QUOTE(Critical_Fallacy @ Oct 18 2014, 02:21 AM)
(1a) If the Employer cannot give site possession on the due date, can the matter be resolved by the Architect giving an instruction to postpone the Works as per the Contract?
(1b) If the Architect does not grant Time Extension, and the Contractor is required to perform accelerated Works to catch up with the project’s completion schedule, can the Contractor use the Employer’s delay in giving the site possession as a reason to justify a claim for VO?
1a. there are basically 2 type of breach in contract. 1 is conditional breach (can rescind the contract and claim for damages) another 1 is warranty breach (cannot rescind the contract but can claim remedy). not giving site possession is a conditional breach and the contractor can terminate the contract and claim for expenses incurred due to the breach. seems like ur case u accepted the late site possession. architect can postpone the work but it's up to contractor to accept it or not.(1b) If the Architect does not grant Time Extension, and the Contractor is required to perform accelerated Works to catch up with the project’s completion schedule, can the Contractor use the Employer’s delay in giving the site possession as a reason to justify a claim for VO?
1b. yes, but it's has to be done at the beginning. let's say contract duration is May 2014 to June 2016, after u take the possession on July 2014, u should immediately claim for eot until August 2016. but in commercial context, u make employer unhappy especially when starting the work at beginning.
if u said claim vo due to the late sit possession, have to see whether it have direct impact to the vo work. but bear in mine VO is additional work to the project while loss and expenses claim is due to extended period of time.
This post has been edited by iwubpreve: Oct 18 2014, 08:56 AM
Oct 18 2014, 08:18 AM

Quote

0.0173sec
0.19
6 queries
GZIP Disabled