1) Please look into the lighting point .. Only crazy people will direct lighting every point to DB.. looking at the BQ .. thats a lot of ceiling light point.
Contractor need to split the quantity
a) direct light point to DB - how many point direct to DB
b) How many point will be looping from the direct point (price should be lesser than the direct to DB price )
from that BQ- the contractor simply put everything as direct... not split looping and direct pricing..
this will save a lot of RM
2) Same goes to the 13amp power point.. not every point goes direct to DB... some point just need to loop side by side...... (depends on the electrical usage or appliances used)
3) Does this price inclusive concealed plastering works back after the installation of conduit?
hope this help
cheers mate
Izwan
www.archidstudio.com