 Renovation Secret & Tips Revealed, Secret&Tips contractor wont tell you

views
     
aquaria87
post Nov 14 2013, 09:58 AM

Getting Started
**
Junior Member
129 posts

Joined: Mar 2009


Hi Tomjason.

My condolences to you n your family.

It is very informative knowledge you had shared with us.

I am also in the middle renovating my house.

I have a few question.

1) Do you think it is adequate to use Y16 bar to extend the car porch as in the picture below. My contractor use Y16 and we have remove the center column so we can get wide span free column to my car porch.
user posted image

2) What shoould i do for the discharge sewage pipe which is close to the manhole wall (the very left pipe). I did ask the contractor to hack more to the wall so that the flow of the sewage are not block by the wall. What say u.



user posted image

3) In addition, when the contractor lay the sewage pipe, at the bend/corner they not construct a manhole due to reason that my perimeter drain will cross at the junction. they use the 45degree bend. as shown below (the bend has been covered with earth).

user posted image

4) What do you think about this plaster ceiling support. is it adequate i mean in term of spacing?
user posted image

Uploaded with ImageShack.us


stbeh
post Nov 14 2013, 10:01 AM

New Member
*
Newbie
2 posts

Joined: Jan 2003
please pm me the formula, thanks.
corticalsteelx
post Nov 14 2013, 10:40 AM

New Member
*
Newbie
1 posts

Joined: Nov 2013
Hi bro. Can you PM me the formula too. Cheers
TStomjason
post Nov 14 2013, 10:31 PM

Enthusiast
*****
Senior Member
866 posts

Joined: Oct 2011
QUOTE(aquaria87 @ Nov 14 2013, 09:58 AM)
Hi Tomjason.

My condolences to you n your family.

It is very informative knowledge you had shared with us.

I am also in the middle renovating my house.

I have a few question.

1) Do you think it is adequate to use Y16 bar to extend the car porch as in the picture below. My contractor use Y16 and we have remove the center column so we can get wide span free column to my car porch.
user posted image

2) What shoould i do for the discharge sewage pipe which is close to the manhole wall (the very left pipe). I did ask the contractor to hack more to the wall so that the flow of the sewage are not block by the wall. What say u.
user posted image

3) In addition, when the contractor lay the sewage pipe, at the bend/corner they not construct a manhole due to reason that my perimeter drain will cross at the junction. they use the 45degree bend. as shown below (the bend has been covered with earth).

user posted image

4) What do you think about this plaster ceiling support. is it adequate i mean in term of spacing?
user posted image

Uploaded with ImageShack.us
*
below is my answer:


1. Question 1)

For this, Y16 is sufficient if you do not want to have centre column, ip possible use Y16 (BS). Secondly , since you don’t have centre pillar,it is very important the size of the beam to carry the weight. Min is more than 1 feet..1 ½ feet for centre column is sufficient. The bigger the better. From the picture, I can say pass. Pls ensure the new beam is connect to the existing beam properly.

My suggestion is to have the angle beam is the best as my picture below red color (hope you understand)


Attached Image



2. Second Question

For normal sewage man hole is 18x24 inches, this because normal ready man steel cover is 18x24…that why ur contractor do not want to make the main hole bigger……your contractor has made mistake cause the 2 pairs were too much a part. From the picture, I don’t give pass to the second pair of the pipe..sure sangkut…
Since it is already nearly completed, what you can do is, to place angle / corner clay drain (clay drain have corner and straight). Below is my suggestion:


Attached Image



3. 3rd question:


Your contractor has made mistake, as my previous post, corner advisable to have main hole. It become worst if the pipe share with sink waste…if clog at the corner/bend, how are you going to clear the clog. Normally clog happened at the bend or corner of the pipe. If you can answer my question then, I will give you pass mark.


4. Question:

As in my previous post , advisable the gap is about 18 inches, the less is the better, cause plaster ceiling is heavy.

This post has been edited by tomjason: Nov 14 2013, 10:51 PM
aquaria87
post Nov 14 2013, 10:54 PM

Getting Started
**
Junior Member
129 posts

Joined: Mar 2009


1. Question 1)

For this, Y16 is sufficient if you do not want to have centre column, ip possible use Y16 (BS). Secondly , since you don’t have centre pillar,it is very important the size of the beam to carry the weight. Min is more than 1 feet..1 ½ feet for centre column is sufficient. The bigger the better. From the picture, I can say pass. Pls ensure the new beam is connect to the existing beam properly.

