January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

RUBBER RESEARCH INSTITUTE

Aerial view of the MRT guideway being constructed by the launch gantry.
user posted image

View of the complete MRT elevated guideway and construction work for the future MRT station, provisionally called Taman Industri Sungai Buloh.
user posted image

View of the launch gantry completing the first continuous kilometer of elevated guideway of the MRT Sungai Buloh-Kajang Line.
user posted image

View of the launch gantry completing the span of the first continuous kilometer of elevated guideway of the MRT Sungai Buloh-Kajang Line.
user posted image

View of the launch gantry completing the span of the first continuous kilometer of elevated guideway of the MRT Sungai Buloh-Kajang Line.
user posted image

Close-up view of the launching of segmented box girders for the MRT elevated guideway.
user posted image

View of segmented box girders for the MRT elevated guideway being launched.
user posted image

View of piers towards Jalan Sungai Buloh-Subang awaiting the launch gantry.
user posted image

TAMAN INDUSTRI SUNGAI BULOH

MRT piers awaiting the launch gantry to construct the guideway
user posted image

Completed MRT piers in between factory lots, Pasar Muhibbah Kota Damansara and other buildings.
user posted image
TSKampung2005
post Mar 14 2014, 12:09 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

PERSIARAN SURIAN, PJU 5

MRT pier construction along Persiaran Surian.
user posted image

user posted image

PERSIARAN SURIAN, DATARAN SUNWAY

View of the completed diversion for the monsoon drain to enable the construction of the underpass at the Persiaran Mahogani intersection.
user posted image

PERSIARAN SURIAN, PELANGI DAMANSARA

MRT construction work along the median of Persiaran Surian.
user posted image

user posted image

PERSIARAN SURIAN, MUTIARA DAMANSARA

View of the traffic management plan where LDP-bound traffic is diverted onto the right side (Kota Damansara-bound) of the road to enable the construction of the MRT guideway and station to be carried out.
user posted image

user posted image

DAMANSARA-PUCHONG HIGHWAY, DAMANSARA UTAMA

MRT piers being constructed beside the highway. The MRT alignment will span across the highway at this location.
user posted image
TSKampung2005
post Mar 14 2014, 12:14 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

JALAN DAMANSARA, TAMAN TUN DR ISMAIL

MRT elevated guideway being constructed above the median of the road.
user posted image

user posted image

user posted image

MRT piers waiting for the launch gantry to construct the elevated guideway.
user posted image

SPRINT HIGHWAY, KELAB GOLF PERKHIDMATAN AWAM

MRT pier construction along the highway.
user posted image

SPRINT HIGHWAY, SECTION 16

View of a launch gantry constructing the MRT guideway at the site of the future MRT station.
user posted image

SPRINT HIGHWAY, MEDAN DAMANSARA AND BUKIT DAMANSARA

MRT construction work along the median of the highway. Space at the median was created when the new left lane for the highway was opened.
user posted image

MRT construction work along the median of the highway. Space at the median was created when the new left lane for the highway (right) was opened.
user posted image
TSKampung2005
post Mar 14 2014, 12:19 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

SPRINT HIGHWAY, MAAROF INTERCHANGE

View of the completed piers at Maarof Interchange. The steel trusses (red structure) is a temporary structure for the construction of the future Pusat Bandar Damansara Station.
user posted image

user posted image

user posted image

SPRINT HIGHWAY, PUSAT BANDAR DAMANSARA

Pier construction taking place near Pusat Bandar Damansara.
user posted image

JALAN SEMANTAN

View of MRT station construction works taking place at the intersection of Jalan Semantan and Jalan Damansara Endah.
user posted image

Construction works for the MRT project in front on 10 Semantan Condominium.
user posted image
TSKampung2005
post Mar 14 2014, 12:23 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

SEMANTAN PORTAL

Ventilation fans blowing fresh air into the tunnels.
user posted image

View of the work area at the portal where tunnel lining segments are loaded onto a train to be brought to the tunnel boring machine.
user posted image

Wagons which are pulled by a locomotive used to transport tunnel lining segments to the tunnel boring machine.
user posted image

View of the completed tunnel between the Semantan Portal and KL Sentral MRT Station. The tunnel for north-bound trains was completed on 24 December 2013 while the tunnel for south-bound trains was completed on 16 January 2014.
user posted image

KL SENTRAL MRT STATION

Personnel from MRT Project underground package contractor MMC Gamuda KVMRT (T) Sdn Bhd celebrating the Semantan 2 Tunnel Boring Machine breakthrough on 16 January 2014.
user posted image

