nice one!
stimix
post May 6 2012, 03:55 PM

Dunno
Group Icon
Moderator
3,542 posts

Joined: Jan 2003
From: Puchong, Selangor



Ampang lime ext Stn no 11- Puchong Prima Opp OTK - Soil testing works started

user posted image

BTW, Puchong Perdana (Stn 10) & Wisma Tracto/Puteri Mart - (Stn 9). Still no progress.
TSKampung2005
post May 7 2012, 12:50 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
http://www.sjecho.com.my/NewsDetails.aspx?ArticleID=283

QUOTE
user posted image
Work along Persiaran Jengka

user posted image
Adequate banners and signboards will be placed at strategic locations near the project site to keep residents abreast of the work in progress

JinXXX
post May 7 2012, 01:03 AM

Look at all my stars!!
*******
Senior Member
2,516 posts

Joined: Feb 2007
From: Uarla Umpur



yeahhh

faster faster build finish....
supermoto
post May 7 2012, 01:10 AM

Casual
***
Junior Member
386 posts

Joined: Dec 2010
can connect to sunway piramid from putra wangsa maju?
TSKampung2005
post May 7 2012, 01:14 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
QUOTE(supermoto @ May 7 2012, 01:10 AM)
can connect to sunway piramid from putra wangsa maju?
*
no, not that close.

There will be bus service from LRT extension station to Sunway Pyramid.
supermoto
post May 7 2012, 01:17 AM

Casual
***
Junior Member
386 posts

Joined: Dec 2010
QUOTE(Kampung2005 @ May 7 2012, 01:14 AM)
no, not that close.

There will be bus service from LRT extension station to Sunway Pyramid.
*
'
u mean upon completion or existing service?

taxi ride how much?
Wangan
post May 7 2012, 01:21 AM

Getting Started
**
Junior Member
84 posts

Joined: Sep 2008
QUOTE(patienceGNR @ Jan 17 2012, 01:50 PM)
My friends in QS (Quantity Surveying) told me those blocks are for safety test purposes. i.e to test if 99999999999kg can go on to the elevated platforms, or not.
*
its called cube test.
TSKampung2005
post May 7 2012, 01:28 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
QUOTE(supermoto @ May 7 2012, 01:17 AM)
'
u mean upon completion or existing service?

taxi ride how much?
*
Completion.

Well, at this moment, there is bus service to Sunway from LRT, it is U623 from Kelana Jaya station.

Taxi ride, I don't know because I never take taxi to there.
supermoto
post May 7 2012, 01:29 AM

Casual
***
Junior Member
386 posts

Joined: Dec 2010
QUOTE(Kampung2005 @ May 7 2012, 01:28 AM)
Completion.

Well, at this moment, there is bus service to Sunway from LRT, it is U623 from Kelana Jaya station.

Taxi ride, I don't know because I never take taxi to there.
*
when will it be complete?
TSKampung2005
post May 7 2012, 01:29 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
QUOTE(supermoto @ May 7 2012, 01:29 AM)
when will it be complete?
*
End 2014.
supermoto
post May 7 2012, 01:35 AM

Casual
***
Junior Member
386 posts

Joined: Dec 2010
still very long... cant wait to eat hartz chicken buffet...
davkong
post May 7 2012, 01:41 AM

reConnect
******
Senior Member
1,766 posts

Joined: Jan 2003
From: Malaysia


QUOTE(Wangan @ May 7 2012, 01:21 AM)
its called cube test.
*
It is called static load test..
stimix
post May 7 2012, 09:14 AM

Dunno
Group Icon
Moderator
3,542 posts

Joined: Jan 2003
From: Puchong, Selangor



QUOTE(Kampung2005 @ May 7 2012, 12:50 AM)
The progress by Sunway at Subang Jaya side much faster than the MRCB-Bina Puri side.. Till Yesterday.. The only real progress were stn1, 2, 3 & 4 in Kinrara side & stn 6 beside IOI Mall. Elsewhere, just land clearing (Stn 7 -Tesco), covered - can't see -(Rakan Muda -Stn 8) - No progress at Stn 9 (Puteri Mart) & Stn 10 (Puchong Perdana) & soil survey work just started at stn 11 (Puchong Prima as posted earlier) sad.gif
stimix
post May 7 2012, 09:16 AM

