Latest update, they have obtained CCC, and started for inspection and key collection.
This post has been edited by HappyChillax: Jul 14 2017, 06:40 PM
Duet Residence @ Bandar Kinrara
Duet Residence @ Bandar Kinrara
|
|
Jul 13 2017, 02:43 PM
|
![]()
Newbie
2 posts Joined: Jul 2017 |
Latest update, they have obtained CCC, and started for inspection and key collection.
This post has been edited by HappyChillax: Jul 14 2017, 06:40 PM |
|
|
|
|
|
Jul 26 2017, 02:23 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,790 posts Joined: Aug 2007 |
Helped a friend to do defect liability.
All I can say… omg. |
|
|
Jul 26 2017, 09:31 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
2,908 posts Joined: Aug 2011 |
|
|
|
Jul 26 2017, 09:47 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,678 posts Joined: Mar 2016 |
|
|
|
Jul 27 2017, 10:27 AM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,790 posts Joined: Aug 2007 |
QUOTE(natman @ Jul 26 2017, 09:31 PM) I didn’t take any pictures that day, was so tired and besides it was partly done.I started defect liability inspection at 4pm, ended about 7pm. Had to do a rush job because my friend’s entire family was there. They thought defect liability checks are short and quick. Boy they were in for a surprise. Haha… I even conscripted my friend’s children to help out. Am not an expert in construction matters but I can roughly identify them from previous experience. Areas I check that day include: 1. Foyer 2. Dining Area 3. Living Area 4. Dry Kitchen 5. Balcony 1 6. Master bedroom 7. Master bedroom toilet 8. Balcony 2 9. Bedroom 2. 10. common toilet Remaining 10. Bedroom 1 11. Wet Kitchen 12. Storeroom 13. Yard. |
|
|
Jul 30 2017, 08:20 PM
|
![]()
Newbie
2 posts Joined: Oct 2007 |
QUOTE(aurora97 @ Jul 27 2017, 10:27 AM) I didn’t take any pictures that day, was so tired and besides it was partly done. Aurora97, I went to c and it's omg too. Jus wonder hav you realize the toilet design is weird and also the toilet door size? It's smaller than standard size!!I started defect liability inspection at 4pm, ended about 7pm. Had to do a rush job because my friend’s entire family was there. They thought defect liability checks are short and quick. Boy they were in for a surprise. Haha… I even conscripted my friend’s children to help out. Am not an expert in construction matters but I can roughly identify them from previous experience. Areas I check that day include: 1. Foyer 2. Dining Area 3. Living Area 4. Dry Kitchen 5. Balcony 1 6. Master bedroom 7. Master bedroom toilet 8. Balcony 2 9. Bedroom 2. 10. common toilet Remaining 10. Bedroom 1 11. Wet Kitchen 12. Storeroom 13. Yard. |
|
|
|
|
|
Jul 31 2017, 12:05 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,790 posts Joined: Aug 2007 |
QUOTE(summerssh @ Jul 30 2017, 08:20 PM) Aurora97, I went to c and it's omg too. Jus wonder hav you realize the toilet design is weird and also the toilet door size? It's smaller than standard size!! I don’t know whether the toilet is smaller than usual and the toilet door size is abnormal or otherwise.In any case, there is a provision in the Sales and Purchase Agreement that deal with this (NOTE: APOLOGIES in advance, am using the old Schedule H (2002) but I think this provision is unchanged) Position and area of Parcel 13. » Click to show Spoiler - click again to hide... « I suggest that after you have done your defect rectification, you immediate request for a copy of the building plan, more specifically for your unit. You will than need to measure your unit to see if its similar to the building plan. |
|
|
Aug 7 2017, 01:43 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,790 posts Joined: Aug 2007 |
Hi All, some of the defects i have discovered. Not sure if they are or not, I will let the developer explain to owner.