View of the tunnel eye for the south-bound tunnel at the platform level of the station awaiting the tunnel boring machine to breakthrough.
user posted image
user posted image

Semantan 1 Tunnel Boring Machine which excavated the north-bound tunnel and broke through on 24 December 2013 being refurbished at the platform level of the station box.
user posted image
TSKampung2005
post Mar 14 2014, 12:30 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

PASAR SENI MRT STATION

View of the station box where construction of the reinforced concrete wall between the concourse slab and the roof slab is in progress.
user posted image

Construction of the reinforced concrete wall between the concourse slab and the roof slab is in progress at the former Klang Bus Stand location.
user posted image

View of the basement of the former Plaza Warisan being demolished.
user posted image

Reinforced concrete wall of the station being constructed.
user posted image

MERDEKA STATION

View of struts holding apart the walls of the station box. As at the end of January, excavation of the base slab formation level had begun.
user posted image

user posted image

View of the top side of the station box.
user posted image
TSKampung2005
post Mar 14 2014, 12:36 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

PUDU LAUNCH SHAFT

View of the top side of the shaft. Behind is the Kuala Lumpur Police Contingent building.
user posted image

View of the southbound tunnel slab of the shaft. The tunnel boring machine will be launched from here.
user posted image
user posted image

Struts holding apart the wall of the shaft.
user posted image

BUKIT BINTANG MRT STATION

Aerial view of the new work area of the station site just after Jalan Bukit Bintang was realigned back to the original alignment.
user posted image

Aerial view of the new area of the station worksite at the end of January, with more had been machinery deployed.
user posted image

The closed road diversion after Jalan Bukit Bintang was realigned back to the original alignment.
user posted image

Machinery starting work at the new area of the station worksite.
user posted image

The closed road diversion (right) after Jalan Bukit Bintang was realigned back to the original alignment.
user posted image

View of the Jalan Bukit Bintang sidewalk between KFC and Agora Hotel after the removal of hoardings.
user posted image
TSKampung2005
post Mar 14 2014, 12:39 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

INAI LAUNCH SHAFT

View of the completed section of the tunnel for southbound trains from Inai Shaft towards Bukit Bintang.
user posted image

View of the multi-service vehicle leaving the tunnel boring machine inside the completed section of the tunnel for southbound trains from Inai Shaft towards Bukit Bintang.
user posted image

View inside the back-up gantries of the tunnel boring machine inside the completed section of the tunnel for southbound trains from Inai Shaft towards Bukit Bintang.
user posted image

Crane at the topside of the shaft which lowers tunnel lining segments into the shaft.
user posted image

Crane at the topside of the shaft which lifts tunnel lining segments into the shaft.
user posted image

View of the Inai Lower Shaft where the temporary mortar fill is being hacked to enable the tunnel to be reached.
user posted image
TSKampung2005
post Mar 14 2014, 12:45 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

PASAR RAKYAT STATION

Cochrane 2 Tunnel Boring Machine breaking through on 9 January 2014.
user posted image

Tunnel eye for the Cochrane 2 Tunnel Boring Machine breakthrough on 9 January 2014.
user posted image

View from the top of the shaft of the tunnel eye for the Cochrane 2 Tunnel Boring Machine breakthrough on 9 January 2014.
user posted image

Backhoe clearing the debri after the Cochrane 2 Tunnel Boring Machine breakthrough on 9 January 2014.
user posted image

MRT Project Underground Work Package Contractor MMC Gamuda KVMRT (T) Sdn Bhd personnel celebrating the Cochrane 2 Tunnel Boring Machine breakthrough on 9 January 2014.
user posted image

View of the northern end of the station box.
user posted image
TSKampung2005
post Mar 14 2014, 12:51 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

COCHRANE LAUNCH SHAFT AND STATION

View of the Cochrane Station box (which was also used as the launch shaft for four tunnel boring machines) where the station structure is being constructed.
user posted image

Construction of the station wall in progress.
user posted image

Station wall and platform being constructed at the bottom of the station box.
user posted image

Construction of the platform and platform edge pillars in progress.
user posted image

Rebar for the platform slab being installed.
user posted image

View of the completed tunnel from Cochrane.
user posted image

MALURI MRT STATION

Drilling for kingposts in progress in the station box area.
user posted image

View of metro decking over the station box area which is unusually clear of traffic.
user posted image

