I think it will be very high elevated viaduct on top of the existing Highway ramps

Ultimate LRT extension construction update thread!, Ara Damansara, USJ, Puchong!
|
|
Jan 17 2012, 12:02 PM
Return to original view | Post
#1
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Forgot to add this piling machine & piling concrete at the junction of Puchong Jaya-IOI to Sg-Besi Bypass & the U-Turn back to Puchong Jaya
I think it will be very high elevated viaduct on top of the existing Highway ramps ![]() |
|
|
Jan 17 2012, 12:24 PM
Return to original view | Post
#2
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Sunway already served by Subang Jaya & Sri Setia Komuter stations liao. Probably in future, feeder buses to st 5 (Ss15) or st6 USJ 14)?
Currently I think there is also feeder buses to Kelana Jaya station and so do existing Yellow mini bus to IOI Mall from Sunway..nearby only |
|
|
Jan 17 2012, 12:30 PM
Return to original view | Post
#3
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
QUOTE(lj0000 @ Jan 17 2012, 12:25 PM) That's what Puchog community been saying since another Tesco is currently under construction at Bkt Puchong 2. Here's the progress of the new Tesco Puchong last mth..but not much progress since last taken dunno why ..probably due to the disputed Hindu temple in the far right in cricle kua![]() Added on January 17, 2012, 12:32 pm QUOTE(Icehart @ Jan 17 2012, 12:26 PM) The land beside IOI Mall / ex-Esso is confirmed LRT Station. The piling there I suspect only based on the existing allignment as per the route mapThis post has been edited by stimix: Jan 17 2012, 12:33 PM |
|
|
Jan 17 2012, 12:57 PM
Return to original view | Post
#4
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
The new U/C tesco in Bkt Puchong 2 for sure getting super duper competition on that bt14 area.
Existing Hypermarkets and supermarkets surrounding this Bt 14 inc: 1) Carrefour 2) Hero (1 in Bt 14 & another in Meranti Jaya) 3) Mydin (1 in Puchong Utama & another at Tasik Prima) 4) Speedmart 99 (1 in Bt14 & another at Puchong Utama) Cham liao..worst jam ever at bt14 |
|
|
Jan 17 2012, 02:42 PM
Return to original view | Post
#5
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Haha..tnx for the info..I also din know that's test equipmet..thinking of concreate for the station paisehh
|
|
|
Jan 29 2012, 03:17 PM
Return to original view | Post
#6
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Another update. Taken this Morning. The viaduct beside Kesas Highway at Bkt Jalil here: N3 03.780 E101 40.387
![]() |
|
|
Jan 29 2012, 03:39 PM
Return to original view | Post
#7
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Actually the LRT will resulted more ppl taking LRT to KL during weekend esp areas soon to be covered wth LRT lines..I'm eagerly waiting for this day haha
|
|
|
Jan 29 2012, 05:35 PM
Return to original view | Post
#8
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Yeah.. I hv taken the picture besdie the Elite Highway junction few wks ago as per 1st pg. Now beside the flyover, they laid lotsa soil testing concrete
QUOTE(newbi3s @ Jan 29 2012, 04:59 PM) |
|
|
Jan 29 2012, 05:42 PM
Return to original view | Post
#9
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
From the current progress in Bkt Jalil. Puchong, Ara Damansara & Putra Height, chances of bothe lines opeming almost at the same time very high
|
|
|
Feb 5 2012, 04:13 PM
Return to original view | Post
#10
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Latest:
Progress in Ara Damansara/Subang beside Rapid KL HQ at Subang: ![]() Viaducts along Jln Subang airport: ![]() |
|
|
Feb 5 2012, 05:34 PM
Return to original view | Post
#11
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Actually the LRT extension beside the depot abit slow compare to the progress at Bkt Jalil.. If I still can recalled, mths ago, they already started the viaduct project.. now similar nia..
Added on February 5, 2012, 5:35 pmOnly the Old Subang road area, the progress intensified This post has been edited by stimix: Feb 5 2012, 05:35 PM |
|
|
Feb 5 2012, 06:23 PM
Return to original view | Post
#12
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
|
|
|
Feb 10 2012, 10:37 AM
Return to original view | Post
#14
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Hmnnn All the Bkt Jalil-Puchong stations already in wikimapia but so sad no rapidkl our ther associate wanna update the Kelana Jaya-USJ stations..No entries at all although really can see extensive progress at Ara Damansara, Subang & Putra Height side. USJ side stil quiet.
On Puchong, The hap Seng Star- Mercedes station progressing fast & so do the IOI Mall station. The Tesco stn still quiet but fencing already erected wth rapidkl signboard at the Rakan Muda-Indian temple site |
|
|
Feb 10 2012, 10:59 AM
Return to original view | Post
#15
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Wah yuur life expectancy lower than M'sian average liao
Anyway, KTM just need to upgraded their komuter and increase number of trains & timing -can liao..Komuter also part of Urban metro system what. Only it's currently very slow from so many complaints everywhere. QUOTE(Marcus @ Feb 10 2012, 10:46 AM) |
|
|
Feb 12 2012, 01:27 PM
Return to original view | Post
#16
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Latest update as at this Morning 12/2/2012:
Stn 1: OUG (More like explanade haha: ![]() ![]() Stn 2: Kg Muhibbah Flat: ![]() ![]() Stn 4: Giant Kinrara: ![]() Stn 6 IOI Mall: ![]() |
|
|
Feb 14 2012, 11:50 AM
Return to original view | Post
#17
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Pictures of KJ extension lines posted earlier:
QUOTE(stimix @ Feb 5 2012, 04:13 PM) Latest: Add the progress of the USJ-Putrajaya side at the junction of USJ/HICOM- Elite Highway-USJ toll (Taken early Feb. As at Today, they started to clear the pyramid liao - Was told earlier for the purpose of soil stability testing)Progress in Ara Damansara/Subang beside Rapid KL HQ at Subang: ![]() Viaducts along Jln Subang airport: ![]() ![]() |
|
|
Feb 26 2012, 09:53 PM
Return to original view | Post
#18
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Taken Today:
Location Subang, just after Chitta Mall & Dana 1 Biz ctr here: http://wikimapia.org/#lat=3.1089024&lon=10...44&z=17&l=0&m=b Viaduct ready and rail beam currently in progress: ![]() Location Putra Height USJ- Last stn 13: MRCB or Puchong/Ampang side last stn. ![]() However on the site, ths small Board also showing Sunway Cont.. i.e the contractor for Subang Jaya till Putra Height sid..meaning this will be a side by side stantions Location: http://wikimapia.org/#lat=2.9957988&lon=10...12&z=17&l=0&m=b ![]() |
|
|
Feb 26 2012, 10:06 PM
Return to original view | Post
#19
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
Yeah no idea but from both MRCG & Suncon singboards for sure both are building in the same location
|
|
|
Feb 27 2012, 02:25 PM
Return to original view | Post
#20
|
|
Moderator
3,542 posts Joined: Jan 2003 From: Puchong, Selangor |
BTW, forgotten to update on USJ side. I din take any photo but SunCon already put up plastic barriers in between Sekolah Wawasan & USJ19 mall. This will be the 1st progress at Jln Kewajipan to date
|