QUOTE(weezerd @ Mar 18 2023, 11:58 AM)
This is the Fasa 4
https://forum.lowyat.net/topic/4973987/+80Duta Kiara Road, no idea about it. But the connection would be very helpful to traffic users if its connected.
Jalan Segambut Upgrade is divided into 4 phases.
Think of Phase 1 as starting from north, which is Jln Segambut whereas Phase 4 is from south , Mont Kiara.
Phase 1 - The main Jln Segambut, along the road we have Era Duta North, Riana Dutamas, SRJKC Khai Chee, etc, it ended at flyover near SPPK Segambut. Completed long time ago, a decade or so.
Phase 2 - Currently road construction in progress. It’s about 800 mtr stretch connecting the end of flyover (in phase 1) to Petron North Kiara. Expected to complete by June 2023.
Phase 3 - Not started yet, This is supposed to be a road from Petron North Kiara connecting to Jalan Kiara 4. I think this will start concurrently with MRT construction, as MRT Bkt Segambut will be along this road. Miranda Hill is along this road as well.
Phase 4 - It’s considered semi-complete. This is actually Jalan Kiara 4, and currently it is terminating at Inspirasi Mont Kiara. Allevia Mont Kiara which is currently under construction will further extend the road a little bit, and DBKL will then takeover and link it to Phase 3.
This post has been edited by Avenger_2012: Mar 20 2023, 02:45 AM