Excavation work beneath the metro decking. As at the end of January, 35% of the station box has been excavated.
user posted image

user posted image


TSKampung2005
post Mar 14 2014, 12:52 PM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp

http://mymrt.com.my/en/project-updates#prettyPhoto

MALURI PORTAL

Controlled blasting works in progress at the tunnel boring machine retrieval area of the shaft.
user posted image

Struts holding apart the retaining wall at the cut-and-cover section of the portal.
user posted image

user posted image

Aerial view of the portal abutment with the elevated guideway near SJK© Naam Kheung.
user posted image
TSKampung2005
post Mar 16 2014, 01:17 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp
http://mymrt.com.my/en/project-updates#prettyPhoto

SRI SABAH FLATS, CHERAS

Completed MRT guideway from the Maluri Portal (right) where the alignment emerges from underground. As at the end of January, 19 spans of the guideway had been completed in Package V5.
user posted image

A launch gantry constructing the span over the road near SJK© Naam Kheung. As at the end of January, 19 spans of the guideway had been completed in Package V5.
user posted image

View of the completed MRT guideway running parallel to Jalan Loke Yew. As at the end of January, 19 spans of the guideway had been completed in Package V5.
user posted image

TAMAN MIDAH, CHERAS

Completed piers and MRT station construction work being carried out in front of the shops in Taman Midah.
user posted image

MRT station construction work being carried out in front of the shops in Taman Midah.
user posted image

A launch gantry constructing the MRT guideway in front of Tesco Taman Midah. As at the end of January, 19 spans of the guideway had been completed in Package V5.
user posted image

TAMAN MUTIARA BARAT, CHERAS

MRT construction along the median of Jalan Cheras. Completed piers on the right are for a siding track.
user posted image

MRT construction along the median of Jalan Cheras (right). Completed piers on the left are for a siding track.
user posted image

CHERAS-KAJANG HIGHWAY, TAMAN SHAHJAYA

A launch gantry constructing the MRT guideway. As at the end of January, 20 spans of the guideway had been completed in Package V6.
user posted image

A launch gantry constructing the MRT guideway. As at the end of January, 20 spans of the guideway had been completed in Package V6.
user posted image
cnvery
post Mar 16 2014, 01:32 AM

Regular
******
Senior Member
1,786 posts

Joined: Dec 2009

Good progress!

+1
TSKampung2005
post Mar 16 2014, 01:36 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp
http://mymrt.com.my/en/project-updates#prettyPhoto

CHERAS-KAJANG HIGHWAY, BANDAR TUN HUSSEIN ONN

View of completed guideway spanning over Lebuh Besar Bandar Tun Hussein Onn. As at the end of January, 20 spans of the guideway had been completed in Package V6.
user posted image

View of completed guideway spanning over Lebuh Besar Bandar Tun Hussein Onn. As at the end of January, 20 spans of the guideway had been completed in Package V6.
user posted image

Construction for the Bandar Tun Hussein Onn station in progress.
user posted image

Construction for the Bandar Tun Hussein Onn station in progress.
user posted image

CHERAS-KAJANG HIGHWAY, BUKIT DUKUNG

Construction of the pier for the special crossing over the highway in progress.
user posted image

Construction for the MRT station provisionally known as Taman Koperasi in progress.
user posted image

CHERAS-KAJANG HIGHWAY, SUNGAI BALAK INTERCHANGE

Completed piers and segmented box girders ready for the launch gantry to erect the MRT guideway.
user posted image

A launch gantry erecting the MRT guideway. As at the end of January, 12 spans of the guideway had been completed in Package V7.
user posted image

A launch gantry erecting the MRT guideway. As at the end of January, 12 spans of the guideway had been completed in Package V7.
user posted image

A launch gantry erecting the MRT guideway. As at the end of January, 12 spans of the guideway had been completed in Package V7.
user posted image

This post has been edited by Kampung2005: Mar 16 2014, 01:37 AM
TSKampung2005
post Mar 16 2014, 01:37 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp
http://mymrt.com.my/en/project-updates#prettyPhoto

CHERAS-KAJANG HIGHWAY, TAMAN MESRA

MRT piers being constructed along the highway.
user posted image

Launch gantry 1 being assembled along the highway.
user posted image

Launch gantry 1 being assembled along the highway.
user posted image

MRT pier construction at the junction of the spur line to the Kajang Depot.
user posted image

MRT pier construction for the spur line into the Kajang Depot.
user posted image

Launch Gantry 2 constructing the MRT guideway for the spur line into the Kajang Depot. As at the end of January, five spans of the guideway had been completed in Package V8.
user posted image

