hey everyone, just want to share with you of an update for central SOHO i got from yuktung when i drop by their office last week. according to the person in charge for central residence, at this time they are still on track to get CCC by end of december 2014, and told me to expect call by then to settle some fees.
CCC or previously CF is on basic unit as in S&P without any additional fittings eg kitchen cabinet etc that yuktung offered.
once they got CCC and can VP, they will call us to visually inspect. when is this? it's by batch of units. some purchaser will get this by Q1 and some by Q2 2015
once inspection is done after VP, you will need to return the key back to them so that they can install the additional fittings eg kitchen cabinets, water heater plaster ceiling etc for about 3 months and then you have to come again and inspect the additional fittings with them before they can fully handover the key.
every units in central SOHO are expected to be ready to move in by purchaser by end of Q2 2015.
hope this answer to our questions
Thanks for the update. ....