Anyone know when is the latest date that the developer has to issue the CF before penalty?
Axile
post Nov 17 2015, 11:35 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(LSA82 @ Nov 17 2015, 11:18 PM)
Mine one is after feb 2016
*
Means ur SNP date is February 2013?
Axile
post Nov 18 2015, 03:24 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(badman84 @ Nov 18 2015, 03:19 PM)
What is ccc??
*
Certificate of Completion and Compliance. Means owner can move in if CCC issued.
Axile
post Nov 24 2015, 09:33 AM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(badman84 @ Nov 24 2015, 06:58 AM)
If not mistaken, yours is b block right?
*
Any idea the first block to receive CCC will be which block?
Axile
post Nov 24 2015, 08:02 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(Fairview @ Nov 24 2015, 04:18 PM)
Believe all three (3) blocks received the CCC at the same time. However as different purchasers signed the SPA at different time we are unsure whether the developer will release the keys at the same time or in batches following the date of the SPA.  Anyway the 1st group of purchasers without doubt are scheduled to receive their keys next month ie Dec as they had signed the SPA in Dec 2012. It must be very exciting. Cheers.
*
Hope can move in by Dec / Jan.

Btw, anyone know if the basement comes with a hose or water tap for us to wash our cars?
Axile
post Dec 3 2015, 10:23 AM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(waterking911 @ Dec 3 2015, 08:48 AM)
How developer answer you, have developer told you when can get the key to move in?
*
They pick up the call after 2 beep surprisingly. I asked them but they are unable to give me an exact date but latest by end of this month. Current status is pending for bank to revert them on the loan. Hmmmm.
Axile
post Dec 4 2015, 02:57 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(Fairview @ Dec 4 2015, 10:51 AM)
Understand once your bank pay the latest billing you could go and collect the keys. So check with your bank next week whether they have disbursed the money to the developer. Best wishes.
*
Are you one of the owner too?
Axile
post Dec 8 2015, 11:27 AM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


Congratulations to all owners who have received their CCC. Got mine today smile.gif
Axile
post Dec 8 2015, 11:58 AM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(henry514 @ Dec 8 2015, 11:40 AM)
U can get ur key edy? May I know the date u sign S&P?
*
S&P signed on 12 Dec. Haven't get the key yet. Need to schedule a day somewhere this or next week to retrieve the key.
Axile
post Dec 8 2015, 12:05 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(henry514 @ Dec 8 2015, 12:02 PM)
Mine is JAN 2013. I wondering the key only open for person who sign the S&P on DEC 2012 1st or open for all in 1 shot... hmm.gif  hmm.gif
So Jealous leh...coz i not yet receive mine.... cry.gif  cry.gif  cry.gif
*
No worries, I think you will received it pretty soon. Give it 1-2 weeks smile.gif
Axile
post Dec 18 2015, 09:57 AM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


Anyone going to take their keys this weekend?
Axile
post Dec 19 2015, 12:25 AM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(henry514 @ Dec 18 2015, 04:46 PM)
Bank release your last payment edy??
*
Yup. smile.gif
Axile
post Dec 21 2015, 02:43 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(badman84 @ Dec 20 2015, 10:36 AM)
Have u received the progressive payment notice inside the VP too? That means bank release payment ady?
*
Yeah released already.
Axile
post Dec 22 2015, 09:11 AM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(badman84 @ Dec 22 2015, 08:47 AM)
mine will get the key at 3.30pm today as called. yeah
*
Congratulations! rclxms.gif
Axile
post Dec 22 2015, 02:53 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


» Click to show Spoiler - click again to hide... «


Do share any defects found with image and the affected area if found any.

Thanks!

This post has been edited by Axile: Dec 22 2015, 02:53 PM
Axile
post Dec 22 2015, 10:43 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(badman84 @ Dec 22 2015, 07:31 PM)
Now the problem how to renovate. The layout a bit weird when u see the actual.
*
Agree on the layout is kind of unique.
Axile
post Jan 6 2016, 02:54 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(badman84 @ Jan 4 2016, 12:04 PM)
yes, will do grille at yard side. I won't move in so fast as some renovation jobs are needed.
*
Does the developer allow doing grille at yard open area? Since the grille layout that they provide cover entrance, balcony, room window and toilet but doesn't has yard specs and design.
Axile
post Jan 6 2016, 11:31 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(Dreambig99 @ Jan 4 2016, 11:06 AM)
Anyone have start to renovate your house? Mind to share the cost for the main door grill, kitchen cabinet, plaster ceiling, wardrobe, tv console, painting..
Also, will you all do a wall with window at yard side?

Anyone will move in before CNY?
*
Hi Dreambig, will you move in before CNY? I will be moving in before CNY (hopefully).

Would like to know have you already gotten contact for grille contractor? If not yet, just want to share with you my contractor because he will give us special rate if both parties come to an agreement for him to be our grille contractor.

The company is Three Kim Metal Works.

Portfolio & Reviews

FB
https://www.facebook.com/Three-Kim-Sdn-Bhd-...19963244769158/

LYN
https://forum.lowyat.net/topic/2494426/all
https://forum.lowyat.net/topic/3262659/all
https://forum.lowyat.net/topic/3303625/all


I have surveyed with another 2 more contractors but this comes to the most affordable yet not compromising QC (good review on workmanship).

If you are interested please PM me for further discussion on the price.

Thanks and appreciate your prompt response on this!

Anyone who interested can PM me too. smile.gif

Axile
post Jan 19 2016, 09:12 AM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


Recommended contractors:

Mr Aik (Electrician) - 013-322 3333
Mr Kum (Plaster ceiling) - 012-318 1135
Mr Yap (Kitchen cabinet) - 012-7280699
3 Kim Metal (Grille) - 012-214 9382

Anyone moving in before CNY?
Axile
post Jan 20 2016, 02:34 PM

Getting Started
**
Junior Member
85 posts

Joined: Nov 2015


QUOTE(skyny @ Jan 20 2016, 01:35 PM)
Can u pls pm me the quotation for plaster ceiling and electrician. Thanks!
*
Hi Skyny, I do not have quotation for plaster ceiling as I have ask him to proceed to work after comparing to 2 other plaster ceiling quotations and he is the cheapest (recommended by my friend).

As for electrician here is the charges:
1) Lighting point ceiling downlight - RM50/point
2) 13A power point - RM80/point
3) Ceiling downlight cut - RM15/hole
4) Pendant lights installation - RM12/pcs