Segmented box girder delivery to Launch Gantry 2 for the construction of the MRT guideway for the spur line into the Kajang Depot. As at the end of January, five spans of the guideway had been completed in Package V8.
user posted image

Launch Gantry 2 constructing the MRT guideway for the spur line into the Kajang Depot. As at the end of January, five spans of the guideway had been completed in Package V8.
user posted image

Launch Gantry 2 constructing the MRT guideway for the spur line into the Kajang Depot. As at the end of January, five spans of the guideway had been completed in Package V8.
user posted image
TSKampung2005
post Mar 16 2014, 01:43 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp
http://mymrt.com.my/en/project-updates#prettyPhoto

KAJANG CENTRALISED LABOUR QUARTERS

Aerial view of the Kajang Centralised Labour quarters. On the left is the quarters for Package V7 while that on the right is for Package V8.
user posted image

Aerial view of the Kajang Centralised Labour Quarters for Package V7.
user posted image

Living quarters in the centralized labour quarters.
user posted image

Aerial view of the Kajang Centralised Labour Quarters for Package V8.
user posted image

KAJANG DEPOT

Aerial view of the Kajang Depot.
user posted image
TSKampung2005
post Mar 16 2014, 01:45 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp
http://mymrt.com.my/en/project-updates#prettyPhoto

JALAN CHERAS, SUNGAI JERNIH

MRT construction along Jalan Cheras north of Kajang.
user posted image

MRT pier construction in RTM land near Kajang Stadium.
user posted image
TSKampung2005
post Mar 16 2014, 01:48 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
January 2013 update by MRT Corp
http://mymrt.com.my/en/project-updates#prettyPhoto

KAJANG KTM STATION

Temporary siding track for KTM being constructed.
user posted image

MRT piers being constructed near the Kajang KTM Station.
user posted image

MRT piers being constructed near the Kajang KTM Station.
user posted image

MRT piers being constructed near the Kajang KTM Station.
user posted image

View of the temporary car park (left) and construction work for the Kajang Station Multistorey Park and Ride.
user posted image

Concreting works for ground beams in progress for the Kajang Station Multistorey Park and Ride.
user posted image
TSKampung2005
post Mar 16 2014, 02:00 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
Underground updates (February or March 2014) from MyMRT Underground

https://www.facebook.com/mrtunderground?fref=ts

Semantan portal aerial view
user posted image

Overview of Precast Segments Ring Storage Yard
user posted image

Semantan 1 Tunnel Drive
user posted image

Semantan 1 Tunnel Drive (Ring Beam Erection at Cross Passage, CP1)
user posted image

INTERVENTION SHAFT 1 @ JALAN DAMANSARA - Aerial View
user posted image

Please note that the patching works of the hole using mortar had completed. A steel sheet is put over the area and the road has been re-opened to traffic at 6.05pm.
user posted image

KL Sentral MRT station site aerial view
user posted image
user posted image

RC Structure Works at Vent Shaft B (Base Slab – Curing Works)
user posted image

RC Structure Works (Roof Slab Wall – Rebar Works)
user posted image
TSKampung2005
post Mar 16 2014, 02:05 AM

Proudly Kampungite, will always be one.
Group Icon
VIP
3,028 posts

Joined: Feb 2005
From: 梅田,大阪 //Sabah
Underground updates (February or March 2014) from MyMRT Underground

https://www.facebook.com/mrtunderground?fref=ts

Pasar Seni station site aerial view
user posted image
user posted image

RC Structure Works at Klang Bus Station (Concourse Slab - Concreting Works)
user posted image

RC Structure Works at Klang Bus Station (Concourse Slab Wall - Rebar Works)
user posted image

Merdeka station site aerial view
user posted image

RC Structure Works (Construction of Sump Pit at Base Level)
user posted image

RC Base Slab Structure Preparation Works (Installation of Earthing System & Subsoil Drain)
user posted image

RC Base Slab Structure Preparation Works (Installation of Earthing System & Subsoil Drain)
user posted image

Pudu launch shaft aerial view
user posted image

Excavation Works (Up to Lower Plant Room Level)
user posted image


45 Pages « < 32 33 34 35 36 > » 
Bump Topic Add ReplyOptions New Topic
 

Change to:
| Lo-Fi Version
0.0213sec    0.35    6 queries    GZIP Disabled
Time is now: 27th November 2022 - 11:54 PM