My suggestion is to have the angle beam is the best as my picture below red color (hope you understand)

Yes sir, the new rebar are extended 2 feet inside the original beam. Further the original beam are also deepen (add additional 2 bottom bar

Attached Image

2. Second Question

For normal sewage man hole is 18x24 inches, this because normal ready man steel cover is 18x24…that why ur contractor do not want to make the main hole bigger……your contractor has made mistake cause the 2 pairs were too much a part. From the picture, I don’t give pass to the second pair of the pipe..sure sangkut…
Since it is already nearly completed, what you can do is, to place angle / corner clay drain (clay drain have corner and straight). Below is my suggestion:

Attached Image

Meaning ask the contractor to install 45 degree bend at the tip of the pipe?


3. 3rd question:


Your contractor has made mistake, as my previous post, corner advisable to have main hole. It become worst if the pipe share with sink waste…if clog at the corner/bend, how are you going to clear the clog. Normally clog happened at the bend or corner of the pipe. If you can answer my question then, I will give you pass mark.

Agree with u. luckily there is no sink wast pass thru this waste pipe. Only afraid if in future the sh*t inside stuck at the bend, then it will be my major headache. any idea how to do control damage?


4. Question:

As in my previous post , advisable the gap is about 18 inches, the less is the better, cause plaster ceiling is heavy.

Plaster ceiling completed. too bad i nt find ur post earlier. huhu..


Thank you for ur guidance.

This post has been edited by aquaria87: Nov 14 2013, 10:55 PM
aquaria87
post Nov 14 2013, 10:57 PM

Getting Started
**
Junior Member
129 posts

Joined: Mar 2009


BTW boss, can u PM me the formula smile.gif tq
TStomjason
post Nov 14 2013, 11:51 PM

Enthusiast
*****
Senior Member
866 posts

Joined: Oct 2011
QUOTE(aquaria87 @ Nov 14 2013, 10:54 PM)
1. Question 1)

For this, Y16 is sufficient if you do not want to have centre column, ip possible use Y16 (BS). Secondly , since you don’t have centre pillar,it is very important the size of the beam to carry the weight. Min is more than 1 feet..1 ½ feet for centre column is sufficient. The bigger the better. From the picture, I can say pass. Pls ensure the new beam is connect to the existing beam properly.

My suggestion is to have the angle beam is the best as my picture below red color (hope you understand)

Yes sir, the new rebar are extended 2 feet inside the original beam. Further the original beam are also deepen (add additional 2 bottom bar

Attached Image

2. Second Question

For normal sewage man hole is 18x24 inches, this because normal ready man steel cover is 18x24…that why ur contractor do not want to make the main hole bigger……your contractor has made mistake cause the 2 pairs were too much a part. From the picture, I don’t give pass to the second pair of the pipe..sure sangkut…
Since it is already nearly completed, what you can do is, to place angle / corner clay drain (clay drain have corner and straight). Below is my suggestion:

Attached Image

Meaning ask the contractor to install 45 degree bend at the tip of the pipe?
3. 3rd question:
Your contractor has made mistake, as my previous post, corner advisable to have main hole. It become worst if the pipe share with sink waste…if clog at the corner/bend, how are you going to clear the clog. Normally clog happened at the bend or corner of the pipe. If you can answer my question then, I will give you pass mark.

Agree with u. luckily there is no sink wast pass thru this waste pipe. Only afraid if in future the sh*t inside stuck at the bend, then it will be my major headache. any idea how to do control damage?
4. Question:

As in my previous post , advisable the gap is about 18 inches, the less is the better, cause plaster ceiling is heavy.

Plaster ceiling completed. too bad i nt find ur post earlier. huhu..
Thank you for ur guidance.
*
below is the clay drainage (for main hole)...hope you understand...


Attached Image


from your picture..there is an ample space to built mainhole..i suppose your contractor do not want to do it since already completed...hopefully no clog since no sink waste....




aquaria87
post Nov 15 2013, 10:32 AM

Getting Started
**
Junior Member
129 posts

Joined: Mar 2009


Bro Tomjason, this is the end result for the manhole

user posted image


Reason why the contractor not built the manhole due to this perimeter drain (which i think they can built it up furhter. Hope that the new manhole near the bend could help me if the bend get clog in the future..