The wooden floor, kitchen cabinet, free items given by developer and small toilet excluded from this checking because owner has other plans. Meanwhile, my 2 cents worth, the wooden flooring is badly done and wear and tear has really took its toll. The gaps and split ends are huge headache. Consolation? 1. the wall is quite flat. 2. the door frames are solid except when you reach the base of the frames, i think they covered it with plaster and they made a hash out of it. 3. overall the house is quite bright and well lit but the kitchen, small toilet and yard quite dark. Did not see common area, so no comments. This post has been edited by aurora97: Aug 7 2017, 01:49 PM Attached thumbnail(s) |
|
|
Aug 7 2017, 04:28 PM
|
![]() ![]()
Junior Member
70 posts Joined: Apr 2014 |
QUOTE(aurora97 @ Aug 7 2017, 01:43 PM) Hi All, some of the defects i have discovered. Not sure if they are or not, I will let the developer explain to owner. Big window panels, nice viewThe wooden floor, kitchen cabinet, free items given by developer and small toilet excluded from this checking because owner has other plans. Meanwhile, my 2 cents worth, the wooden flooring is badly done and wear and tear has really took its toll. The gaps and split ends are huge headache. Consolation? 1. the wall is quite flat. 2. the door frames are solid except when you reach the base of the frames, i think they covered it with plaster and they made a hash out of it. 3. overall the house is quite bright and well lit but the kitchen, small toilet and yard quite dark. Did not see common area, so no comments. |
|
|
Aug 7 2017, 05:06 PM
|
![]()
Newbie
2 posts Joined: Oct 2007 |
QUOTE(aurora97 @ Jul 31 2017, 12:05 PM) I don’t know whether the toilet is smaller than usual and the toilet door size is abnormal or otherwise. Thanks for your info.. I hav write in to claim for LAD of delay while waiting my defects to be fixed. Hopefully my defects will be fix well.In any case, there is a provision in the Sales and Purchase Agreement that deal with this (NOTE: APOLOGIES in advance, am using the old Schedule H (2002) but I think this provision is unchanged) Position and area of Parcel 13. » Click to show Spoiler - click again to hide... « I suggest that after you have done your defect rectification, you immediate request for a copy of the building plan, more specifically for your unit. You will than need to measure your unit to see if its similar to the building plan. |
|
|
Aug 7 2017, 05:37 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,790 posts Joined: Aug 2007 |
QUOTE(summerssh @ Aug 7 2017, 05:06 PM) Thanks for your info.. I hav write in to claim for LAD of delay while waiting my defects to be fixed. Hopefully my defects will be fix well. Here you go LAD letter i drafted for my friend. Is copied from House Buyer Association Web Site with some slight modifications.» Click to show Spoiler - click again to hide... « Calculation of LAD:- To calculate LAD, your SPA state that the condo need to be completed 36 months from SPA date. Basically, it is End of 36 months calculated up to VP date. (approximately 600+ days overdue) » Click to show Spoiler - click again to hide... « |
|
|
Aug 7 2017, 06:03 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,790 posts Joined: Aug 2007 |
QUOTE(KL HellBoy @ Aug 7 2017, 04:28 PM) The view is nice, almost 180 degree view of Bandar Kinrara (to the rear u have the forest reserve, you have terrace houses on both flanks, semi-D/bungalows in front and the golf course etc…).Also, noteworthy is the security feature of the condo is pretty good, if they gone the extra-mile to do it up properly, it would have been the best condo in Kinrara. Can see the developer made some effort but alas… |
|
|
Aug 7 2017, 06:55 PM
|
![]() ![]()
Junior Member
70 posts Joined: Apr 2014 |
QUOTE(aurora97 @ Aug 7 2017, 06:03 PM) The view is nice, almost 180 degree view of Bandar Kinrara (to the rear u have the forest reserve, you have terrace houses on both flanks, semi-D/bungalows in front and the golf course etc…). Can share why VP delayed for so long? It looked completed many months agoAlso, noteworthy is the security feature of the condo is pretty good, if they gone the extra-mile to do it up properly, it would have been the best condo in Kinrara. Can see the developer made some effort but alas… |
|
|
|
|
|
Aug 7 2017, 07:57 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
3,790 posts Joined: Aug 2007 |
|
|
|
Aug 7 2017, 09:28 PM
|
![]() ![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
2,908 posts Joined: Aug 2011 |
QUOTE(aurora97 @ Aug 7 2017, 05:37 PM) Here you go LAD letter i drafted for my friend. Is copied from House Buyer Association Web Site with some slight modifications. Seriously 600 days ?wow !» Click to show Spoiler - click again to hide... « Calculation of LAD:- To calculate LAD, your SPA state that the condo need to be completed 36 months from SPA date. Basically, it is End of 36 months calculated up to VP date. (approximately 600+ days overdue) » Click to show Spoiler - click again to hide... « |
|
|
Aug 9 2017, 06:47 PM
|
![]() ![]() ![]() ![]() ![]() ![]()
Senior Member
1,646 posts Joined: Jan 2017 |
Really? So long? 600 days OMG
|
|
|
Aug 9 2017, 07:45 PM
|
![]()
Newbie
5 posts Joined: Aug 2017 |
Received a request for Painting and furnishing services From an owner here
He wants us To also check the units for defects. Hope not Too many in his unit So My work can Move decently fast |
|
|
Aug 28 2017, 03:55 PM
|
![]()
Newbie
2 posts Joined: Aug 2017 |
QUOTE(MrProperty.me @ Aug 28 2011, 07:51 PM) Duet Residence a new residential project in Bandar Kinrara (between BK6 Hening and Melodi) will be selling at RM450psf. Any room for it to go beyond RM500 in 1-2 years time? Or will it need longer time to hit that? http://mrproperty.me/wp-content/uploads/2011/08/1.jpg |
|
|
Aug 28 2017, 03:57 PM
|
![]()
Newbie
2 posts Joined: Aug 2017 |
QUOTE(JonathanIB @ Jun 28 2017, 10:38 AM) I tried calling the developer but unable to reach....any idea on the latest updates on duet residence Block B?Please update if anyone have latest updates. thank you. This post has been edited by Sueshas2017: Aug 28 2017, 03:58 PM |
|
|