views
     
TScisdelo
post Oct 26 2020, 05:06 AM, updated 6y ago

New Member
*
Newbie
8 posts

Joined: Oct 2017


So i have a question, what can we do if the developer keeps delaying the project? its been 2 years over the schedule. can we just change our mind and just sell back to the developer? is there something we can do?
TScisdelo
post Oct 26 2020, 05:06 AM

New Member
*
Newbie
8 posts

Joined: Oct 2017


So i have a question, what can we do if the developer keeps delaying the project? its been 2 years over the schedule. can we just change our mind and just sell back to the developer? is there something we can do?
mini orchard
post Oct 26 2020, 05:59 AM

10k Club
********
All Stars
14,511 posts

Joined: Sep 2017
QUOTE(cisdelo @ Oct 26 2020, 05:06 AM)
So i have a question, what can we do if the developer keeps delaying the project? its been 2 years over the schedule. can we just change our mind and just sell back to the developer? is there something we can do?
*
The only thing you can do is to complaint to whoever wants to listen ... Zuraida's office, MP, Adun, Press, and of course this forum.

Gather as many purchasers b4 doing the above. Lone voice is like an MP without a party in Parliment.

PS ...

If only some buyers dont get entice by freebies and cashback, developer's background check is never a concern until such things happened. Sometimes buying a slightly more expensive subsale is not too bad afterall and with today's market, more subsales are cheaper than launching ... can choose, can see, can nego, everything also can ... but of course need some downpayment and cost.

This post has been edited by mini orchard: Oct 26 2020, 07:25 AM
CHIP CN
post Oct 26 2020, 06:36 AM

Tuned by CHIP CN
******
Senior Member
1,262 posts

Joined: Apr 2007


Boleh saman...
cy91
post Oct 26 2020, 08:02 AM

Regular
******
Senior Member
1,296 posts

Joined: Nov 2019
Maju Kuala Lumpur?
BeetchX
post Oct 26 2020, 10:34 AM

Getting Started
**
Junior Member
115 posts

Joined: Sep 2013
QUOTE(cisdelo @ Oct 26 2020, 05:06 AM)
So i have a question, what can we do if the developer keeps delaying the project? its been 2 years over the schedule. can we just change our mind and just sell back to the developer? is there something we can do?
*
Delaying meaning they already completed but have not handover yet or they are still building?. There's nothing you can do for now.. may be you can check their construction period. If the construction is below 50% and you decided to pull out, then you will get a 10% penalty charge. then meanwhile your bank loan also will kena penalty if you cancel the loan. But if you continue with the project.. then suddenly the developer declare bankruptcy.. then you got no choice but to continue serve the loan for the remaining year.. Thats the worst case scenario. I have not come across this issue yet.. but i think its more or less like this la...

Which project ha... where?
l4nunm4l4y4
post Oct 26 2020, 10:36 AM

Enthusiast
*****
Junior Member
749 posts

Joined: Aug 2011
Talam again ah (using some other name)?
mini orchard
post Oct 26 2020, 10:45 AM

10k Club
********
All Stars
14,511 posts

Joined: Sep 2017
QUOTE(BeetchX @ Oct 26 2020, 10:34 AM)
Delaying meaning they already completed but have not handover yet or they are still building?. There's nothing you can do for now.. may be you can check their construction period. If the construction is below 50% and you decided to pull out, then you will get a 10% penalty charge. then meanwhile your bank loan also will kena penalty if you cancel the loan. But if you continue with the project.. then suddenly the developer declare bankruptcy.. then you got no choice but to continue serve the loan for the remaining year.. Thats the worst case scenario. I have not come across this issue yet.. but i think its more or less like this la...

Which project ha... where?
*
What happen then to the partial loan released to developer ? You think the developer will return to the bank ?

If is 10% penalty only and nothing else, I will go for it.

So what penalty payment are you refering about the bank loan ?

This post has been edited by mini orchard: Oct 26 2020, 10:48 AM
dannychen
post Oct 26 2020, 10:52 AM

Regular
******
Senior Member
1,263 posts

Joined: Dec 2009
I think you can report to KPKT and seek for their advice.

source
kochin
post Oct 26 2020, 10:54 AM

I just hope I do!
********
All Stars
10,314 posts

Joined: Dec 2009
From: Malaysia


if you can share which project, forummers here can advise better.
kochin
post Oct 26 2020, 10:55 AM

I just hope I do!
********
All Stars
10,314 posts

Joined: Dec 2009
From: Malaysia


QUOTE(BeetchX @ Oct 26 2020, 10:34 AM)
Delaying meaning they already completed but have not handover yet or they are still building?. There's nothing you can do for now.. may be you can check their construction period. If the construction is below 50% and you decided to pull out, then you will get a 10% penalty charge. then meanwhile your bank loan also will kena penalty if you cancel the loan. But if you continue with the project.. then suddenly the developer declare bankruptcy.. then you got no choice but to continue serve the loan for the remaining year.. Thats the worst case scenario. I have not come across this issue yet.. but i think its more or less like this la...