(THIS NEW MANHOLE WILL BE CONNECTED TO THE EXISTING MANHOLE)

user posted image


TStomjason
post Nov 15 2013, 03:01 PM

Enthusiast
*****
Senior Member
866 posts

Joined: Oct 2011
QUOTE(aquaria87 @ Nov 15 2013, 10:32 AM)
Bro Tomjason, this is the end result for the manhole

user posted image
Reason why the contractor not built the manhole due to this perimeter drain (which i think they can built it up furhter. Hope that the new manhole near the bend could help me if the bend get clog in the future..

(THIS NEW MANHOLE WILL BE CONNECTED TO THE EXISTING MANHOLE)

user posted image
*
hi bro,

from your picture..for me your main hole still no pass...pls follow my suggestion to pass....

by the way i saw your remark in :

https://forum.lowyat.net/topic/3030656

who are u really?..r u contractor?.....
icepixes
post Nov 15 2013, 06:11 PM

New Member
*
Junior Member
17 posts

Joined: Jul 2008


Tomjason, If I may, would like to have that secret formula too. I will start my reno next month. Thank you in advance
aquaria87
post Nov 15 2013, 08:42 PM

Getting Started
**
Junior Member
129 posts

Joined: Mar 2009


QUOTE(tomjason @ Nov 15 2013, 03:01 PM)
hi bro,

from your picture..for me your main hole still no pass...pls follow my suggestion to pass....

by the way i saw your remark in :

https://forum.lowyat.net/topic/3030656

who are u really?..r u contractor?.....
*
Nope.. i am internal auditor (by profession)... my ex uitm colleague carry out my house renovation and based on my 5 years exp as Quantity surveyor (Practially know abt dollar and cents and contract rather than building technology - which more on theory rather than practical). But never had on site exprnce for small reno/house works... working for firm handling high rise building and shopping complex.. huhu..

Now as currently doing my own renovation which i monitor everyday, i hv practically learn a lot on trick and tweak of small construction works which is far from the one taught in lecture hall and even practice in high rise/big project... feel very noobies...


BTW TQ for your knowledge.. i am stilll monitor the progress of the works.

This post has been edited by aquaria87: Nov 15 2013, 08:49 PM
vjeyamahla
post Nov 19 2013, 09:22 AM

Getting Started
**
Junior Member
56 posts

Joined: Apr 2013
Please pm me as well. I would be starting renovation soon. Thank you...
core9design
post Nov 19 2013, 05:45 PM

Getting Started
**
Junior Member
69 posts

Joined: Jan 2003


hi tomjason, could you PM me the secret formula. thank you. your information have been helpful
7thsoundstation
post Nov 19 2013, 09:44 PM

New Member
*
Junior Member
12 posts

Joined: Dec 2008


Hi bro...can pm me the formula....love diy too and avoid main contractor. BTW, nice reno you did.

TQ
param124
post Nov 24 2013, 06:45 PM

Getting Started
**
Junior Member
116 posts

Joined: May 2007


Hi sir,

About to begin my reno journey

Please pm me the secret formula as well

Thanks for sharing
imgoh
post Nov 27 2013, 11:02 AM

New Member
*
Junior Member
13 posts

Joined: Oct 2008


Anyone can PM me the formula to work out the budget? Thanks. Really headache...
vjeyamahla
post Nov 27 2013, 12:37 PM

Getting Started
**
Junior Member
56 posts

Joined: Apr 2013
Dear Tomjason,

I found your information very useful.I would be extremely happy if you could calculate how much it would cost to renovate my wet kitchen.It is double storey endlot. I intend to hack the back wall and extend the wet kitchen till the end. The yard need to level as it is 8 inches below the wet kitchen. I also need to move the back door to the back of the new wet kitchen and install another door at the side. The side wall need to be tiled until the ceiling. A contractor has quoted RM 30K to do these renovation.. What is your opinion?
Thanking you for your time.

This post has been edited by vjeyamahla: Nov 27 2013, 12:40 PM


Attached File(s)
Attached File  Groundfloor_layout.doc ( 681k ) Number of downloads: 82
pk330
post Nov 28 2013, 08:11 PM

New Member
*
Junior Member
25 posts

Joined: Sep 2013
can anyone share the TJ formula with me? 10q
limlim78
post Dec 2 2013, 10:21 AM

Getting Started
**
Junior Member
98 posts

Joined: Jan 2005


Just want to ask piling beside terraced double storey. I want to extend my double storey terraced house (corner lot) Engineer proposed to piling ask foundation for column, i just want to know if we piling beside my house, will it affected other house? Anyone piling beside terrace house before? Thank you.
wckw2002
post Dec 3 2013, 10:22 AM

New Member
*
Newbie
1 posts

Joined: Aug 2011
can pm me your formula please? thanks