Very disappointed with Sri Donglai / Dergahayu project.
The 3 Towers Jalan Ampang has been completed since last year. Hawever, they still not willing release the VP.
I know part of the Towers have released but don't know why they keep delay for Tower 2A.
My SPA signed in year 2016 and they directly billed me 95% (due to almost completed) and this year I started to pay my monthly full loan instalment.
Paying interest for 3 years and get nothing, and keep on telling completion date will be within 4 years from SPA date and LAD only can be claim after 4 years from SPA date. What can I do now? Keep paying only?
Can any sifu give advise or anyone facing the same situation?
This post has been edited by mia1998: Jul 25 2019, 05:45 PM
3 Towers Jalan Ampang Tower 2A, Whole building completed but no VP issue
Jul 25 2019, 05:42 PM, updated 7y ago