Dunno
Group Icon
Moderator
3,542 posts

Joined: Jan 2003
From: Puchong, Selangor



QUOTE(supermoto @ May 7 2012, 01:17 AM)
'
u mean upon completion or existing service?

taxi ride how much?
*
Taxi ride in Subang mostly fixed charges & they reluctant to use meter.. expecting RM10 to Pyramid from either Suabng Jaya KTM/ KJ LRT
asd5139
post May 7 2012, 09:21 AM

New Member
*
Newbie
19 posts

Joined: Feb 2011


QUOTE(stimix @ May 7 2012, 09:14 AM)
The progress by Sunway at Subang Jaya side much faster than the MRCB-Bina Puri side.. Till Yesterday.. The only real progress were stn1, 2, 3 & 4 in Kinrara side & stn 6 beside IOI Mall. Elsewhere, just land clearing (Stn 7 -Tesco), covered - can't see -(Rakan Muda -Stn 8) - No progress at Stn 9 (Puteri Mart) & Stn 10 (Puchong Perdana) & soil survey work just started at stn 11 (Puchong Prima as posted earlier)  sad.gif
*
some tender are not fully given hence the delay i think.. can dig back in few news article posted by kampung.
stimix
post May 7 2012, 09:24 AM

Dunno
Group Icon
Moderator
3,542 posts

Joined: Jan 2003
From: Puchong, Selangor



QUOTE(asd5139 @ May 7 2012, 09:21 AM)
some tender are not fully given hence the delay i think.. can dig back in few news article posted by kampung.
*
Yeah-kah? Bcos on Puchong side, mostly to MRCB & Bina Puri and works are extensive at Kinrara-IOI side but thereafter.. abit slow.. The Puchong Perdana & Puteri Mart probably facing problem bcos from what I observed on these 2 stations, there are no landbank at all haha..
asd5139
post May 7 2012, 09:40 AM

New Member
*
Newbie
19 posts

Joined: Feb 2011


QUOTE(stimix @ May 7 2012, 09:24 AM)
Yeah-kah? Bcos on Puchong side, mostly to MRCB & Bina Puri and works are extensive at Kinrara-IOI side but thereafter.. abit slow.. The Puchong Perdana & Puteri Mart probably facing problem bcos from what I observed on these 2 stations, there are no landbank at all haha..
*
i take this from kampung previous thread: http://www.btimes.com.my/Current_News/BTIM...l#ixzz1tr1f1lgK
stimix
post May 7 2012, 09:47 AM

Dunno
Group Icon
Moderator
3,542 posts

Joined: Jan 2003
From: Puchong, Selangor



QUOTE(asd5139 @ May 7 2012, 09:40 AM)
i take this from kampung previous thread: http://www.btimes.com.my/Current_News/BTIM...l#ixzz1tr1f1lgK
*
Hmnnn Stn 10 & 11 delayed due to tender award... hmm.gif From what I see, more like nothing happening at all at stn 9 (Puteri Mart) & Stn 10 (Puchong Perdana) These two really problematic from what I see. Stn 10.. right at a very busy roundabout beside Perdana complex. No landbank at all & stn 9. fronting Wisma Tractor entrance & junction to Puteri MArt -.. Wondering how they gonna build the stn haha

STn 11.. soil cube survey works started liao.. So I dun think this is a delay hmm.gif

user posted image

This post has been edited by stimix: May 7 2012, 09:48 AM
asd5139
post May 7 2012, 10:00 AM

New Member
*
Newbie
19 posts

Joined: Feb 2011


then need to korek back on who get the tender...cannot comment on that..

52 Pages « < 8 9 10 11 12 > » 
Bump Topic Add ReplyOptions New Topic
 

Change to:
| Lo-Fi Version
0.0243sec    0.83    6 queries    GZIP Disabled
Time is now: 12th December 2025 - 01:37 PM