QUOTE(Yuin Chuan See @ Jan 14 2015, 03:31 PM)
Mmm... It is a big concern as people in BTP wish to witness the transformation of more advanced township.
1. Can someone update with the information of why the PETRONAS Petrol Station in BTP does not begin to operate even it has obtained the permit last month and with complete facilities?
2. How is the progress of rubbish collection in Garden Height Phase 2, Block 4 BTP?
3. How is the progress of maintenance for the defects in Garden Height Phase 2 mentioned by the forum members?
3. Any update for the date and venue of the launching event for Seiring Semi-D?
Hi Yuin Chuan See, our response to the above are as follows:
1. PETRONAS has already obtained their CCC for the building, we have checked with them and we were told it will be opened for business next month as they are awaiting for their licenses and permit. Should not be long we believe.
2. As for the rubbish collection, as explained earlier, we have already commenced collection. Let the residents speak for themselves.
3. Rectification of defects are on going and again let the buyers voice their opinion.
4. Seiring Semi-detach units will be launched this 24th and 25th January, that is next weekend. All of you are most welcome. Light refreshments will be served. We have also planned some events for the month of February to coincide with the Chinese New year. Please watch out for our announcement including the advertisement in the newspapers.