QUOTE(keneeth111 @ Aug 11 2013, 11:21 AM)
According to fren who had checked with the uncle whom believed to be main-con on the site the other day,
the slow progress due to the followings:-
1) Soil is too soft, more pilings are required than normal site....
2) The earlier pilings for abandoned shop-lots weren't sufficient, they have redo............
3) They have to stop work at 5pm sharp, as there's some complaints lodged by the residents nearby.....
Noted that's only one piling machine crane there which is really inadequate to cope the speed and fight with stipulated completion time-frame..........
but there's progress................better than nothing..................
Let's do some calculation.
Late interest charge, say = 10 % per annum
Let say it is late for 3 months,
Average property value, say 400,000
Total number of units = 412
10/100 * 3/12 * 400,000 * 412 = 4.12 million.
Is my calculation anything wrong ?