QUOTE(shagalot @ Aug 14 2014, 04:31 PM)
Your capacity expansion follow current rate or your original rate?
the additional capacity follows 2014 rate, i.e. RM1.0184 basic+ RM0.2153 bonus rate = RM1.2337 per kWh (10% degression over 2013.
the existing capacity follows 2013 rate, i.e. RM1.1316 basic+ RM0.2392 bonus rate = RM1.3708 per kWh.
My SI will install the new capacity as a new system, separate fro the existing PV system. The 1kWp system will have 4 panels connected to a new inverter and these are connected to a new Renewable Energy meter.
Therefore, I will have 2 RE meters, one recording the output from the existing 2.45 kWp system and another RE meter recording the output from the new 1 kWp system. I will receive two sets of Payment Advice each montj.
i will document this solar capacity expansion episode when it happens.