmongery is work, the key is correct, the qty of power points is as per agreement, check the wall facing outside 1 whether it's humid to ensure no water seeping through especially windows edge, check the toilet floor by pour a lot of water on the floor to see if the water will flow to the floor trap. sometimes the floor tile they didn't make it a fall, to let the water flow to floor trap, check the floor/wall tile if it already broken as sometimes after completed the work, the other trade by damage it. check timber floor also if u have that as timber floor is fragile especially contact v water. it will bulging when contact with water.

basically is like that. if first tier, there were a lot of thing have to taken care of biggrin.gif
TSiwubpreve
post Nov 1 2014, 05:05 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Pugface @ Nov 1 2014, 03:38 PM)
I see I see! I plan to renovate abit. It's a one bedroom house so I plan to build a wall in between to create another smaller room. Any idea on the budget I should prepare?? Thanks again sifu
*
depend what are the wall u want. gymsum board, brickwall, etc. gymsum board is pretty cheap nowadays. since ur qty is small, should be within 1.5k.
TSiwubpreve
post Nov 1 2014, 05:07 PM

Regular
******
Senior Member
1,829 posts

Joined: Mar 2013
QUOTE(Hollow21 @ Nov 1 2014, 04:58 PM)
May I know what is the psf to build a 2-story shoplot??
*
depend how big u want la. assume 900 - 1000 sqft per storey. standard.