Which project ha... where?
*
correct. if more than 50% it's 20% penalty cost.
gks
post Oct 26 2020, 11:09 AM

Look at all my stars!!
*******
Senior Member
3,833 posts

Joined: May 2008
QUOTE(BeetchX @ Oct 26 2020, 10:34 AM)
Delaying meaning they already completed but have not handover yet or they are still building?. There's nothing you can do for now.. may be you can check their construction period. If the construction is below 50% and you decided to pull out, then you will get a 10% penalty charge. then meanwhile your bank loan also will kena penalty if you cancel the loan. But if you continue with the project.. then suddenly the developer declare bankruptcy.. then you got no choice but to continue serve the loan for the remaining year.. Thats the worst case scenario. I have not come across this issue yet.. but i think its more or less like this la...

Which project ha... where?
*
This i believe is condition where purchaser has defaulted, not by developer. If it is standard sch h, I do not think purchaser and bank have any recovery clause in case of delay/ abandon potential from developer.

That's is one of the primary push by HBA to go forward with BTS where buyers only require to put 10% deposit till VP.

This post has been edited by gks: Oct 26 2020, 11:10 AM
TScisdelo
post Oct 26 2020, 12:31 PM

New Member
*
Newbie
8 posts

Joined: Oct 2017


QUOTE(BeetchX @ Oct 26 2020, 10:34 AM)
Delaying meaning they already completed but have not handover yet or they are still building?. There's nothing you can do for now.. may be you can check their construction period. If the construction is below 50% and you decided to pull out, then you will get a 10% penalty charge. then meanwhile your bank loan also will kena penalty if you cancel the loan. But if you continue with the project.. then suddenly the developer declare bankruptcy.. then you got no choice but to continue serve the loan for the remaining year.. Thats the worst case scenario. I have not come across this issue yet.. but i think its more or less like this la...

Which project ha... where?
*
shah alam seksyen 13. beside giant supermarket.
TScisdelo
post Oct 26 2020, 12:33 PM

New Member
*
Newbie
8 posts

Joined: Oct 2017


QUOTE(kochin @ Oct 26 2020, 10:54 AM)
if you can share which project, forummers here can advise better.
*
shah alam seksyen 13. called sentralis by ttdi naza
TScisdelo
post Oct 26 2020, 12:50 PM

New Member
*
Newbie
8 posts

Joined: Oct 2017


QUOTE(mini orchard @ Oct 26 2020, 05:59 AM)
The only thing you can do is to complaint to whoever wants to listen ... Zuraida's office, MP, Adun, Press, and of course this forum.

Gather as many purchasers b4 doing the above. Lone voice is like an MP without a party in Parliment.

PS ...

If only some buyers dont get entice by freebies and cashback, developer's background check is never a concern until such things happened. Sometimes buying a slightly more expensive subsale is not too bad afterall and with today's market, more subsales are cheaper than launching ... can choose, can see, can nego, everything also can ... but of course need some downpayment and cost.
*
Okay here's a little details about the project it was ttdi sentralis, seksyen 13 shah alam. in spa it says completion early 2019. then it got delayed they said it should be completed early 2020. but now it still under construction. so its already 1 year and half.
BeetchX
post Oct 26 2020, 01:04 PM

Getting Started
**
Junior Member
115 posts

Joined: Sep 2013
QUOTE(cisdelo @ Oct 26 2020, 12:33 PM)
shah alam seksyen 13. called sentralis by ttdi naza
*
By Naza TTDI wohhh... consider one of the big developer. wont run away ba.... or else how they gonna continue with their other projects.
BeetchX
post Oct 26 2020, 01:11 PM

Getting Started
**
Junior Member
115 posts

Joined: Sep 2013
Now pandemic, you barely see foreign worker in the construction side.. and also those on going highway construction... in the end of the day.. just claim LAD then... also depends on whether developer got apply for extension due to the pandemic which i believe in the next 2 to 3 years, tribunal gonna be super busy with the LAD cases for those project completing on that time.

 