Koi Kinrara
|
yukisee
|
Sep 21 2011, 09:52 PM
|
Getting Started

|
QUOTE(JRZ @ Sep 21 2011, 02:17 PM) this are the few reasons given by the management for the slow progress of Block D:- 1) Delay in arrival of purchased raw materials 2) Foundation work and frame structure is more complex because of the sky garden weight balance requirements 3) Unsold 18 units (1,405sf) Nobody want to buy 1405sf ?
|
|
|
|
|
|
yukisee
|
Oct 4 2011, 10:10 PM
|
Getting Started

|
QUOTE(kendotnet @ Oct 4 2011, 12:05 AM) Hello all, My name is KEN from Public Bank HeadOffice. Feel free to contact me if you need financing for this project. Thank you very much. Regards, KEN +6017 3707 235 kenweitang@gmail.com Hi Ken, i thought already quota full for public bank loan?
|
|
|
|
|
|
yukisee
|
Oct 17 2011, 10:15 PM
|
Getting Started

|
QUOTE(vincent kee @ Oct 17 2011, 01:10 PM) finaly block d got a bit progress liao.. Yea Hopefully can be done by end of next year
|
|
|
|
|
|
yukisee
|
Oct 18 2011, 08:59 PM
|
Getting Started

|
QUOTE(hornbill_78 @ Oct 18 2011, 01:45 PM) Who want to release Block C unit facing PJ view. Please PM me. Y duwan take block D?
|
|
|
|
|
|
yukisee
|
Oct 19 2011, 10:35 PM
|
Getting Started

|
QUOTE(vincent kee @ Oct 19 2011, 01:27 PM) block c no sunway view, only kl view or landscape vie. Then he want block c for pj view??
|
|
|
|
|
|
yukisee
|
Oct 31 2011, 09:48 PM
|
Getting Started

|
QUOTE(vincent kee @ Oct 31 2011, 08:38 PM) thank you for sharing, hopefully end of next year can get the key.... Wow, got level 8 ady? when i count looks like level 5 only, dunnu how to count
|
|
|
|
|
|
yukisee
|
Nov 1 2011, 01:07 PM
|
Getting Started

|
Nope..lol I know it  Added on November 1, 2011, 1:11 pmNope..lol I know it This post has been edited by yukisee: Nov 1 2011, 01:11 PM
|
|
|
|
|
|
yukisee
|
Dec 20 2011, 10:31 PM
|
Getting Started

|
QUOTE(vincent kee @ Dec 20 2011, 12:06 PM) standing where can get this view? In sunway.. Its opposite the river..
|
|
|
|
|
|
yukisee
|
Jan 2 2012, 04:43 PM
|
Getting Started

|
31.12.11 Block D - Level 12 This post has been edited by yukisee: Feb 5 2012, 10:13 PM
|
|
|
|
|
|
yukisee
|
Jan 24 2012, 01:38 PM
|
Getting Started

|
QUOTE(yukisee @ Jan 2 2012, 04:43 PM) 31.12.11 - Level 12 
|
|
|
|
|
|
yukisee
|
Feb 5 2012, 10:11 PM
|
Getting Started

|
05.02.12 Block C - Lvl 20 Block D - Lvl 15  Added on February 5, 2012, 10:13 pmQUOTE(bcts85 @ Feb 5 2012, 03:35 PM) hi, just want to check in, already bought a unit, corner at block D. yesterday went to block B as my friend stay there. Block D completion now is 12th floor  hopefully can finish up by end of the year. I'll be at Block D level 07  How much u bought? This post has been edited by yukisee: Feb 5 2012, 10:13 PM
|
|
|
|
|
|
yukisee
|
Feb 9 2012, 09:03 PM
|
Getting Started

|
QUOTE(hornbill_78 @ Feb 9 2012, 06:01 PM) yes. this was told by the project engineer. Block C will done by middle of this year? that's fast  Added on February 9, 2012, 9:07 pmQUOTE(janqier @ Jan 30 2012, 03:29 PM) hope can get the key by end of this year. i'll be at block D level 13A  I'm level 16 This post has been edited by yukisee: Feb 9 2012, 09:07 PM
|
|
|
|
|
|
yukisee
|
Feb 10 2012, 09:09 PM
|
Getting Started

|
QUOTE(hornbill_78 @ Feb 10 2012, 05:44 PM) mine also.. which unit your are? maybe we are future nighbour... 12..how about u?
|
|
|
|
|
|
yukisee
|
Feb 13 2012, 04:26 PM
|
Getting Started

|
QUOTE(frimily @ Feb 13 2012, 11:33 AM) Hi Yuki We are neighbour, I am level 12-11. And you?  Sorry, im lvl 16.type wrong ady.however, we r still neighbour
|
|
|
|
|
|
yukisee
|
Feb 13 2012, 10:56 PM
|
Getting Started

|
QUOTE(hornbill_78 @ Feb 13 2012, 04:43 PM) Hi Yuki, You are my neighbour.. mine is L16 too LOL, which unit?
|
|
|
|
|
|
yukisee
|
Feb 20 2012, 09:06 PM
|
Getting Started

|
QUOTE(vincent kee @ Feb 20 2012, 06:12 PM) it's two individual tower, so it's possible, they might close the block d like how the close phase 2 last time. What u mean by close the block D? When is the expection date for block C and D? Added on February 20, 2012, 9:49 pmQUOTE(vincent kee @ Feb 20 2012, 06:12 PM) it's two individual tower, so it's possible, they might close the block d like how the close phase 2 last time. What u mean by close the block D? When is the expection date for block C and D? This post has been edited by yukisee: Feb 20 2012, 09:49 PM
|
|
|
|
|
|
yukisee
|
Feb 20 2012, 10:21 PM
|
Getting Started

|
QUOTE(vincent kee @ Feb 20 2012, 10:16 PM) m means devide block d by using bill board or hoarding than can continue the construction work at block d. so will handover block c first, i guess!! Added on February 20, 2012, 10:17 pmi think very soon will withdraw another 5% for drainage work. OIC so when is the expectation date for both block? Added on February 20, 2012, 10:21 pmQUOTE(vincent kee @ Feb 20 2012, 10:16 PM) m means devide block d by using bill board or hoarding than can continue the construction work at block d. so will handover block c first, i guess!! Added on February 20, 2012, 10:17 pmi think very soon will withdraw another 5% for drainage work. OIC so when is the expectation date for both block? This post has been edited by yukisee: Feb 20 2012, 10:21 PM
|
|
|
|
|
|
yukisee
|
Feb 23 2012, 10:31 PM
|
Getting Started

|
QUOTE(lionking331 @ Feb 23 2012, 09:17 PM) Mine is on the 11th floor... corner lot but is 1200++ sqft.. Yup yup.. we can discuss in LYN too.. kitchen cabinet i might wan to go for LYN highest recommended one...Erny_Looi. Kitchen cabinet not included already?
|
|
|
|
|
|
yukisee
|
Feb 24 2012, 11:08 PM
|
Getting Started

|
QUOTE(lionking331 @ Feb 24 2012, 02:53 PM) Mine type is not included... Which type?
|
|
|
|
|